Renovations at Veterans Assistance Commission and Court Annex on Track for Winter Completion

Spread the love

Article Summary: Will County’s new Veterans Assistance Commission facility in Joliet is projected to be completed by December, while major renovations for the State’s Attorney’s office in the Court Annex are on schedule for a November move-in. Director of Facilities Bill Fern updated a county committee on the progress of these and other key capital projects across the county.

Capital Projects Update Key Points:

  • Interior renovations at the Veterans Assistance Commission buildout at 1300 Copperfield are underway, with a target completion of December 2025.

  • The Court Annex renovations for the State’s Attorney’s office at 57 N. Ottawa are nearing completion and on track for a November 2025 move-in.

  • A potential delay in the delivery of rooftop air handlers for the VAC building is being monitored by the facilities department.

  • Other completed projects include exterior stone repairs at the new courthouse and the installation of speed bumps at the county office building.

JOLIET, IL — Two major Will County building projects are nearing the finish line, with the new Veterans Assistance Commission (VAC) facility expected to open by December and the State’s Attorney’s office set to move into its renovated space in November.

Will County Director of Facilities Bill Fern provided the updates to the Capital Improvements & IT Committee on Tuesday, October 7, 2025.

The buildout of the former Copperfield building at 1300 Copperfield for the VAC is progressing well, with mechanical, lighting, and security systems currently being installed. Fern noted one potential issue that staff is monitoring closely. “The air handling units for the rooftop… the timeline for shipment has been delayed twice,” he said. “We’re coming into the critical point where we’re going to need to condition the space for heat, not air.” Despite the potential delay, the project is still aiming for completion by the end of the year.

Meanwhile, renovations on the second level of the Court Annex building at 57 N. Ottawa for the State’s Attorney’s office are moving quickly. “We’re in a finished space now with the carpet down,” Fern reported, adding that the project is on track for its November move-in date. The remodel includes opening up previously sealed windows to provide natural light to the new offices.

Fern also reported on several smaller projects, including the recent installation of speed bumps and fresh striping in the parking lot of the Will County Office Building to improve pedestrian safety. He also noted that exterior stone repairs on the new courthouse are complete, with scaffolding now removed, at no cost to the county.

Leave a Comment





Latest News Stories

Screenshot 2025-10-25 at 10.49.23 AM

Senior Shared Housing Facility Recommended for Approval in Crete Township

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: The Will County Planning and Zoning Commission has recommended approval for a special use permit that would...
Screenshot 2025-10-25 at 10.49.32 AM

Crete Township ‘Tiny Home’ Owner Appeals Permit Denial

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: A Crete Township property owner has appealed to the Will County Planning and Zoning Commission after being...
Will County Finance Logo

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board Article Summary:The Will County Board’s Finance Committee on Tuesday, November 12, 2025, narrowly approved a series of...
mokena school district 159.1

Board Approves $190,000 Transfer from Working Cash Fund Amid Dissent

Mokena School District 159 Meeting | November 19, 2025 Article Summary: The Mokena School District 159 Board of Education approved a resolution to abate $190,000 from its working cash fund...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
mokena fire protection district logo graphic.5

Mokena Fire District Secures $160,000 in Grants to Replace Hoses and Nozzles

Mokena Fire Protection District Meeting | October 14, 2025 Article Summary: The Mokena Fire Protection District has successfully secured approximately $160,000 in grant funding, nearly covering the entire cost to...
solar panels photovoltaics in solar farm

New Lenox to Host Large Pollinator-Friendly Solar Farm

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a commercial solar energy facility spanning approximately 63 acres in...
joliet junior college logo

JJC Receives Clean Audit, Reports $21.6 Million Increase in Net Position

Joliet Junior College Meeting | November 12, 2025 Article Summary:Joliet Junior College received a "clean unmodified audit opinion" for the fiscal year ending June 30, 2025, the highest level of...
will county board graphic

Will County Board Passes 0% Tax Levy, Creating “Unbalanced” Budget Crisis

Will County Board Meeting | November 2025 Article Summary: In a contentious fiscal showdown, the Will County Board voted to keep the corporate property tax levy flat, rejecting a proposed...
Poll: Majority of Americans still support legal immigration

Poll: Majority of Americans still support legal immigration

By Andrew RiceThe Center Square A majority of Americans say that legal immigration is good for the United States, according to a new poll commissioned by The Center Square. The...
New Illinois youth center begins housing youth in Lincoln

New Illinois youth center begins housing youth in Lincoln

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) - After a short delay to finalize staffing and safety preparations, the new Monarch Center in Lincoln...