Public Works & Transportation Committee Meeting | December 2, 2025

Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch of Wilmington-Peotone Road. Officials confirmed the project will add safety features like passing lanes but rejected a suggestion to simultaneously run utility lines to spur development.

Wilmington-Peotone Road Project Key Points:

  • Phase I Engineering: The board approved a $1,989,737 contract with Alfred Benesch and Company for design engineering.

  • Scope of Work: The project covers the stretch from US Route 45/52 to Center Road in Peotone Township.

  • Safety Features: Planned improvements include 10-foot wide shoulders and passing lanes to accommodate heavy truck traffic; the road will not be expanded to four lanes.

  • Utility Cost: A proposal to run natural gas main lines during construction to attract housing was deemed too expensive by the county engineer.

JOLIET, Ill. — A project to improve safety along a heavily trafficked corridor in Peotone Township moved forward Tuesday, December 2, 2025, as the Will County Board Public Works Committee authorized a nearly $2 million contract for design engineering.

The project targets Wilmington-Peotone Road between US Route 45/52 and Center Road. Director of Transportation Jeff Ronaldson noted that public feedback on the corridor has been polarized, with residents split between wanting “no trucks” and requesting a massive expansion to five lanes.

Ronaldson confirmed the county is taking a middle ground focused on safety.

“There’s going to be passing lanes through there to allow opportunities to get around some trucks. Wide 10-foot shoulders,” Ronaldson said. “It is not going to be a multi-lane, four-lane highway.”

Board Member Mark Revis (R-Plainfield) asked if the road construction offered an opportunity to work with utilities to run a natural gas main line down the corridor, suggesting it could help homeowners currently on propane and potentially attract residential development.

Ronaldson pushed back on the idea, citing the immense cost.

“The main line… would be very expensive,” Ronaldson said. “You need thousands of homes in order for that to make sense for a utility company.”

Ronaldson added that current residents in the agricultural area generally oppose dense subdivisions. “I think people in that area want to see more homes… they certainly don’t think they want to see a bunch of subdivisions,” he said.

The committee also approved a speed zone extension for Channahon-Minooka Road (CH 32) and a new speed zone for Golfview Drive in Green Garden Township.

Leave a Comment





Latest News Stories

will-county-board

Will County Health Department Faces Funding Uncertainty as Federal Grants Under Review

Multiple revenue sources threatened as department seeks legislative support for public health programs Will County Health Department officials are closely monitoring potential federal funding cuts that could impact multiple programs...

Will County Land Use Meeting Briefs

LAND USE ACTIONS Accessory Dwelling Unit Rules Modified: The committee recommended approval of text amendments allowing accessory dwelling units to exceed current building area limitations in certain circumstances. The changes...
Medicaid-logo

Federal Reconciliation Bill Targets Medicaid, SNAP Programs

Will County Legislators Briefed on Potential Local Impacts Federal legislation making sweeping cuts to Medicaid and food assistance programs could significantly impact Will County residents and services, county legislators learned...
will-county-board.2

Will County Approves Modified $756 Million Transportation Plan Despite Terminology Debate

Will County's Public Works and Transportation Committee approved a five-year, $756 million transportation improvement plan on June 3, but not before a heated debate over whether to call it a...
will-county-board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
will-county-board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will-county-board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...