Mokena School District 159 Board of Education Meeting | October 15, 2025

Article Summary: The Mokena School District 159 Board of Education approved a cost increase for a new storage shed at Mokena Junior High School, raising the project’s total cost to a maximum of $176,000. The decision, which passed in a contentious 5-2 vote, sparked a debate over fiscal responsibility in light of the district’s budget deficit and the intent of referendum funds.

MJHS Storage Shed Project Key Points:

  • The board approved a revised project cost not to exceed $176,000, an increase from the previously approved $162,500.

  • The cost increase is due to a newly required perimeter frost footing for the shed’s foundation, a change from the original design.

  • The project is funded through the “Warm, Safe, and Dry” referendum funds, designated for facilities and maintenance.

  • Board members debated whether the expenditure was responsible given the district’s budget deficit and if the funds could be better used elsewhere.

MOKENA, IL — The Mokena School District 159 Board of Education on Wednesday, October 15, 2025, approved an increased budget for the Mokena Junior High School (MJHS) storage shed project, bringing the total cost to a maximum of $176,000. The vote followed a lengthy and pointed debate among board members about the project’s necessity, timing, and funding source amid a projected $1.3 million budget deficit.

The project, initially approved in September 2024 for $162,500, requires additional funding due to a change in construction requirements. According to a memo from Dr. Teri Shaw, the district’s Chief School Business Official, the shed’s provider now requires a perimeter frost footing instead of the previously planned thickened slab edge. This change necessitates deeper excavation and more concrete, increasing the cost for contractor Bear Construction by $14,600 to a total of $159,600. The total project cost is not to exceed $176,000.

Board member Kelli MacMillan voiced strong opposition to the project, calling it an “irresponsible spend.” She argued that the district is operating without the shed now and could delay the project indefinitely, particularly given the budget deficit.

“We are in a deficit, meaning we are spending $1.3 million… more than the revenue we have coming in,” MacMillan stated. “I don’t feel good about prioritizing a shed over students and staff. I don’t feel good about it and that’s why I won’t do it.”

MacMillan also questioned the use of referendum funds, which she said were intended to keep students “warm, safe and dry, not construction equipment.” She pointed out that the district is budgeting to transfer $190,000 from its working cash fund reserves to its Operations and Maintenance (O&M) fund. “Essentially, we’re saying we need money from our reserves to pay for a $176,000 shed that does not impact our classrooms. And I have an issue with that,” she said.

Board President Jim Andresen countered, stating that the funds for the shed come from the “Warm, Safe, and Dry” referendum, which are legally restricted for facilities, maintenance, and equipment protection. He stressed that this money could not be reallocated to classroom or salary expenses.

“This does not impact a classroom. The promise was made… to use that money for the facilities,” Andresen said. “This is not making the students do without. This is making sure we are protecting the capital investments we made with our equipment… We have to take care of our equipment and this is no different.”

Andresen added that a “forever lock” was placed on the referendum funds, requiring a unanimous board vote to ever use them for purposes outside of facilities, such as salaries or school supplies. “Please do not think for a second that that trust is going to be violated,” he said.

Board member Lisa Zielinski also expressed reservations but ultimately supported the project. “I struggle with the warm, safe, and dry and if it’s aesthetics,” she commented, before thanking the administration for bringing the cost increase to the board for a vote, even though the amount was within a 10% threshold that did not technically require re-approval.

The motion to approve the increased cost passed 5-2, with members MacMillan and Julie Oost voting against it.

Leave a Comment





Latest News Stories

Will County Logo Graphic

Crete “Group Care” Home Approved for Senior Living

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a senior group care home in Crete Township. The facility...
mokena fire protection district logo graphic.4

Mokena Fire District Approves Insurance Renewals With Below-Average Hikes

Mokena Fire Protection District Meeting | October 14, 2025 Article Summary: The Mokena Fire Protection District Board of Trustees unanimously approved the renewal of its health and dental insurance premiums,...
will county board graphic

New Bar Approved in Frankfort Despite Board Opposition

Will County Board Meeting | November 2025 Article Summary: The Will County Board narrowly approved a special use permit for a new bar in Frankfort Township, paving the way for...
joliet junior college logo

JJC Board Approves Grundy County Land Purchase Amid Heated Debate

Joliet Junior College Meeting | November 12, 2025 Article Summary:The Joliet Junior College Board of Trustees voted 6-2 to approve a real estate contract for a new campus in Grundy...
mokena school district 159.2

Mokena PTA Donates Over $8,000 for Student Enrichment Programs

Mokena School District 159 Meeting | November 19, 2025 Article Summary: The Mokena School District 159 Board of Education gratefully accepted a series of donations totaling $8,040 from the Mokena...
Screenshot 2025-11-21 at 10.20.03 AM

Support Staff Urge Lincoln-Way 210 Board for ‘Fair Contract’ During Public Comment

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Three members of Lincoln-Way District 210's support staff addressed the Board of Education, voicing frustrations over working without...
Will County Board Graphic.01

County Takes Over “Central Will” Dial-A-Ride in Major Consolidation

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved an intergovernmental agreement to absorb the "Central Will" Dial-A-Ride system into the county-wide "Access Will County"...
mokena fire protection district logo graphic.3

Mokena Fire District to End Response Protocol for I-80 East of Route 45

Mokena Fire Protection District Meeting | October 14, 2025 Article Summary: Effective January 1st, the Mokena Fire Protection District will no longer respond to incidents on Interstate 80 east of...
Will County Board Graphic.02

Board Denies Appeal for “Tiny Home” RV Living in Crete

Will County Board Meeting | November 2025 Article Summary: The Will County Board voted 19-2 to uphold a denial of a temporary use permit for a recreational vehicle (RV) being...
joliet junior college logo

JJC Board Censures Trustee Broderick Twice, Denies Request to Restore Good Standing

Joliet Junior College Meeting | November 12, 2025 Article Summary:In a series of contentious votes, the Joliet Junior College Board of Trustees censured Trustee Maureen Broderick for two separate alleged...
mental health awareness day bipolar disorder anxiety stress emot

Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board on Thursday, October 16, 2025, approved a $10 million tax levy for the Community Mental Health...
The Wild Flowe rFarm

Green Garden’s Wildflower Farm Granted Second Extension for Rural Events Permit

Will County Board Regular Meeting | October 16, 2025 Article Summary: Bengston Land Management, LLC, operators of The Wildflower Farm in Green Garden Township, received a second 180-day extension from the...
Screenshot 2025-10-17 at 3.14.53 PM

Will County Board Rejects Proposed Tax Hike, Approves 0% Levy Increase in Contentious Vote

Will County Board Regular Meeting | October 16, 2025 Article Summary: In a significant move providing relief to taxpayers, the Will County Board on Thursday, October 16, 2025, voted to approve...
Screenshot 2025-10-17 at 3.14.41 PM

Will County Awards $10.4 Million Contract for Bell Road Widening Project

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board has approved a $10.4 million contract with P.T. Ferro Construction Co. for a major roadway widening...
Screenshot 2025-10-17 at 3.15.09 PM

Regional Office of Education Highlights School Safety, New Learning Programs in Update

Will County Board Regular Meeting | October 16, 2025 Article Summary: Will County Regional Superintendent Dr. Lisa Caparelli-Ruff updated the County Board on key initiatives, including the installation of shooter-resistant window...