Mokena School District Terminates Contract with Evans and Sons Blacktop Over Project Deficiencies

Spread the love

MOKENA, Ill. – The Mokena School District 159 Board of Education voted unanimously Wednesday to terminate its contract with Evans and Sons Blacktop for the playground and parking lot improvements project at Mokena Elementary and Intermediate Schools, citing breach of contract and significant performance issues.

The move comes as the new school year approaches, with district officials expressing a lack of confidence in the contractor’s ability to complete the project in a timely and acceptable manner.

In a letter dated July 16, 2025, addressed to Daniel Evans of Evans and Sons Blacktop, Chief School Business Official Dr. Teri Shaw stated the contractor was in “breach of its obligations to perform the work in an acceptable and timely manner.” The letter directed the West Chicago-based company to cease all work on the project immediately.

“You have received several communications from our architects regarding performance deficiencies and with the new school year rapidly approaching we have no confidence that you will be able to complete the Project on time and in accordance with the contract documents,” Shaw wrote.

According to an action memo presented to the board, the decision followed a July 10 meeting between district officials, including Buildings and Grounds Director Dave Rana, and representatives from the project architect, Dan Kritta, and the project’s bonding company, emc Insurance, represented by Frank Alampi.

The district has already filed a claim with the bonding company and is moving to hire replacement contractors to finish the job. As part of its leverage, the district has withheld $140,000 from its original contract with Evans and Son due to the incomplete and unsatisfactory work.

“If we incur any additional costs beyond the $140,000 the bonding company will pay the cost,” Shaw noted in the memo.

The termination, effective July 17, was recommended based on multiple breaches of the contract, specifically sections 14.2.1.2 through 14.2.1.5 and 14.2.1.8 of the A201-2017 contract document. The letter serves as the company’s seven-day notice of termination.

The district also plans to seek an emergency resolution to hire a new site contractor, which would bypass the standard 10-day bid notification requirement. This is being done to expedite the hiring process and ensure the project is finished with minimal further delay, particularly with student safety and school operations in mind. The district expressly reserved all rights to pursue reimbursement for any extra costs incurred due to the breach.

The playground and parking lot improvements are part of a series of summer projects intended to upgrade district facilities before students return in August.

Today Jun 13
Showers And Thunderstorms then Mostly Cloudy
71° 51°

Showers And Thunderstorms then Mostly Cloudy

💨 10 to 20 mph 💧 75%

Latest News Stories

Will County P&Z Logo Planning Zoning.2

Will County P&Z Grants Variances for Unpermitted Structures in Crete and Manhattan

Will County P&Z Commission Meeting | Jan. 20, 2026 Article Summary: The Planning and Zoning Commission approved variances for property owners in Crete and Manhattan who built agricultural structures without...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Landfill Committee for Jan. 13, 2026

Will County Landfill Committee Meeting | Jan. 13, 2026 The Will County Board Landfill Committee met on Tuesday, January 13, 2026, to address operational improvements at the Prairie View Landfill...
Scam Alert Grahpic

Monee Police warn residents of phone scammers impersonating officers

MONEE, Ill. – The Monee Police Department issued a community alert this week regarding a resurgence of telephone scams in which fraudsters are impersonating police officers to solicit money from residents....
Will County P&Z Logo Planning Zoning

Will County P&Z Approves Mokena Scrap Drop-Off Despite Municipal Objections

Will County P&Z Commission Meeting | Jan. 20, 2026 Article Summary: The Will County Planning and Zoning Commission granted a special use permit for an outdoor recyclable material drop-off facility...
solar panels photovoltaics in solar farm

Will County Braces for 6,000-Acre Solar Project; Prepare for ‘Massive’ Solar Hearings

Will County P&Z Commission Meeting | Jan. 20, 2026 Will County Braces for 6,000-Acre Solar Project; Commissioners Weigh Conflicts and Crowds Article Summary:The Will County Planning and Zoning Commission is...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board for January 15, 2026

Will County Board Meeting | January 15, 2026 Meeting SummaryThe Will County Board met on January 15, 2026, to tackle a heavy agenda focused on infrastructure investment, legislative policy, and...
Police Crime

Pursuit following railroad theft ends in New Lenox; one suspect at large

NEW LENOX, Ill. – A reported cargo theft in Wilmington Township sparked a multi-jurisdictional pursuit Saturday morning that ended with a crash and a manhunt in a New Lenox neighborhood. The...
Will County Board Graphic.04

Waste Management Commits to Expanded Litter Patrols Around Landfill

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Following complaints from county officials, Waste Management has agreed to significantly expand its litter collection efforts along roadways surrounding...
Meeting Briefs

Meeting Summary and Briefs: Mokena School District 159 for January 21, 2026

Mokena School District 159 Meeting | January 21, 2026 Overall Meeting SummaryThe Mokena School District 159 Board of Education met on Wednesday, January 21, 2026, addressing a mix of student...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for Jan. 13, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, January 13, 2026, to continue its comprehensive update...
Will County Board Graphic.01

County Approves $22 Million in Road Projects for Lorenzo Road and Mills Road

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved major infrastructure contracts, including an $18.8 million bridge replacement on Lorenzo Road and a $3.2...
Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable...
mokena school district 159.5

Fifth Graders Honored for DARE Essays on Decision Making

Mokena School District 159 Meeting | January 21, 2026 Article Summary: Two fifth-grade students were spotlighted at the Mokena School District 159 Board meeting for their winning essays on the...
Will County Board Graphic.03

Ad-Hoc Committee Retains Noise Ordinance Despite Enforcement Frustrations

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Ad-Hoc Ordinance Review Committee voted to retain the county’s public nuisance noise ordinance despite members describing...
Will County Board Graphic.03

Will County Commits $15M to Transfer Sanitary District Operations to City of Joliet

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board has authorized an intergovernmental agreement to dissolve the Southeast Joliet Sanitary District and transfer its water...