Mokena School District Terminates Contract with Evans and Sons Blacktop Over Project Deficiencies

Spread the love

MOKENA, Ill. – The Mokena School District 159 Board of Education voted unanimously Wednesday to terminate its contract with Evans and Sons Blacktop for the playground and parking lot improvements project at Mokena Elementary and Intermediate Schools, citing breach of contract and significant performance issues.

The move comes as the new school year approaches, with district officials expressing a lack of confidence in the contractor’s ability to complete the project in a timely and acceptable manner.

In a letter dated July 16, 2025, addressed to Daniel Evans of Evans and Sons Blacktop, Chief School Business Official Dr. Teri Shaw stated the contractor was in “breach of its obligations to perform the work in an acceptable and timely manner.” The letter directed the West Chicago-based company to cease all work on the project immediately.

“You have received several communications from our architects regarding performance deficiencies and with the new school year rapidly approaching we have no confidence that you will be able to complete the Project on time and in accordance with the contract documents,” Shaw wrote.

According to an action memo presented to the board, the decision followed a July 10 meeting between district officials, including Buildings and Grounds Director Dave Rana, and representatives from the project architect, Dan Kritta, and the project’s bonding company, emc Insurance, represented by Frank Alampi.

The district has already filed a claim with the bonding company and is moving to hire replacement contractors to finish the job. As part of its leverage, the district has withheld $140,000 from its original contract with Evans and Son due to the incomplete and unsatisfactory work.

“If we incur any additional costs beyond the $140,000 the bonding company will pay the cost,” Shaw noted in the memo.

The termination, effective July 17, was recommended based on multiple breaches of the contract, specifically sections 14.2.1.2 through 14.2.1.5 and 14.2.1.8 of the A201-2017 contract document. The letter serves as the company’s seven-day notice of termination.

The district also plans to seek an emergency resolution to hire a new site contractor, which would bypass the standard 10-day bid notification requirement. This is being done to expedite the hiring process and ensure the project is finished with minimal further delay, particularly with student safety and school operations in mind. The district expressly reserved all rights to pursue reimbursement for any extra costs incurred due to the breach.

The playground and parking lot improvements are part of a series of summer projects intended to upgrade district facilities before students return in August.

Events

No events

Latest News Stories

New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $550,000 Fund Transfer for Major Park Projects

The Mokena Community Park District Board of Commissioners has approved a $550,000 fund transfer to complete several key capital projects, including the construction of a new bathroom facility at Hecht...
LWSRA

Mokena Park District Joins Regional Partners in Renewed Funding Commitment for LWSRA

The Mokena Community Park District is renewing its financial commitment to the Lincolnway Special Recreation Association (LWSRA), joining eight other local park districts in an intergovernmental agreement that ensures continued...
mokena park Yunker Barn

Mokena Park District Seeks Nearly $1 Million State Grant for Yunker Barn Renovation

The Mokena Park District is seeking nearly $1 million in state funding to help transform the historic Yunker Park Barn into a year-round facility. Executive Director Greg Vitale announced at...
Meeting-Briefs

Meeting Briefs: Mokena Park District Board of Commissioners for June 27, 2023

The Mokena Park District Board of Commissioners met on June 27 to approve funding for capital projects, renew a regional partnership agreement, and review staff reports on recent and upcoming...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
mokena library logo graphic.4

Library Board Approves Annual Budget, Begins Review of Financial Advisor Proposals

The Library Board of Trustees unanimously approved its working budget for the new fiscal year at its June 24 meeting and formally began the process of selecting a financial advisor...
Screenshot-2025-07-06-at-9.50.39-AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot-2025-07-06-at-9.45.35-AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...
Meeting-Briefs

L-W School Board June 26 Meeting Briefs

Special Education District Update: The fence installation around the playground at Lincoln Way Area Special Education District 843 has been completed except for one gate section that will allow equipment...
mokena library logo graphic.10

Library Explores New IT and Copier Services Amid Equipment Failures

The Library is evaluating an overhaul of its technology services, exploring new providers for both IT support and its public-facing print management system due to ongoing equipment failures. During Tuesday's...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...