Mokena 159 Board Approves Increased Cost for Junior High Storage Shed Amid Budget Debate

Spread the love

Mokena School District 159 Board of Education Meeting | October 15, 2025

Article Summary: The Mokena School District 159 Board of Education approved a cost increase for a new storage shed at Mokena Junior High School, raising the project’s total cost to a maximum of $176,000. The decision, which passed in a contentious 5-2 vote, sparked a debate over fiscal responsibility in light of the district’s budget deficit and the intent of referendum funds.

MJHS Storage Shed Project Key Points:

  • The board approved a revised project cost not to exceed $176,000, an increase from the previously approved $162,500.

  • The cost increase is due to a newly required perimeter frost footing for the shed’s foundation, a change from the original design.

  • The project is funded through the “Warm, Safe, and Dry” referendum funds, designated for facilities and maintenance.

  • Board members debated whether the expenditure was responsible given the district’s budget deficit and if the funds could be better used elsewhere.

MOKENA, IL — The Mokena School District 159 Board of Education on Wednesday, October 15, 2025, approved an increased budget for the Mokena Junior High School (MJHS) storage shed project, bringing the total cost to a maximum of $176,000. The vote followed a lengthy and pointed debate among board members about the project’s necessity, timing, and funding source amid a projected $1.3 million budget deficit.

The project, initially approved in September 2024 for $162,500, requires additional funding due to a change in construction requirements. According to a memo from Dr. Teri Shaw, the district’s Chief School Business Official, the shed’s provider now requires a perimeter frost footing instead of the previously planned thickened slab edge. This change necessitates deeper excavation and more concrete, increasing the cost for contractor Bear Construction by $14,600 to a total of $159,600. The total project cost is not to exceed $176,000.

Board member Kelli MacMillan voiced strong opposition to the project, calling it an “irresponsible spend.” She argued that the district is operating without the shed now and could delay the project indefinitely, particularly given the budget deficit.

“We are in a deficit, meaning we are spending $1.3 million… more than the revenue we have coming in,” MacMillan stated. “I don’t feel good about prioritizing a shed over students and staff. I don’t feel good about it and that’s why I won’t do it.”

MacMillan also questioned the use of referendum funds, which she said were intended to keep students “warm, safe and dry, not construction equipment.” She pointed out that the district is budgeting to transfer $190,000 from its working cash fund reserves to its Operations and Maintenance (O&M) fund. “Essentially, we’re saying we need money from our reserves to pay for a $176,000 shed that does not impact our classrooms. And I have an issue with that,” she said.

Board President Jim Andresen countered, stating that the funds for the shed come from the “Warm, Safe, and Dry” referendum, which are legally restricted for facilities, maintenance, and equipment protection. He stressed that this money could not be reallocated to classroom or salary expenses.

“This does not impact a classroom. The promise was made… to use that money for the facilities,” Andresen said. “This is not making the students do without. This is making sure we are protecting the capital investments we made with our equipment… We have to take care of our equipment and this is no different.”

Andresen added that a “forever lock” was placed on the referendum funds, requiring a unanimous board vote to ever use them for purposes outside of facilities, such as salaries or school supplies. “Please do not think for a second that that trust is going to be violated,” he said.

Board member Lisa Zielinski also expressed reservations but ultimately supported the project. “I struggle with the warm, safe, and dry and if it’s aesthetics,” she commented, before thanking the administration for bringing the cost increase to the board for a vote, even though the amount was within a 10% threshold that did not technically require re-approval.

The motion to approve the increased cost passed 5-2, with members MacMillan and Julie Oost voting against it.

Leave a Comment





Latest News Stories

Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot-2025-07-06-at-9.45.35-AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Meeting-Briefs

L-W School Board June 26 Meeting Briefs

Special Education District Update: The fence installation around the playground at Lincoln Way Area Special Education District 843 has been completed except for one gate section that will allow equipment...
mokena library logo graphic.10

Library Explores New IT and Copier Services Amid Equipment Failures

The Library is evaluating an overhaul of its technology services, exploring new providers for both IT support and its public-facing print management system due to ongoing equipment failures. During Tuesday's...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...
Meeting-Briefs

Meeting Briefs: Library Board of Trustees for June 24, 2025

The Library Board of Trustees unanimously approved its annual working budget after amending the family programs line to $25,000. The board is also moving forward with long-term financial planning, having...
Meeting-Briefs

Meeting Summary: Joliet Junior College Board of Trustees for June 25, 2025

The Joliet Junior College Board of Trustees met on Wednesday, June 25, 2025. Key actions included the approval of the fiscal year 2026 budget after a contentious debate and hearing...
Mokena Logo Graphic.5

Mokena Enacts Local Grocery Tax to Avert $850,000 Revenue Loss

The Mokena Village Board has moved to preserve a crucial revenue stream, unanimously approving a new local grocery tax to replace state-collected funds that will disappear in 2026. The move...
Mokena Logo Graphic.6

Mokena Dissolves Two Committees to Streamline Development Process

In a bid to become more business-friendly, the Village of Mokena is dissolving two of its long-standing advisory committees to accelerate the process for new development. Mayor George J. Metanias...
Mokena Police Logo Graphic

Mokena Police to Get New Axon In-Car Cameras in $176K Deal

The Mokena Police Department is set to receive a significant technology upgrade after the Village Board approved a five-year, $176,526 contract with Axon Enterprise for a new in-car video system....
Callery Pear trees

Mokena Targets Invasive Callery Pear Trees for Removal

The Village of Mokena is taking proactive steps to improve its urban forest by removing dozens of invasive Callery Pear trees from public parkways, funded in part by a grant...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for June 23, 2025

The Mokena Village Board took several major actions at its June 23 meeting, including approving a new local grocery tax to head off a projected $850,000 revenue loss after the...
mokena school district 159.4

Mokena 159 Board Approves Amended Budget Amid Transparency, Deficit Concerns

The Mokena School District 159 Board of Education approved an amended budget for fiscal year 2025 in a contentious 6-1 vote Wednesday night, following sharp criticism from a board member...