The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Today Jun 13
Chance Rain Showers then Mostly Cloudy
71° 51°

Chance Rain Showers then Mostly Cloudy

💨 10 to 20 mph 💧 45%

Leave a Comment





Latest News Stories

Pritzker signs Clean Slate Act to automatically seal some criminal convictions

Pritzker signs Clean Slate Act to automatically seal some criminal convictions

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker has signed legislation to automate the state’s record-sealing process for individuals with certain criminal...
Will County Board Graphic.02

Freight Clusters Drive Push for Overhaul of Wilmington-Peotone Road; County Advances Broader 2050 Plan

Will County Board Meeting | January 15, 2026 Article Summary: Citing the emergence of "new freight clusters," Will County is seeking federal support for a massive study to redesign 22...
sunny hill nursing home joliet il

Sunny Hill Administrator Defends Private Room Model Amidst Capacity Discussions

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: During the January 7, 2026, meeting, Sunny Hill Nursing Home Administrator Maggie McDowell reported a...
mokena fire protection district logo graphic.4

Mokena Fire District to Charge Care Facilities for Lift Assists

Mokena Fire Protection District Meeting | December 9, 2025 Article Summary: The Mokena Fire Protection District Board has approved a new ordinance authorizing fees for lift assist services provided to...
Elite private colleges can’t cap off price-fixing collusion class action

Elite private colleges can’t cap off price-fixing collusion class action

By Scott Holland | Legal NewslineThe Center Square A federal judge in Chicago has refused to end an antitrust class action complaint accusing elite universities of colluding in the financial...
Illinois Quick Hits: GOP gubernatorial forum set for Monday

Illinois Quick Hits: GOP gubernatorial forum set for Monday

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – All four Republican gubernatorial candidates are scheduled to participate in a forum in East Dundee on Monday....
lincoln way school district 210 logo.2

Lincoln-Way Board Approves Girls Flag Football for 2026-2027 Season

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: The Lincoln-Way Community High School District 210 Board of Education unanimously approved the addition of girls flag football...
WATCH: Ives investigates tax dollars for NGOs; Republicans say Pritzker raising energy prices

WATCH: Ives investigates tax dollars for NGOs; Republicans say Pritzker raising energy prices

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop talks live with Jeanne...
ICE hiring ban bill reignites SAFE-T Act fight at Illinois Capitol

ICE hiring ban bill reignites SAFE-T Act fight at Illinois Capitol

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A newly introduced bill that would bar former Immigration and Customs Enforcement agents from working in...
Will County Board Graphic.02

Executive Committee Advances Dissolution of Southeast Joliet Sanitary District

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee moved forward with two resolutions to facilitate the dissolution of the Southeast Joliet Sanitary District...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Board Legislative Committee for January 6, 2026

Will County Board Legislative Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Legislative Committee met on Tuesday, January 6, 2026, to finalize the county’s state and...
Will County Logo Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for January 6, 2026

Capital Improvements & IT Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Capital Improvements and IT Committee met on Tuesday, January 6, 2026, to discuss facility...
Will County Board Graphic.04

Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for January 7, 2026

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Overall Meeting SummaryThe Will County Board Public Health and Safety Committee met on Wednesday, January 7, 2026,...
Will County Board Graphic.03

Executive Committee: Relaxes Rules for Retiring Employee Proclamations

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee voted to amend county board rules to allow proclamations honoring retiring county employees to pass...