Mokena School District Terminates Contract with Evans and Sons Blacktop Over Project Deficiencies

Spread the love

MOKENA, Ill. – The Mokena School District 159 Board of Education voted unanimously Wednesday to terminate its contract with Evans and Sons Blacktop for the playground and parking lot improvements project at Mokena Elementary and Intermediate Schools, citing breach of contract and significant performance issues.

The move comes as the new school year approaches, with district officials expressing a lack of confidence in the contractor’s ability to complete the project in a timely and acceptable manner.

In a letter dated July 16, 2025, addressed to Daniel Evans of Evans and Sons Blacktop, Chief School Business Official Dr. Teri Shaw stated the contractor was in “breach of its obligations to perform the work in an acceptable and timely manner.” The letter directed the West Chicago-based company to cease all work on the project immediately.

“You have received several communications from our architects regarding performance deficiencies and with the new school year rapidly approaching we have no confidence that you will be able to complete the Project on time and in accordance with the contract documents,” Shaw wrote.

According to an action memo presented to the board, the decision followed a July 10 meeting between district officials, including Buildings and Grounds Director Dave Rana, and representatives from the project architect, Dan Kritta, and the project’s bonding company, emc Insurance, represented by Frank Alampi.

The district has already filed a claim with the bonding company and is moving to hire replacement contractors to finish the job. As part of its leverage, the district has withheld $140,000 from its original contract with Evans and Son due to the incomplete and unsatisfactory work.

“If we incur any additional costs beyond the $140,000 the bonding company will pay the cost,” Shaw noted in the memo.

The termination, effective July 17, was recommended based on multiple breaches of the contract, specifically sections 14.2.1.2 through 14.2.1.5 and 14.2.1.8 of the A201-2017 contract document. The letter serves as the company’s seven-day notice of termination.

The district also plans to seek an emergency resolution to hire a new site contractor, which would bypass the standard 10-day bid notification requirement. This is being done to expedite the hiring process and ensure the project is finished with minimal further delay, particularly with student safety and school operations in mind. The district expressly reserved all rights to pursue reimbursement for any extra costs incurred due to the breach.

The playground and parking lot improvements are part of a series of summer projects intended to upgrade district facilities before students return in August.

Events

No events

Latest News Stories

Meeting-Briefs

Meeting Summary: Joliet Junior College Board of Trustees for June 25, 2025

The Joliet Junior College Board of Trustees met on Wednesday, June 25, 2025. Key actions included the approval of the fiscal year 2026 budget after a contentious debate and hearing...
Mokena Logo Graphic.5

Mokena Enacts Local Grocery Tax to Avert $850,000 Revenue Loss

The Mokena Village Board has moved to preserve a crucial revenue stream, unanimously approving a new local grocery tax to replace state-collected funds that will disappear in 2026. The move...
Mokena Logo Graphic.6

Mokena Dissolves Two Committees to Streamline Development Process

In a bid to become more business-friendly, the Village of Mokena is dissolving two of its long-standing advisory committees to accelerate the process for new development. Mayor George J. Metanias...
Mokena Police Logo Graphic

Mokena Police to Get New Axon In-Car Cameras in $176K Deal

The Mokena Police Department is set to receive a significant technology upgrade after the Village Board approved a five-year, $176,526 contract with Axon Enterprise for a new in-car video system....
Callery Pear trees

Mokena Targets Invasive Callery Pear Trees for Removal

The Village of Mokena is taking proactive steps to improve its urban forest by removing dozens of invasive Callery Pear trees from public parkways, funded in part by a grant...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for June 23, 2025

The Mokena Village Board took several major actions at its June 23 meeting, including approving a new local grocery tax to head off a projected $850,000 revenue loss after the...
mokena school district 159.4

Mokena 159 Board Approves Amended Budget Amid Transparency, Deficit Concerns

The Mokena School District 159 Board of Education approved an amended budget for fiscal year 2025 in a contentious 6-1 vote Wednesday night, following sharp criticism from a board member...
mokena school district 159.3

Mokena 159 Board Signals Support for Recording Meetings After Public Push

Following requests from several residents, the Mokena School District 159 Board of Education on Wednesday discussed and expressed broad support for recording and publicly posting its meetings to increase transparency....
Wayfinder

District 159 Adopts ‘Wayfinder’ Program to Boost Middle Schoolers’ Social-Emotional Health

Mokena Junior High School students will have a new curriculum focused on social-emotional learning (SEL) next year after the Board of Education unanimously approved the adoption of the "Wayfinder" program....
mokena school district 159.3

Mokena 159 Principals Report End-of-Year Academic Progress, Focus on Writing

Principals from Mokena School District 159 presented their end-of-year School Improvement Plan (SIP) updates to the Board of Education on Wednesday, highlighting student progress with a particular focus on improving...
Meeting-Briefs

Meeting Briefs: Mokena School District 159 for June 18, 2025

The Mokena School District 159 Board of Education met on June 18, 2025. The board approved an amended budget for the upcoming fiscal year after significant debate. It also signaled...
Will-County-Board-Meeting-June-18-2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...
Will-County-Board-Meeting-June-18-2025

Will County Board Upholds Zoning Denials, Rejecting Developer Appeals

The Will County Board on Wednesday backed its Planning and Zoning Commission (PZC), denying two separate appeals from property owners who sought to overturn the commission’s recommendations against their projects....
Will-County-Board-Meeting-June-18-2025

Split Vote Halts Monee Truck Terminal Project

A proposed truck terminal on vacant land at West Monee-Manhattan Road in Monee Township was stopped in its tracks Wednesday after the Will County Board delivered a split decision on...
Will-County-Board-Meeting-June-18-2025

Future Quarry Fight Looms as Board Approves ‘Tequila Barrel’ Retreat

While the Will County Board greenlit a unique tourist destination featuring overnight stays in repurposed tequila barrels, it also received formal notice of a coming fight to shut down a...