Mokena Renews Traffic Signal Maintenance Contract at Reduced Cost
The Village of Mokena has extended its traffic signal maintenance contract for another year, securing the service at a lower cost after the number of signals under its jurisdiction was reduced.
On June 9, the Village Board approved a one-year extension with H&H Electric Company of Franklin Park for Fiscal Year 2026. The total cost of the contract is $17,905.92, which is below the $25,200 budgeted for the work in the Motor Fuel Tax Account.
Public Works Director Dan Peloquin explained that the cost reduction was possible because the Will County Department of Highway recently took over maintenance responsibilities for three signalized intersections: 191st Street & 88th Avenue, 191st Street & Hickory Creek Drive, and Townline Road & Francis Road.
This change reduces the number of signals maintained by H&H Electric for the village from 11 to eight, lowering the monthly cost to $1,492.16.
The contract covers routine monthly checks of timing, detectors, electrical components, and the alignment of signal heads. Peloquin noted that H&H Electric has been the village’s current contractor and has performed its duties well. Any extra work not included in the contract, such as emergency callouts or damage repairs, is paid for on a time-and-material basis. The board approved the extension unanimously.
Latest News Stories
 Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation
 Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support
 Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025
 Mokena Overhauls Zoning Code to Streamline Rules for Sheds, Pools, and Patios
 Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property
 Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026
 Mokena Awards $472K Contract for Countryview Estates Storm Sewer Project
 Frankfort Establishes New Zoning Rules to Attract Data Centers
 Fiber Internet Provider Pavlov Media Details Plans to Expand into Mokena
 Currie Motors Expansion Gets Approval with Site Modifications
 Mokena Celebrates Successful July 4th Events, Honors Parade Winners
 Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters