Will County Grants Extensions to Five Solar Projects Sold to New Developers

Spread the love

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy developers. The new operators, Nautilus Solar and Madison Energy Infrastructure, now have until 2026 to begin construction as they work to secure final permits.

Solar Project Sales Key Points:

  • Projects Involved: Five separate solar farms in Peotone, Monee, Crete, and Joliet townships received 180-day extensions.

  • New Developers: Two projects were sold to Nautilus Solar, and three were sold to Madison Energy Infrastructure.

  • Action: The extensions give the new owners until February or April 2026 to secure construction permits and lawfully establish the facilities.

  • Status: While required variances for the projects have been established, construction permits submitted by the new developers remain under review by the county.

JOLIET — A pattern of smaller solar energy projects being sold to larger developers has prompted the Will County Board to grant permit extensions for five separate solar farms. The board unanimously approved the first 180-day extensions for the projects, which are now owned by Nautilus Solar and Madison Energy Infrastructure.

According to county memos, the original applicants for all five projects had successfully established required variances related to ground cover and mowing, but the special use permits were nearing their two-year expiration dates. The projects were subsequently sold to the new developers, who have since applied for construction permits that are still under review.

Nautilus Solar acquired two projects:

  • A facility from Aequo Foundation, Inc. on Kennedy Road in Peotone.

  • A facility from Felipe D. Recendez on South Will Center Road in Monee.
    Both permits are now valid through April 17, 2026.

Madison Energy Infrastructure acquired three projects:

  • Two facilities from Dart Farms, Inc. in Joliet Township at the northwest and southwest corners of Cherry Hill Road and W. Schweitzer Road/US 52.

  • A facility from The Moeller Trust on Torrence Avenue in Crete.
    These permits are now valid through February 13, 2026.

The board’s approval of the extensions provides the new operators additional time to finalize the permitting process and begin construction on the renewable energy facilities.

Leave a Comment





Latest News Stories

Mokena Logo Graphic.6

Mokena Dissolves Two Committees to Streamline Development Process

In a bid to become more business-friendly, the Village of Mokena is dissolving two of its long-standing advisory committees to accelerate the process for new development. Mayor George J. Metanias...
Mokena Police Logo Graphic

Mokena Police to Get New Axon In-Car Cameras in $176K Deal

The Mokena Police Department is set to receive a significant technology upgrade after the Village Board approved a five-year, $176,526 contract with Axon Enterprise for a new in-car video system....
Callery Pear trees

Mokena Targets Invasive Callery Pear Trees for Removal

The Village of Mokena is taking proactive steps to improve its urban forest by removing dozens of invasive Callery Pear trees from public parkways, funded in part by a grant...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for June 23, 2025

The Mokena Village Board took several major actions at its June 23 meeting, including approving a new local grocery tax to head off a projected $850,000 revenue loss after the...
mokena school district 159.4

Mokena 159 Board Approves Amended Budget Amid Transparency, Deficit Concerns

The Mokena School District 159 Board of Education approved an amended budget for fiscal year 2025 in a contentious 6-1 vote Wednesday night, following sharp criticism from a board member...
mokena school district 159.3

Mokena 159 Board Signals Support for Recording Meetings After Public Push

Following requests from several residents, the Mokena School District 159 Board of Education on Wednesday discussed and expressed broad support for recording and publicly posting its meetings to increase transparency....
Wayfinder

District 159 Adopts ‘Wayfinder’ Program to Boost Middle Schoolers’ Social-Emotional Health

Mokena Junior High School students will have a new curriculum focused on social-emotional learning (SEL) next year after the Board of Education unanimously approved the adoption of the "Wayfinder" program....
mokena school district 159.3

Mokena 159 Principals Report End-of-Year Academic Progress, Focus on Writing

Principals from Mokena School District 159 presented their end-of-year School Improvement Plan (SIP) updates to the Board of Education on Wednesday, highlighting student progress with a particular focus on improving...
Meeting-Briefs

Meeting Briefs: Mokena School District 159 for June 18, 2025

The Mokena School District 159 Board of Education met on June 18, 2025. The board approved an amended budget for the upcoming fiscal year after significant debate. It also signaled...
Will-County-Board-Meeting-June-18-2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...
Will-County-Board-Meeting-June-18-2025

Will County Board Upholds Zoning Denials, Rejecting Developer Appeals

The Will County Board on Wednesday backed its Planning and Zoning Commission (PZC), denying two separate appeals from property owners who sought to overturn the commission’s recommendations against their projects....
Will-County-Board-Meeting-June-18-2025

Split Vote Halts Monee Truck Terminal Project

A proposed truck terminal on vacant land at West Monee-Manhattan Road in Monee Township was stopped in its tracks Wednesday after the Will County Board delivered a split decision on...
Will-County-Board-Meeting-June-18-2025

Future Quarry Fight Looms as Board Approves ‘Tequila Barrel’ Retreat

While the Will County Board greenlit a unique tourist destination featuring overnight stays in repurposed tequila barrels, it also received formal notice of a coming fight to shut down a...
Meeting-Briefs

News Briefs from the Will County Board June 18 Meeting

Monee Church Designated Historic LandmarkThe Will County Board unanimously voted to designate St. Paul's United Church of Christ in Monee as a historical landmark. Member Judy Ogalla, a Monee native,...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort Approves Outdoor Patios for The Loft and Grounded Coffee Bar, Waives All Parking Requirements

Downtown Frankfort is set to expand its outdoor dining options after the Village Board on Monday approved plans for new patios at two adjacent businesses, The Loft and Grounded Coffee...