Report: Offshore wind critics played role in Revolution Wind work stoppage

Report: Offshore wind critics played role in Revolution Wind work stoppage

Spread the love

Offshore wind opponents in the fishing industry helped shape the Trump administration’s decision to halt work on the Revolution Wind project, a $4 billion development off the coasts of Rhode Island and Connecticut, a new report says.

Annie Hawkins is a former fishing industry attorney and executive director at the Responsible Offshore Development Alliance (RODA), which opposes offshore wind farms. She is now the National Oceanic and Atmospheric Administration’s top lawyer. As NOAA’s attorney, Hawkins was included on Interior Department emails planning the work stoppage, Politico E&E News reported after receiving the emails through public information requests.

Seafreeze Shoreside, a Rhode Island based seafood company that is now owned by Spanish multinational company Profand Fishing Holding, is a member of RODA and is a plaintiff in a lawsuit against the Trump administration after the administration allowed another offshore wind project to proceed.

Emails also show Green Oceans, a Rhode Island group opposed to offshore wind, sent Interior a 68-page report called Cancelling Offshore Wind Leases ahead of the administration’s recent stop-work order for Revolution Wind, Politico reported.

The NOAA did not immediately respond to The Center Square’s request for comment, and declined to comment to Politico.

The stoppage has drawn sharp criticism from political leaders, unions and grid operators.

Connecticut Gov. Ned Lamont said on CNBC that Revolution Wind is nearly complete.

“Revolution Wind is in the 8th inning, and it’s going to generate 700 MW of power for our region, it’s going to bring down costs for people, it’s almost done… Not everyone in Washington knew about this. It was a sudden decision coming out of the White House,” Lamont said.

He warned of negative grid impacts if the administration canceled the project.

“…First thing that happens is much more likely we have blackouts in coming years because energy use is going up and this is a way we can generate a lot more electricity now… So, it will jack up prices and make our power a lot less reliable. It’s a terrible negative,” Lamont said.

The International Association of Bridge, Structural, Ornamental and Reinforcing Ironworkers also blasted the decision.

“This order puts hardworking American Workers out of a job and stalls a project our members have nearly brought over the finish line,” the union’s General President Eric Dean said. “Halting this job now doesn’t make America safer; it puts families at risk, kneecaps a nearly complete piece of critical infrastructure, and jeopardizes thousands of working-class union jobs. Let us finish the work we started.”

ISO New England, which manages the region’s electric grid, also raised concerns.

“Through the region’s wholesale markets, Revolution Wind has committed to helping meet New England’s demand for electricity, beginning in 2026,” ISO said, Reuters reported. “Delaying the project will increase risks to reliability.”

Dan Dolan, president of the New England Power Generators Association, expressed a similar sentiment, according to RTO Insider.

“When projects like Revolution Wind have met every legal requirement, secured financing, and obtained a Capacity Supply Obligation to support reliability, they should not face the rules being changed midstream,” he said. “Actions like this erode investor confidence and jeopardize long-term electric reliability in the region.”

The AFL-CIO called the stop-work order “an outrage,” saying it “effectively [kicks] hundreds of union members out of jobs their families and communities were relying on.”

Revolution Wind is 80% complete, according to the Iron Workers Union.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Mokena School District 159 for December 17, 2025

Mokena School District 159 Meeting | December 17, 2025 The Mokena District 159 Board of Education met on Wednesday, Dec. 17, 2025, to finalize the annual tax levy and review...
Will County Board Graphic.04

County Approves Engineering for Peotone Road and Safety Upgrades

Will County Board Meeting | December 18, 2025 Article Summary: The County Board approved a Phase I engineering contract for improvements to Wilmington-Peotone Road and authorized an agreement for license...
Screenshot 2025-12-20 at 12.27.11 PM

Lincoln-Way Board Approves $731,000 Freshman Laptop Purchase

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The District 210 Board of Education authorized the purchase of 1,750 Lenovo laptops to equip the incoming...
Will County Board Graphic.01

Monee Solar Farm Projects Granted Extensions

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee...
Sufyan Farhan

Frankfort Man Arrested in Gas Station Robbery Found Hiding in McDonald’s Restroom

Article Summary: Sufyan Farhan, 27, was arrested on December 21 following an armed robbery at a Frankfort Circle K. Deputies located the suspect hiding in a nearby McDonald's restroom after...
Mokena Library District Graphic

Mokena Library Board Approves 2025 Tax Levy and Seeks State Grant Funding

Mokena Community Public Library District Meeting | Nov. 25, 2025 Article Summary:The Mokena Community Public Library District Board of Trustees unanimously approved its annual tax levy and authorized an application...
mokena school district 159.1

District 159 Approves Working Cash Abatement and New Superintendent Goals

Mokena School District 159 Meeting | December 17, 2025 Article Summary: The Mokena District 159 Board on Wednesday, Dec. 17, 2025, approved a series of administrative and financial measures, including...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025

Will County Board Executive Committee Meeting | December 11, 2025 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, December 11, 2025, tackling a diverse agenda that included...
Planning & Zoning Graphic.4

New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: A New Lenox homeowner received approval to build a large pole barn that exceeds the county's size limits...
Will County Board Graphic.03

County Expands Paratransit Services, Board Members Question Long-Term Funding

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board approved an intergovernmental agreement with Pace to expand paratransit services county-wide for seniors and residents with...
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board for Dec. 10, 2025

Joliet Junior College Board Meeting | Dec. 10, 2025 Meeting Summary The Joliet Junior College Board of Trustees met on Wednesday, December 10, 2025, for a meeting marked by both...
Screenshot 2025-12-20 at 12.26.58 PM

District 210 Awards $24.4 Million Contract for Major HVAC Upgrades

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive...
mokena school district 159.3

Mokena 8th Graders Showcase App Designs and Green Architecture in STEM Spotlight

Mokena School District 159 Meeting | December 17, 2025 Article Summary: During the Dec. 17, 2025, meeting, eight female students from Mokena Junior High School presented innovative projects developed in...
Will County Board Graphic.02

Mental Health Board Updates Committee on 2026 Grant Cycle and Funding Priorities

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Will County Community Mental Health Board provided a quarterly update, outlining the timeline and strategic priorities for...
Will County P&Z Logo Planning Zoning

PZC Approves Homer Township Landscape Business Despite Neighbor Concerns; Adds Berm Condition

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a new landscape business on...