Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Leave a Comment





Latest News Stories

mokena fire protection district logo graphic.5

Mokena Fire District Approves Annual Budget After Public Hearing

The Mokena Fire Protection District Board of Trustees unanimously adopted its budget and appropriation ordinance for the 2025-2026 fiscal year, finalizing the district’s spending plan after a formal public hearing...
mokena fire protection district logo graphic.4

Mokena Fire District Faces 14% Insurance Hike, Renews Policies

The Mokena Fire Protection District is grappling with significant increases in insurance costs, with its property and liability policy renewal rate jumping by approximately 14%. The Board of Trustees unanimously...
mokena fire protection district logo graphic.1

Fire District Inks New Banking Agreement with Old Plank Trail

The Mokena Fire Protection District Board of Trustees has approved a new two-year banking agreement with Old Plank Trail, a move aimed at securing favorable rates amid a volatile market....
Meeting-Briefs

Meeting Briefs: Mokena Fire Protection District for June 10, 2025

The Mokena Fire Protection District Board of Trustees formally adopted its budget and appropriation ordinance for the 2025-2026 fiscal year following a public hearing. With no members of the public...
Will-County-Executive-Committee-Meeting-June-12-2025

Mental Health Board Awards $5 Million in Grants to Will County Organizations

The Will County Community Mental Health Board has distributed over $5 million in grants to 39 local organizations, marking the completion of its inaugural funding cycle since voters approved the...
frankfort-square-park-district.2

Frankfort Square Park District Adopts Budget and Appropriation Ordinance, Updates Financial Policy

The Frankfort Square Park District Board of Commissioners formally adopted its Budget and Appropriation Ordinance for the 2025-2026 fiscal year on Thursday, finalizing the district's legal spending authority for the...
Will-County-Executive-Committee-Meeting-June-12-2025

County Board Approves Major Code Updates, Discusses Employee Benefits

The Will County Board Executive Committee approved several ordinance updates Wednesday while engaging in detailed discussions about employee compensation and benefits. The committee passed ordinances updating three chapters of the...
frankfort-square-park-district.1

Major Park District Projects Advance as Hunter Prairie Park Gets Green Light

Work on the Frankfort Square Park District's three major capital projects is hitting key milestones, with the long-awaited redevelopment of Hunter Prairie Park now officially underway. Executive Director Audrey Marcquenski...
Meeting-Briefs

Executive Committee June 12 Meeting Briefs

Property Purchase Approved: The county authorized purchase of two parcels along Governor's Highway in Monee for $545,000 to establish a roadway maintenance facility for the eastern end of the county....
frankfort-square-park-district.2

Developer to Donate Land, Playground for New Park in Tinley Park

A new park is coming to a Tinley Park development thanks to a land and equipment donation from a local home builder. Frank Bradley, owner of Crana Homes, is donating...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for June 12, 2025

The Frankfort Square Park District Board of Commissioners formally adopted its annual Budget and Appropriation Ordinance on June 12, a key legal step that sets the district’s spending authority for...
frankfort-school-district-161.2-e1754272831494

Summit Hill Board Approves School Resource Officer for Two Schools in Contentious Vote

The Summit Hill School District 161 Board of Education voted to hire a School Resource Officer (SRO) to serve two of its schools, approving an annual expenditure of up to...
frankfort-school-district-161.1

Summit Hill School Board Reverses Controversial Principal Non-Renewal Decision

In a significant reversal, the Summit Hill School District 161 Board of Education voted to repeal previous resolutions that aimed to not renew the contract of an unnamed principal, effectively...
frankfort-school-district-161.2-e1754272831494

Meeting Briefs: Summit Hill School District 161 for June 11, 2025

The Summit Hill School District 161 Board of Education made several major decisions at its June 11 meeting, including the hiring of a School Resource Officer for two schools after...
Will-County-Ad-Hoc-Ordinance-Review-Committee-Meeting-June-10-2025

Will County to Draft New Harassment Policy Amid Debate Over Board Authority

The Will County Ad-Hoc Ordinance Review Committee will draft a new, county-wide general harassment policy after a lengthy debate on Tuesday revealed the complexities of the county’s legal obligations and...