Mokena School District Terminates Contract with Evans and Sons Blacktop Over Project Deficiencies

MOKENA, Ill. – The Mokena School District 159 Board of Education voted unanimously Wednesday to terminate its contract with Evans and Sons Blacktop for the playground and parking lot improvements project at Mokena Elementary and Intermediate Schools, citing breach of contract and significant performance issues.

The move comes as the new school year approaches, with district officials expressing a lack of confidence in the contractor’s ability to complete the project in a timely and acceptable manner.

In a letter dated July 16, 2025, addressed to Daniel Evans of Evans and Sons Blacktop, Chief School Business Official Dr. Teri Shaw stated the contractor was in “breach of its obligations to perform the work in an acceptable and timely manner.” The letter directed the West Chicago-based company to cease all work on the project immediately.

“You have received several communications from our architects regarding performance deficiencies and with the new school year rapidly approaching we have no confidence that you will be able to complete the Project on time and in accordance with the contract documents,” Shaw wrote.

According to an action memo presented to the board, the decision followed a July 10 meeting between district officials, including Buildings and Grounds Director Dave Rana, and representatives from the project architect, Dan Kritta, and the project’s bonding company, emc Insurance, represented by Frank Alampi.

The district has already filed a claim with the bonding company and is moving to hire replacement contractors to finish the job. As part of its leverage, the district has withheld $140,000 from its original contract with Evans and Son due to the incomplete and unsatisfactory work.

“If we incur any additional costs beyond the $140,000 the bonding company will pay the cost,” Shaw noted in the memo.

The termination, effective July 17, was recommended based on multiple breaches of the contract, specifically sections 14.2.1.2 through 14.2.1.5 and 14.2.1.8 of the A201-2017 contract document. The letter serves as the company’s seven-day notice of termination.

The district also plans to seek an emergency resolution to hire a new site contractor, which would bypass the standard 10-day bid notification requirement. This is being done to expedite the hiring process and ensure the project is finished with minimal further delay, particularly with student safety and school operations in mind. The district expressly reserved all rights to pursue reimbursement for any extra costs incurred due to the breach.

The playground and parking lot improvements are part of a series of summer projects intended to upgrade district facilities before students return in August.

Events

No events

Latest News Stories

Meeting-Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...
Meeting-Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting-Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $7.9 Million Budget, Eyes Major Park Upgrades

The Mokena Community Park District Board of Commissioners has tentatively approved a $7.9 million budget for the 2023-24 fiscal year, a plan that earmarks significant funds for major park infrastructure...
Mokena Park District.logo.graphic.5

Mokena Park District Overhauls Safety Policies, Adopts Cyber Attack Response Plan

In a move to bolster security and protect participants, the Mokena Community Park District Board of Commissioners on Tuesday unanimously approved a sweeping update to its personnel policies, establishing new...
Mokena Park District.logo.graphic.1

Mokena Park District Bids Farewell to 12-Year Fitness Manager Rachel Bauer

The Mokena Park District is bidding farewell to Rachel Bauer, the longtime Manager of Fitness Center Operations at The Oaks, who is leaving after nearly 12 years of service. Bauer’s...
Mokena Park District.logo.graphic.1

New HVAC, Bleachers, and Lighting Among Recent Park District Upgrades

Visitors to Mokena Park District facilities are being greeted by a series of recent upgrades, including a new high-efficiency HVAC system, state-of-the-art lighting at the Yunker Park Bandshell, and new...
Meeting-Briefs

Meeting Briefs: Mokena Park District Board of Commissioners for July 25, 2023

The Mokena Park District Board of Commissioners met on July 25 to discuss upcoming events, review new policies, and approve the tentative budget for the new fiscal year. The board...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...