Will County Receives Detailed Update on Landfill Expansion Investigation

Spread the love

Article Summary:

The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Leave a Comment





Latest News Stories

Meeting-Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting-Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $550,000 Fund Transfer for Major Park Projects

The Mokena Community Park District Board of Commissioners has approved a $550,000 fund transfer to complete several key capital projects, including the construction of a new bathroom facility at Hecht...
LWSRA

Mokena Park District Joins Regional Partners in Renewed Funding Commitment for LWSRA

The Mokena Community Park District is renewing its financial commitment to the Lincolnway Special Recreation Association (LWSRA), joining eight other local park districts in an intergovernmental agreement that ensures continued...
mokena park Yunker Barn

Mokena Park District Seeks Nearly $1 Million State Grant for Yunker Barn Renovation

The Mokena Park District is seeking nearly $1 million in state funding to help transform the historic Yunker Park Barn into a year-round facility. Executive Director Greg Vitale announced at...
Meeting-Briefs

Meeting Briefs: Mokena Park District Board of Commissioners for June 27, 2023

The Mokena Park District Board of Commissioners met on June 27 to approve funding for capital projects, renew a regional partnership agreement, and review staff reports on recent and upcoming...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
mokena library logo graphic.4

Library Board Approves Annual Budget, Begins Review of Financial Advisor Proposals

The Library Board of Trustees unanimously approved its working budget for the new fiscal year at its June 24 meeting and formally began the process of selecting a financial advisor...
Screenshot-2025-07-06-at-9.50.39-AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...