solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Spread the love

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy developers. The new operators, Nautilus Solar and Madison Energy Infrastructure, now have until 2026 to begin construction as they work to secure final permits.

Solar Project Sales Key Points:

  • Projects Involved: Five separate solar farms in Peotone, Monee, Crete, and Joliet townships received 180-day extensions.

  • New Developers: Two projects were sold to Nautilus Solar, and three were sold to Madison Energy Infrastructure.

  • Action: The extensions give the new owners until February or April 2026 to secure construction permits and lawfully establish the facilities.

  • Status: While required variances for the projects have been established, construction permits submitted by the new developers remain under review by the county.

JOLIET — A pattern of smaller solar energy projects being sold to larger developers has prompted the Will County Board to grant permit extensions for five separate solar farms. The board unanimously approved the first 180-day extensions for the projects, which are now owned by Nautilus Solar and Madison Energy Infrastructure.

According to county memos, the original applicants for all five projects had successfully established required variances related to ground cover and mowing, but the special use permits were nearing their two-year expiration dates. The projects were subsequently sold to the new developers, who have since applied for construction permits that are still under review.

Nautilus Solar acquired two projects:

  • A facility from Aequo Foundation, Inc. on Kennedy Road in Peotone.

  • A facility from Felipe D. Recendez on South Will Center Road in Monee.
    Both permits are now valid through April 17, 2026.

Madison Energy Infrastructure acquired three projects:

  • Two facilities from Dart Farms, Inc. in Joliet Township at the northwest and southwest corners of Cherry Hill Road and W. Schweitzer Road/US 52.

  • A facility from The Moeller Trust on Torrence Avenue in Crete.
    These permits are now valid through February 13, 2026.

The board’s approval of the extensions provides the new operators additional time to finalize the permitting process and begin construction on the renewable energy facilities.

Leave a Comment





Latest News Stories

Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort Police Department to Get Four New Vehicles in Fleet Upgrade

FRANKFORT, Ill. – The Frankfort Police Department will be updating its aging fleet after the Village Board approved the purchase of four new vehicles for a total cost not to...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Indoor Pickleball Facility ‘Pickled!’ Gets Green Light in Frankfort

A new indoor pickleball facility named "Pickled!" is set to open in Frankfort after the Village Board granted a special use permit for the business at its Monday meeting. The...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort to Install Public Wi-Fi at Breidert Green

Visitors to Breidert Green in downtown Frankfort will soon have access to free public wireless internet. The Village Board on Monday approved the purchase and installation of Wi-Fi equipment to...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Frankfort Board Approves Indoor Recreation Facility and Setback Variance

The Frankfort Village Board gave its approval to two separate development projects Monday night, clearing the way for a new indoor pickleball facility and a residential addition. Trustees unanimously granted...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Meeting Briefs: Frankfort Village Board for June 16, 2025

Downtown Patios Approved, Parking Waived: The Village Board approved outdoor seating for The Loft and Grounded Coffee Bar on Ash Street. To support the downtown businesses, trustees also voted to waive...
mokena fire protection district logo graphic.5

Mokena Fire District Approves Annual Budget After Public Hearing

The Mokena Fire Protection District Board of Trustees unanimously adopted its budget and appropriation ordinance for the 2025-2026 fiscal year, finalizing the district’s spending plan after a formal public hearing...
mokena fire protection district logo graphic.4

Mokena Fire District Faces 14% Insurance Hike, Renews Policies

The Mokena Fire Protection District is grappling with significant increases in insurance costs, with its property and liability policy renewal rate jumping by approximately 14%. The Board of Trustees unanimously...
mokena fire protection district logo graphic.1

Fire District Inks New Banking Agreement with Old Plank Trail

The Mokena Fire Protection District Board of Trustees has approved a new two-year banking agreement with Old Plank Trail, a move aimed at securing favorable rates amid a volatile market....
Meeting-Briefs

Meeting Briefs: Mokena Fire Protection District for June 10, 2025

The Mokena Fire Protection District Board of Trustees formally adopted its budget and appropriation ordinance for the 2025-2026 fiscal year following a public hearing. With no members of the public...
Will-County-Executive-Committee-Meeting-June-12-2025

Mental Health Board Awards $5 Million in Grants to Will County Organizations

The Will County Community Mental Health Board has distributed over $5 million in grants to 39 local organizations, marking the completion of its inaugural funding cycle since voters approved the...
frankfort-square-park-district.2

Frankfort Square Park District Adopts Budget and Appropriation Ordinance, Updates Financial Policy

The Frankfort Square Park District Board of Commissioners formally adopted its Budget and Appropriation Ordinance for the 2025-2026 fiscal year on Thursday, finalizing the district's legal spending authority for the...
Will-County-Executive-Committee-Meeting-June-12-2025

County Board Approves Major Code Updates, Discusses Employee Benefits

The Will County Board Executive Committee approved several ordinance updates Wednesday while engaging in detailed discussions about employee compensation and benefits. The committee passed ordinances updating three chapters of the...
frankfort-square-park-district.1

Major Park District Projects Advance as Hunter Prairie Park Gets Green Light

Work on the Frankfort Square Park District's three major capital projects is hitting key milestones, with the long-awaited redevelopment of Hunter Prairie Park now officially underway. Executive Director Audrey Marcquenski...
Meeting-Briefs

Executive Committee June 12 Meeting Briefs

Property Purchase Approved: The county authorized purchase of two parcels along Governor's Highway in Monee for $545,000 to establish a roadway maintenance facility for the eastern end of the county....
frankfort-square-park-district.2

Developer to Donate Land, Playground for New Park in Tinley Park

A new park is coming to a Tinley Park development thanks to a land and equipment donation from a local home builder. Frank Bradley, owner of Crana Homes, is donating...