Report: Claims that preserving coal plants will cost $6B based on unlikely assumptions

Report: Claims that preserving coal plants will cost $6B based on unlikely assumptions

Spread the love

A new report released Tuesday by America’s Power challenges environmental organization-sponsored claims circulating that say the Trump administration’s decision to preserve coal power plants will cost ratepayers $3 billion to $6 billion more a year.

America’s Power is a “national trade organization whose sole mission is to advocate at the federal and state levels on behalf of the U.S. coal fleet and its supply chain,” according to its website.

As stated by America’s Power, consulting firm Grid Strategies released a report sponsored by four environmental organizations that claimed recent “orders issued by the Department of Energy (DOE) to keep fossil power plants operating for reliability purposes instead of retiring could cost $3 billion per year and perhaps as much as $6 billion per year by the end of 2028.”

The Grid Strategies report came to such conclusions by a series of extreme and unlikely assumptions, America’s Power said.

For instance, it was assumed that all the 54 fossil power plants that have announced intentions of retiring by 2028 – called “possible retirements” – would in fact retire.

Additionally, it was assumed that 36 fossil power plants that are 60 years old – called “speculative retirements” – would retire in 2028.

Both these “possible” and “speculative” retirements representing almost 66,400 megawatts were assumed to be soon receiving 202(c) orders from the Department of Energy that would extend for a year, bringing Grid Strategies’ report to the estimated cost of $3 billion to $6 billion a year.

A 202(c) order is a temporary order “that require[s] power plants that are needed during an ‘emergency’ to operate until the emergency ends,” according to America’s Power.

America’s Power said in its report that it “seems unlikely” that every possible and speculative retirement “will actually happen within the next three years and that every retiring plant will receive a 202(c) order directing it to continue operating for one year.”

Twenty-five out of the 27 times 202(c) orders have been in effect since 2000 have been for 90 days or less, America’s Power said.

“There are a couple of reasons to be a little skeptical about the large number of retirements assumed by Grid Strategies,” the report said.

“One is that load growth and other factors are driving utilities to reassess their plans to retire fossil power plants,” the report said. “For example, utilities have already deferred the retirement of almost 29,000 MW of coal-fired generation for a number of reasons, including concerns about load growth and reliability.”

Matt Kandrach from Consumer Action for a Strong Economy (CASE) said in a statement after the report’s release that the U.S. needs coal to avoid an energy shortage.

“It’s the height of lunacy when a highly available and affordable energy resource like coal is attacked by the same radical environmental groups who gladly support trillions of dollars in green energy mandates. We’re concerned that the North American Electricity Reliability Corporation – the nation’s reliability watchdog – warned recently that more than half the nation faces the risk of blackouts in the next decade from higher demand. That would be a disaster of astronomical costs to American businesses and consumers that President Trump is helping prevent by strengthening and stabilizing America’s energy resources.”

Another reason to be skeptical of 90 assumed retirements according to America’s Power is that the EPA “is rewriting or repealing a number of regulations that were expected to cause more fossil power plant retirements.”

America’s Power used different “just as plausible” assumptions such as “only half of the possible and speculative retirements actually occur,” “only half of these retirements receive DOE orders,” and “the orders extend for 90 days, not one year,” and came up with different results.

The estimate per year falls between $195 million and $370 million using these assumptions.

For reference, “customer expenditures nationally for electricity total close to $500 billion per year,” according to America’s Power.

“Obviously, no one knows for sure what will happen over the next three years or what the cost of DOE orders might be if they are needed to maintain reliability,” America’s Power’s report said.

The report additionally stated that “one of the main reasons” for the North American Electric Reliability Corporation’s warning that more than half the nation is possibly headed for “inadequate electricity supplies” is due to “the retirement of fossil power plants.”

