Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Article Summary:
The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.
Public Works Building Key Points:
-
Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.
-
The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.
-
Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.
MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.
Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.
Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”
With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.
“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”
The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.
Latest News Stories
Will County Committee Adds Path to Citizenship Support to Federal Agenda
Health Department Outlines Major Reduction in Consensus Vaccine Schedule
Public Works Committee Forwards Condemnation Proceedings for Francis and Marley Road Improvements
Mokena Village Board Appoints New Capital Engineer and Police Staff
Finance Committee: Scholarship Tax Credit Discussion Halts
Will County Health Department Reports Rise in Respiratory Illnesses, Updates on Facility Issues
Public Works Committee Delays Vote on State Police License Plate Cameras Amid Privacy Concerns
Meeting Summary and Briefs: Mokena Community Park District for Nov. 2025
Mokena 2025 Responses
Flint Man Charged with 1988 Murder of Wife Joan Bernal Following Cold Case Breakthrough
Youth Basketball Draws Nearly 800 as “Winter on the Farm” Gains Popularity
Alex Parks Sworn in as Newest Mokena Police Officer