Report: Offshore wind critics played role in Revolution Wind work stoppage

Report: Offshore wind critics played role in Revolution Wind work stoppage

Spread the love

Offshore wind opponents in the fishing industry helped shape the Trump administration’s decision to halt work on the Revolution Wind project, a $4 billion development off the coasts of Rhode Island and Connecticut, a new report says.

Annie Hawkins is a former fishing industry attorney and executive director at the Responsible Offshore Development Alliance (RODA), which opposes offshore wind farms. She is now the National Oceanic and Atmospheric Administration’s top lawyer. As NOAA’s attorney, Hawkins was included on Interior Department emails planning the work stoppage, Politico E&E News reported after receiving the emails through public information requests.

Seafreeze Shoreside, a Rhode Island based seafood company that is now owned by Spanish multinational company Profand Fishing Holding, is a member of RODA and is a plaintiff in a lawsuit against the Trump administration after the administration allowed another offshore wind project to proceed.

Emails also show Green Oceans, a Rhode Island group opposed to offshore wind, sent Interior a 68-page report called Cancelling Offshore Wind Leases ahead of the administration’s recent stop-work order for Revolution Wind, Politico reported.

The NOAA did not immediately respond to The Center Square’s request for comment, and declined to comment to Politico.

The stoppage has drawn sharp criticism from political leaders, unions and grid operators.

Connecticut Gov. Ned Lamont said on CNBC that Revolution Wind is nearly complete.

“Revolution Wind is in the 8th inning, and it’s going to generate 700 MW of power for our region, it’s going to bring down costs for people, it’s almost done… Not everyone in Washington knew about this. It was a sudden decision coming out of the White House,” Lamont said.

He warned of negative grid impacts if the administration canceled the project.

“…First thing that happens is much more likely we have blackouts in coming years because energy use is going up and this is a way we can generate a lot more electricity now… So, it will jack up prices and make our power a lot less reliable. It’s a terrible negative,” Lamont said.

The International Association of Bridge, Structural, Ornamental and Reinforcing Ironworkers also blasted the decision.

“This order puts hardworking American Workers out of a job and stalls a project our members have nearly brought over the finish line,” the union’s General President Eric Dean said. “Halting this job now doesn’t make America safer; it puts families at risk, kneecaps a nearly complete piece of critical infrastructure, and jeopardizes thousands of working-class union jobs. Let us finish the work we started.”

ISO New England, which manages the region’s electric grid, also raised concerns.

“Through the region’s wholesale markets, Revolution Wind has committed to helping meet New England’s demand for electricity, beginning in 2026,” ISO said, Reuters reported. “Delaying the project will increase risks to reliability.”

Dan Dolan, president of the New England Power Generators Association, expressed a similar sentiment, according to RTO Insider.

“When projects like Revolution Wind have met every legal requirement, secured financing, and obtained a Capacity Supply Obligation to support reliability, they should not face the rules being changed midstream,” he said. “Actions like this erode investor confidence and jeopardize long-term electric reliability in the region.”

The AFL-CIO called the stop-work order “an outrage,” saying it “effectively [kicks] hundreds of union members out of jobs their families and communities were relying on.”

Revolution Wind is 80% complete, according to the Iron Workers Union.

Leave a Comment





Latest News Stories

mokena library logo graphic.10

Library Explores New IT and Copier Services Amid Equipment Failures

The Library is evaluating an overhaul of its technology services, exploring new providers for both IT support and its public-facing print management system due to ongoing equipment failures. During Tuesday's...
Joliet-Junior-college.-Graphic-Logo.2

JJC Embarks on New 10-15 Year Facilities Master Plan Process

Joliet Junior College is laying the groundwork for its physical future, officially launching a comprehensive process to create a new facilities master plan that will guide campus development for the...
Meeting-Briefs

Meeting Briefs: Library Board of Trustees for June 24, 2025

The Library Board of Trustees unanimously approved its annual working budget after amending the family programs line to $25,000. The board is also moving forward with long-term financial planning, having...
Meeting-Briefs

Meeting Summary: Joliet Junior College Board of Trustees for June 25, 2025

The Joliet Junior College Board of Trustees met on Wednesday, June 25, 2025. Key actions included the approval of the fiscal year 2026 budget after a contentious debate and hearing...
Mokena Logo Graphic.5

Mokena Enacts Local Grocery Tax to Avert $850,000 Revenue Loss

The Mokena Village Board has moved to preserve a crucial revenue stream, unanimously approving a new local grocery tax to replace state-collected funds that will disappear in 2026. The move...
Mokena Logo Graphic.6

Mokena Dissolves Two Committees to Streamline Development Process

In a bid to become more business-friendly, the Village of Mokena is dissolving two of its long-standing advisory committees to accelerate the process for new development. Mayor George J. Metanias...
Mokena Police Logo Graphic

Mokena Police to Get New Axon In-Car Cameras in $176K Deal

The Mokena Police Department is set to receive a significant technology upgrade after the Village Board approved a five-year, $176,526 contract with Axon Enterprise for a new in-car video system....
Callery Pear trees

Mokena Targets Invasive Callery Pear Trees for Removal

The Village of Mokena is taking proactive steps to improve its urban forest by removing dozens of invasive Callery Pear trees from public parkways, funded in part by a grant...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for June 23, 2025

The Mokena Village Board took several major actions at its June 23 meeting, including approving a new local grocery tax to head off a projected $850,000 revenue loss after the...
mokena school district 159.4

Mokena 159 Board Approves Amended Budget Amid Transparency, Deficit Concerns

The Mokena School District 159 Board of Education approved an amended budget for fiscal year 2025 in a contentious 6-1 vote Wednesday night, following sharp criticism from a board member...
mokena school district 159.3

Mokena 159 Board Signals Support for Recording Meetings After Public Push

Following requests from several residents, the Mokena School District 159 Board of Education on Wednesday discussed and expressed broad support for recording and publicly posting its meetings to increase transparency....
Wayfinder

District 159 Adopts ‘Wayfinder’ Program to Boost Middle Schoolers’ Social-Emotional Health

Mokena Junior High School students will have a new curriculum focused on social-emotional learning (SEL) next year after the Board of Education unanimously approved the adoption of the "Wayfinder" program....
mokena school district 159.3

Mokena 159 Principals Report End-of-Year Academic Progress, Focus on Writing

Principals from Mokena School District 159 presented their end-of-year School Improvement Plan (SIP) updates to the Board of Education on Wednesday, highlighting student progress with a particular focus on improving...
Meeting-Briefs

Meeting Briefs: Mokena School District 159 for June 18, 2025

The Mokena School District 159 Board of Education met on June 18, 2025. The board approved an amended budget for the upcoming fiscal year after significant debate. It also signaled...
Will-County-Board-Meeting-June-18-2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...