Mokena School District Terminates Contract with Evans and Sons Blacktop Over Project Deficiencies

Spread the love

MOKENA, Ill. – The Mokena School District 159 Board of Education voted unanimously Wednesday to terminate its contract with Evans and Sons Blacktop for the playground and parking lot improvements project at Mokena Elementary and Intermediate Schools, citing breach of contract and significant performance issues.

The move comes as the new school year approaches, with district officials expressing a lack of confidence in the contractor’s ability to complete the project in a timely and acceptable manner.

In a letter dated July 16, 2025, addressed to Daniel Evans of Evans and Sons Blacktop, Chief School Business Official Dr. Teri Shaw stated the contractor was in “breach of its obligations to perform the work in an acceptable and timely manner.” The letter directed the West Chicago-based company to cease all work on the project immediately.

“You have received several communications from our architects regarding performance deficiencies and with the new school year rapidly approaching we have no confidence that you will be able to complete the Project on time and in accordance with the contract documents,” Shaw wrote.

According to an action memo presented to the board, the decision followed a July 10 meeting between district officials, including Buildings and Grounds Director Dave Rana, and representatives from the project architect, Dan Kritta, and the project’s bonding company, emc Insurance, represented by Frank Alampi.

The district has already filed a claim with the bonding company and is moving to hire replacement contractors to finish the job. As part of its leverage, the district has withheld $140,000 from its original contract with Evans and Son due to the incomplete and unsatisfactory work.

“If we incur any additional costs beyond the $140,000 the bonding company will pay the cost,” Shaw noted in the memo.

The termination, effective July 17, was recommended based on multiple breaches of the contract, specifically sections 14.2.1.2 through 14.2.1.5 and 14.2.1.8 of the A201-2017 contract document. The letter serves as the company’s seven-day notice of termination.

The district also plans to seek an emergency resolution to hire a new site contractor, which would bypass the standard 10-day bid notification requirement. This is being done to expedite the hiring process and ensure the project is finished with minimal further delay, particularly with student safety and school operations in mind. The district expressly reserved all rights to pursue reimbursement for any extra costs incurred due to the breach.

The playground and parking lot improvements are part of a series of summer projects intended to upgrade district facilities before students return in August.

Latest News Stories

Screenshot 2025-10-25 at 10.48.48 AM

New Lenox Solar Farm Proposal Advances with Conditions, Following Village and Forest Preserve Input

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission recommended approval for a 62.7-acre commercial solar energy facility in...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for October 16, 2025

Will County Board Regular Meeting | October 16, 2025 The Will County Board took major action on property taxes at its meeting on Thursday, October 16, 2025, narrowly voting to...
30 MPH Speed Limit

Will County Board Approves New 30 MPH Speed Limit for Frankfort Township Road

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board approved a new 30 MPH speed limit for a section of 78th Avenue in Frankfort Township,...
Screenshot 2025-10-25 at 12.42.59 PM

Will County Committee Grapples with $8.9 Million Budget Gap After Contentious 0% Tax Levy Vote

Will County Board Finance Committee Meeting | October 21, 2025 Article Summary: The Will County Board Finance Committee held a contentious debate over how to close an $8.9 million budget shortfall...
Screenshot 2025-10-25 at 10.49.15 AM

Frankfort Township Board Objects, but County Commission Recommends Bar with Video Gaming

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: Despite a formal objection from the Frankfort Township Board, the Will County Planning and Zoning Commission recommended...
Screenshot 2025-10-25 at 10.49.23 AM

Senior Shared Housing Facility Recommended for Approval in Crete Township

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission has recommended approval for a special use permit that would...
Screenshot 2025-10-25 at 10.49.32 AM

Crete Township ‘Tiny Home’ Owner Appeals Permit Denial

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: A Crete Township property owner has appealed to the Will County Planning and Zoning Commission after being...
Will County Finance Logo

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board Article Summary:The Will County Board’s Finance Committee on Tuesday, November 12, 2025, narrowly approved a series of...
mokena school district 159.1

Board Approves $190,000 Transfer from Working Cash Fund Amid Dissent

Mokena School District 159 Meeting | November 19, 2025 Article Summary: The Mokena School District 159 Board of Education approved a resolution to abate $190,000 from its working cash fund...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
mokena fire protection district logo graphic.5

Mokena Fire District Secures $160,000 in Grants to Replace Hoses and Nozzles

Mokena Fire Protection District Meeting | October 14, 2025 Article Summary: The Mokena Fire Protection District has successfully secured approximately $160,000 in grant funding, nearly covering the entire cost to...