Leave a Comment





Latest News Stories

Will County Board Graphic.02

Will County Passes Comprehensive Adult Entertainment Ordinance

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board passed Ordinance 26-133, enacting Chapter 119 of the Business Regulations to establish rigorous licensing, operational, and...
Fifth Circuit hands Texas another win on border security law

Fifth Circuit hands Texas another win on border security law

By Bethany BlankleyThe Center Square The Fifth Circuit Court of Appeals handed Texas its third win Friday on border security. As the border crisis escalated during the Biden administration, Gov....
Illinois Rep faces investigation over sexual harassment

Illinois Rep faces investigation over sexual harassment

By Sean Reed | The Center SquareThe Center Square (The Center Square) – A state representative embattled with allegations of sexual harassment returned to Springfield this week after being stripped...
Talks with Iran to resume

Talks with Iran to resume

By Sarah Roderick-FitchThe Center Square Middle East Special Envoy Steve Witkoff and Jared Kushner will head back to Pakistan over the weekend to resume talks, as Vice President JD Vance...
Return on investment questioned as Chicago Red Line construction begins

Return on investment questioned as Chicago Red Line construction begins

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Taxpayers are facing a hefty price tag as construction begins on a long-anticipated Chicago Transit Authority project...

WATCH: WA Democrat income tax supporter questions ‘necessity clause’ nixing public vote

By Carleen JohnsonThe Center Square A Democratic lawmaker who voted in support of Washington’s new income tax said he didn't see anything scandalous in this week’s revelation of emails showing...
DOJ to face audit for handling of Epstein files release

DOJ to face audit for handling of Epstein files release

By Thérèse BoudreauxThe Center Square Following the drawn-out and politically calamitous release of millions of federal documents related to the exploits of sex trafficker Jeffrey Epstein, the Department of Justice...
ISU strike enters third week; union sues over alleged strikebreaking

ISU strike enters third week; union sues over alleged strikebreaking

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Union support staff at Illinois State University has entered a third week on strike over failed contract...
Trump extends Jones Act waiver, citing national securit

Trump extends Jones Act waiver, citing national securit

By Alton WallaceThe Center Square The Trump administration has suspended for an additional 90 days a law forbidding foreign-owned and crewed ships from transporting goods between U.S. ports in an...
Trump admin continues to crack down on fraudulent visa schemes

Trump admin continues to crack down on fraudulent visa schemes

By Bethany BlankleyThe Center Square The Trump administration is continuing to crack down on fraudulent visa schemes that are occurring nationwide. In New Jersey, a Korean man pleaded guilty to...
Virginia 1 of 4 in courtroom battles for congressional redistricting

Virginia 1 of 4 in courtroom battles for congressional redistricting

By Shirleen GuerraThe Center Square Less than 100 days into Gov. Abigail Spanberger’s administration, Virginia’s redistricting fight is unfolding across multiple fronts, from the ballot box to the Legislature and...
Illinois Quick Hits: State gaming board renew Rockford casino license

Illinois Quick Hits: State gaming board renew Rockford casino license

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Illinois Gaming Board has renewed Hard Rock Casino Rockford’s license for four years, retroactive to January...
Arizona GOP pushes to protect Colorado River's limited water

Arizona GOP pushes to protect Colorado River’s limited water

By Zachery SchmidtThe Center Square Arizona Republicans are seeking to protect the Colorado River as its water supply continues to dwindle. State Senate President Warren Petersen, R-Gilbert; state House Speaker...
Republicans challenge Clyde in Georgia's 9th District

Republicans challenge Clyde in Georgia’s 9th District

By Andrew RiceThe Center Square Incumbent Rep. Andrew Clyde, R-Ga., is facing a primary challenger in his bid to hold on to his 9th District post. Sam Couvillon and Joel...
Fort Bragg soldier’s case continues Tuesday in New York

Fort Bragg soldier’s case continues Tuesday in New York

By Alan WootenThe Center Square An enlisted soldier at Fort Bragg was granted $250,000 bond release on Friday and will have his charges of using classified information to win $400,000...