Report: Claims that preserving coal plants will cost $6B based on unlikely assumptions

Report: Claims that preserving coal plants will cost $6B based on unlikely assumptions

Spread the love

A new report released Tuesday by America’s Power challenges environmental organization-sponsored claims circulating that say the Trump administration’s decision to preserve coal power plants will cost ratepayers $3 billion to $6 billion more a year.

America’s Power is a “national trade organization whose sole mission is to advocate at the federal and state levels on behalf of the U.S. coal fleet and its supply chain,” according to its website.

As stated by America’s Power, consulting firm Grid Strategies released a report sponsored by four environmental organizations that claimed recent “orders issued by the Department of Energy (DOE) to keep fossil power plants operating for reliability purposes instead of retiring could cost $3 billion per year and perhaps as much as $6 billion per year by the end of 2028.”

The Grid Strategies report came to such conclusions by a series of extreme and unlikely assumptions, America’s Power said.

For instance, it was assumed that all the 54 fossil power plants that have announced intentions of retiring by 2028 – called “possible retirements” – would in fact retire.

Additionally, it was assumed that 36 fossil power plants that are 60 years old – called “speculative retirements” – would retire in 2028.

Both these “possible” and “speculative” retirements representing almost 66,400 megawatts were assumed to be soon receiving 202(c) orders from the Department of Energy that would extend for a year, bringing Grid Strategies’ report to the estimated cost of $3 billion to $6 billion a year.

A 202(c) order is a temporary order “that require[s] power plants that are needed during an ‘emergency’ to operate until the emergency ends,” according to America’s Power.

America’s Power said in its report that it “seems unlikely” that every possible and speculative retirement “will actually happen within the next three years and that every retiring plant will receive a 202(c) order directing it to continue operating for one year.”

Twenty-five out of the 27 times 202(c) orders have been in effect since 2000 have been for 90 days or less, America’s Power said.

“There are a couple of reasons to be a little skeptical about the large number of retirements assumed by Grid Strategies,” the report said.

“One is that load growth and other factors are driving utilities to reassess their plans to retire fossil power plants,” the report said. “For example, utilities have already deferred the retirement of almost 29,000 MW of coal-fired generation for a number of reasons, including concerns about load growth and reliability.”

Matt Kandrach from Consumer Action for a Strong Economy (CASE) said in a statement after the report’s release that the U.S. needs coal to avoid an energy shortage.

“It’s the height of lunacy when a highly available and affordable energy resource like coal is attacked by the same radical environmental groups who gladly support trillions of dollars in green energy mandates. We’re concerned that the North American Electricity Reliability Corporation – the nation’s reliability watchdog – warned recently that more than half the nation faces the risk of blackouts in the next decade from higher demand. That would be a disaster of astronomical costs to American businesses and consumers that President Trump is helping prevent by strengthening and stabilizing America’s energy resources.”

Another reason to be skeptical of 90 assumed retirements according to America’s Power is that the EPA “is rewriting or repealing a number of regulations that were expected to cause more fossil power plant retirements.”

America’s Power used different “just as plausible” assumptions such as “only half of the possible and speculative retirements actually occur,” “only half of these retirements receive DOE orders,” and “the orders extend for 90 days, not one year,” and came up with different results.

The estimate per year falls between $195 million and $370 million using these assumptions.

For reference, “customer expenditures nationally for electricity total close to $500 billion per year,” according to America’s Power.

“Obviously, no one knows for sure what will happen over the next three years or what the cost of DOE orders might be if they are needed to maintain reliability,” America’s Power’s report said.

The report additionally stated that “one of the main reasons” for the North American Electric Reliability Corporation’s warning that more than half the nation is possibly headed for “inadequate electricity supplies” is due to “the retirement of fossil power plants.”

Leave a Comment





Latest News Stories

Will County Finance Logo

Will County Health Department Warns of Potential Federal Funding Cuts and Rising Healthcare Costs for FY2027

Will County Board Finance Committee Meeting | May 5, 2026 Article SummaryThe Will County Health Department presented its preliminary FY2027 budget outlook to the Finance Committee, warning of a looming...
Will County P&Z Logo Planning Zoning

Highland Liquors Cleared for Video Gaming Expansion Following Zoning Approval

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission on Tuesday, May 5, 2026, approved a Special Use Permit...
Will County Board Graphic.04

Access Will County Dial-A-Ride Reports Massive Growth After Consolidating Paratransit Services

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Access Will County Dial-a-Ride program has seen explosive growth in ridership following a major consolidation...
Will County Board Graphic.01

Legislative Committee Advances Resolution Opposing Kidney Disease Treatment Delegation Act

Will County Board Legislative Committee Meeting | May 5, 2026 Article SummaryThe Will County Legislative Committee unanimously approved a resolution formally opposing Senate Bill 3445 and House Bill 4402, citing...
Will County P&Z Logo Planning Zoning.2

Commission Approves Massive Lake Michigan Water Infrastructure Project for Troy Township

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission on May 5, 2026, unanimously approved two major public utility...
Will County Board Graphic.02

Committee: Capital Improvements Committee Weighs $300 Million Options for Downtown Joliet Campus

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 Article SummaryThe Will County Capital Improvements & IT Committee is evaluating four multi-million-dollar proposals to replace aging...
Will County Board Graphic.04

State Legislative Update: Housing Mandates, Mega Projects, and Data Centers Prompt Local Control Concerns

Will County Board Legislative Committee Meeting | May 5, 2026 Article SummaryState lobbyists from Mac Strategies briefed the Will County Board Legislative Committee on the final push of the spring...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for May 5, 2026

Will County Board Finance Committee Meeting | May 5, 2026 The Will County Board Finance Committee dedicated nearly its entire May 5, 2026, meeting to a series of rapid-fire, preliminary...
Will County Board Graphic.02

Committee Advances Nearly $212,000 in Road and Facility Contracts for Jackson Township and Monee

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee approved two infrastructure contracts totaling over $212,000 for...
Will County Board Graphic.03

Will County Committee Hits Brakes on License Plate Reader Agreements Awaiting Privacy Policy Review

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee delayed votes on five intergovernmental agreements for Automated...
Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for May 5, 2026

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 The Will County Board Capital Improvements & IT Committee focused heavily on long-term infrastructure planning during its...
Will County P&Z Logo Planning Zoning

Green Garden Solar Project Cleared to Implement Higher “Agrivoltaic” Standards

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission approved four variances on Tuesday, May 5, 2026, to facilitate...
Will County Board Graphic.01

Committee: Facilities Department Reports $92,000 in Energy Savings, Completes Veterans Assistance Commission Buildout

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 Article SummaryAssistant Director of Facilities Ken Rogalski reported significant energy savings and the completion of key county...
Will County P&Z Logo Planning Zoning

Green Garden Solar Farm Approved in Split Vote; Battery Storage Component Rejected

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission recommended approval for a new 4.98-megawatt solar facility in Green...
Screenshot 2026-05-05 at 1.46.14 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for April 15, 2026

Joliet Junior College Board of Trustees Meeting | April 15, 2026 The Joliet Junior College (JJC) Board of Trustees held a strictly ceremonial meeting on Wednesday evening after failing to...