Mokena 159 Board Approves Increased Cost for Junior High Storage Shed Amid Budget Debate

Spread the love

Mokena School District 159 Board of Education Meeting | October 15, 2025

Article Summary: The Mokena School District 159 Board of Education approved a cost increase for a new storage shed at Mokena Junior High School, raising the project’s total cost to a maximum of $176,000. The decision, which passed in a contentious 5-2 vote, sparked a debate over fiscal responsibility in light of the district’s budget deficit and the intent of referendum funds.

MJHS Storage Shed Project Key Points:

  • The board approved a revised project cost not to exceed $176,000, an increase from the previously approved $162,500.

  • The cost increase is due to a newly required perimeter frost footing for the shed’s foundation, a change from the original design.

  • The project is funded through the “Warm, Safe, and Dry” referendum funds, designated for facilities and maintenance.

  • Board members debated whether the expenditure was responsible given the district’s budget deficit and if the funds could be better used elsewhere.

MOKENA, IL — The Mokena School District 159 Board of Education on Wednesday, October 15, 2025, approved an increased budget for the Mokena Junior High School (MJHS) storage shed project, bringing the total cost to a maximum of $176,000. The vote followed a lengthy and pointed debate among board members about the project’s necessity, timing, and funding source amid a projected $1.3 million budget deficit.

The project, initially approved in September 2024 for $162,500, requires additional funding due to a change in construction requirements. According to a memo from Dr. Teri Shaw, the district’s Chief School Business Official, the shed’s provider now requires a perimeter frost footing instead of the previously planned thickened slab edge. This change necessitates deeper excavation and more concrete, increasing the cost for contractor Bear Construction by $14,600 to a total of $159,600. The total project cost is not to exceed $176,000.

Board member Kelli MacMillan voiced strong opposition to the project, calling it an “irresponsible spend.” She argued that the district is operating without the shed now and could delay the project indefinitely, particularly given the budget deficit.

“We are in a deficit, meaning we are spending $1.3 million… more than the revenue we have coming in,” MacMillan stated. “I don’t feel good about prioritizing a shed over students and staff. I don’t feel good about it and that’s why I won’t do it.”

MacMillan also questioned the use of referendum funds, which she said were intended to keep students “warm, safe and dry, not construction equipment.” She pointed out that the district is budgeting to transfer $190,000 from its working cash fund reserves to its Operations and Maintenance (O&M) fund. “Essentially, we’re saying we need money from our reserves to pay for a $176,000 shed that does not impact our classrooms. And I have an issue with that,” she said.

Board President Jim Andresen countered, stating that the funds for the shed come from the “Warm, Safe, and Dry” referendum, which are legally restricted for facilities, maintenance, and equipment protection. He stressed that this money could not be reallocated to classroom or salary expenses.

“This does not impact a classroom. The promise was made… to use that money for the facilities,” Andresen said. “This is not making the students do without. This is making sure we are protecting the capital investments we made with our equipment… We have to take care of our equipment and this is no different.”

Andresen added that a “forever lock” was placed on the referendum funds, requiring a unanimous board vote to ever use them for purposes outside of facilities, such as salaries or school supplies. “Please do not think for a second that that trust is going to be violated,” he said.

Board member Lisa Zielinski also expressed reservations but ultimately supported the project. “I struggle with the warm, safe, and dry and if it’s aesthetics,” she commented, before thanking the administration for bringing the cost increase to the board for a vote, even though the amount was within a 10% threshold that did not technically require re-approval.

The motion to approve the increased cost passed 5-2, with members MacMillan and Julie Oost voting against it.

Leave a Comment





Latest News Stories

mokena library logo graphic.4

Mokena Library Holds Public Hearing on Budget & Appropriation Ordinance

Article SummaryThe Mokena Community Public Library District Board of Trustees conducted its legally required public hearing for the 2025-2026 Budget and Appropriation Ordinance during a special meeting on August 26....
Meeting-Briefs

Meeting Summary and Briefs: Mokena Fire Protection District for August 2025

Mokena Fire Protection District Meeting | August 2025 The Mokena Fire Protection District Board of Trustees on Tuesday, August 12, 2025, focused on fleet management, approving the final payment for...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 15, 2025

Mokena Village Board Meeting | September 15, 2025 The Mokena Village Board held a special meeting on Monday, September 15, 2025, where its primary action was the unanimous approval of...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Mokena Logo Graphic.5

Mokena Board Approves Final Plat for 50-Home Boulder Ridge Phase IV Subdivision

Mokena Village Board Meeting | September 15, 2025 Article Summary: The Mokena Village Board approved the final plat for the 50-lot fourth phase of the Boulder Ridge subdivision, clearing the way...
mokena fire protection district logo graphic.3

Mokena Fire District Hiring, Deploys Drone to Assist Frankfort in Crisis

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is in the process of hiring a new firefighter/paramedic after receiving 11 applications for a vacant...
Joliet-Junior-college.-Graphic-Logo.3

JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees passed a controversial policy change allowing the student trustee to be counted...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 8, 2025

Mokena Village Board Meeting | September 8, 2025 The Mokena Village Board on Monday, September 8, 2025, unanimously approved a major overhaul of its police ticketing system, raising fines for...
Mokena Logo Graphic.5

Mokena Board Greenlights Boulder Ridge Development Settlement

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board has approved a settlement agreement involving the developer of the Boulder Ridge subdivision, resolving outstanding issues and...
mokena fire protection district logo graphic.5

Mokena Fire District Invests in New Inventory System for $5,500 Annually

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is upgrading its internal operations by purchasing a new inventory management system called PSTrax. The board...
Mokena Logo Graphic.1

Mokena Appoints Jacob Hazek as New Village Arborist

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board has appointed Jacob Hazek to the position of Arborist within the Public Works Department. Hazek was selected...
Joliet-Junior-college.-Graphic-Logo.2

Joliet Junior College, City of Joliet to Explore Joint Public Safety Institute

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved an intergovernmental agreement with the City of Joliet to begin...
Mokena Logo Graphic.2

Mokena Awards Nearly $300,000 in Contracts for Road Maintenance and Project Oversight

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board approved two contracts totaling over $292,000 for its Fiscal Year 2026 street improvement and maintenance programs. The...
Mokena Logo Graphic.6

Mokena Board Approves Sweeping Increases to Police Ticket Fines

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board unanimously approved a new ordinance that significantly increases fines for a wide range of non-traffic municipal code...
mokena fire protection district logo graphic.4

Mokena Fire District Adds New Ambulance, Addresses $18,000 in Fleet Repairs

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is preparing to put a new ambulance into service by the end of August after completing...