Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Today Jun 8
Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms
85° 72°

Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 18%

Leave a Comment





Latest News Stories

Frankfort-Township-Logo-Graphic

Frankfort Township Board Grants Supervisor Authority to Negotiate Real Property Development

Article Summary: The Frankfort Township Board of Trustees has unanimously passed a resolution granting Supervisor Nick George the authority to negotiate the development of township-owned real property. This move empowers the...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
mokena library logo graphic.3

Mokena Library Board Approves Final Budget for 2025-2026 Fiscal Year

Mokena Community Public Library District Board of Trustees Meeting | August 2025 Article SummaryThe Mokena Community Public Library District Board of Trustees has officially adopted its Budget and Appropriation (B&A)...
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
mokena library logo graphic.4

Mokena Library Holds Public Hearing on Budget & Appropriation Ordinance

Article SummaryThe Mokena Community Public Library District Board of Trustees conducted its legally required public hearing for the 2025-2026 Budget and Appropriation Ordinance during a special meeting on August 26....
Meeting-Briefs

Meeting Summary and Briefs: Mokena Fire Protection District for August 2025

Mokena Fire Protection District Meeting | August 2025 The Mokena Fire Protection District Board of Trustees on Tuesday, August 12, 2025, focused on fleet management, approving the final payment for...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 15, 2025

Mokena Village Board Meeting | September 15, 2025 The Mokena Village Board held a special meeting on Monday, September 15, 2025, where its primary action was the unanimous approval of...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Mokena Logo Graphic.5

Mokena Board Approves Final Plat for 50-Home Boulder Ridge Phase IV Subdivision

Mokena Village Board Meeting | September 15, 2025 Article Summary: The Mokena Village Board approved the final plat for the 50-lot fourth phase of the Boulder Ridge subdivision, clearing the way...
mokena fire protection district logo graphic.3

Mokena Fire District Hiring, Deploys Drone to Assist Frankfort in Crisis

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is in the process of hiring a new firefighter/paramedic after receiving 11 applications for a vacant...
Joliet-Junior-college.-Graphic-Logo.3

JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees passed a controversial policy change allowing the student trustee to be counted...