Mokena School District Terminates Contract with Evans and Sons Blacktop Over Project Deficiencies
MOKENA, Ill. – The Mokena School District 159 Board of Education voted unanimously Wednesday to terminate its contract with Evans and Sons Blacktop for the playground and parking lot improvements project at Mokena Elementary and Intermediate Schools, citing breach of contract and significant performance issues.
The move comes as the new school year approaches, with district officials expressing a lack of confidence in the contractor’s ability to complete the project in a timely and acceptable manner.
In a letter dated July 16, 2025, addressed to Daniel Evans of Evans and Sons Blacktop, Chief School Business Official Dr. Teri Shaw stated the contractor was in “breach of its obligations to perform the work in an acceptable and timely manner.” The letter directed the West Chicago-based company to cease all work on the project immediately.
“You have received several communications from our architects regarding performance deficiencies and with the new school year rapidly approaching we have no confidence that you will be able to complete the Project on time and in accordance with the contract documents,” Shaw wrote.
According to an action memo presented to the board, the decision followed a July 10 meeting between district officials, including Buildings and Grounds Director Dave Rana, and representatives from the project architect, Dan Kritta, and the project’s bonding company, emc Insurance, represented by Frank Alampi.
The district has already filed a claim with the bonding company and is moving to hire replacement contractors to finish the job. As part of its leverage, the district has withheld $140,000 from its original contract with Evans and Son due to the incomplete and unsatisfactory work.
“If we incur any additional costs beyond the $140,000 the bonding company will pay the cost,” Shaw noted in the memo.
The termination, effective July 17, was recommended based on multiple breaches of the contract, specifically sections 14.2.1.2 through 14.2.1.5 and 14.2.1.8 of the A201-2017 contract document. The letter serves as the company’s seven-day notice of termination.
The district also plans to seek an emergency resolution to hire a new site contractor, which would bypass the standard 10-day bid notification requirement. This is being done to expedite the hiring process and ensure the project is finished with minimal further delay, particularly with student safety and school operations in mind. The district expressly reserved all rights to pursue reimbursement for any extra costs incurred due to the breach.
The playground and parking lot improvements are part of a series of summer projects intended to upgrade district facilities before students return in August.
Community Events
Latest News Stories
Meeting Summary and Briefs: Will County Board Executive Committee for November 13, 2025
SCOTUS issues stay in Texas redistricting case
Marjorie Taylor Greene leaving Congress in January
WATCH: Trump, Mamdani meeting cordial with leaders finding common ground
Study: K-12 public spending nears $1 trillion in U.S.
WATCH: Power grid regulator says PNW in ‘crosshairs’ for potential winter blackouts
States push back on exclusion of noncitizens from SNAP
Pritzker suggests he’s open to tweaking SAFE-T Act after train passenger fire
Arizona attorney general to appeal ‘fake electors’ ruling
Illinois quick hits: Small business grants announced; new Naperville DMV
Clintons ordered to testify on connections to Jeffrey Epstein in December
CBO says foreign companies could pick up some tariff costs