Article Summary: The Mokena School District 159 Board of Education approved a cost increase for a new storage shed at Mokena Junior High School, raising the project’s total cost to a maximum of $176,000. The decision, which passed in a contentious 5-2 vote, sparked a debate over fiscal responsibility in light of the district’s budget deficit and the intent of referendum funds.

MJHS Storage Shed Project Key Points:

  • The board approved a revised project cost not to exceed $176,000, an increase from the previously approved $162,500.

  • The cost increase is due to a newly required perimeter frost footing for the shed’s foundation, a change from the original design.

  • The project is funded through the “Warm, Safe, and Dry” referendum funds, designated for facilities and maintenance.

  • Board members debated whether the expenditure was responsible given the district’s budget deficit and if the funds could be better used elsewhere.

MOKENA, IL — The Mokena School District 159 Board of Education on Wednesday, October 15, 2025, approved an increased budget for the Mokena Junior High School (MJHS) storage shed project, bringing the total cost to a maximum of $176,000. The vote followed a lengthy and pointed debate among board members about the project’s necessity, timing, and funding source amid a projected $1.3 million budget deficit.

The project, initially approved in September 2024 for $162,500, requires additional funding due to a change in construction requirements. According to a memo from Dr. Teri Shaw, the district’s Chief School Business Official, the shed’s provider now requires a perimeter frost footing instead of the previously planned thickened slab edge. This change necessitates deeper excavation and more concrete, increasing the cost for contractor Bear Construction by $14,600 to a total of $159,600. The total project cost is not to exceed $176,000.

Board member Kelli MacMillan voiced strong opposition to the project, calling it an “irresponsible spend.” She argued that the district is operating without the shed now and could delay the project indefinitely, particularly given the budget deficit.

“We are in a deficit, meaning we are spending $1.3 million… more than the revenue we have coming in,” MacMillan stated. “I don’t feel good about prioritizing a shed over students and staff. I don’t feel good about it and that’s why I won’t do it.”

MacMillan also questioned the use of referendum funds, which she said were intended to keep students “warm, safe and dry, not construction equipment.” She pointed out that the district is budgeting to transfer $190,000 from its working cash fund reserves to its Operations and Maintenance (O&M) fund. “Essentially, we’re saying we need money from our reserves to pay for a $176,000 shed that does not impact our classrooms. And I have an issue with that,” she said.

Board President Jim Andresen countered, stating that the funds for the shed come from the “Warm, Safe, and Dry” referendum, which are legally restricted for facilities, maintenance, and equipment protection. He stressed that this money could not be reallocated to classroom or salary expenses.

“This does not impact a classroom. The promise was made… to use that money for the facilities,” Andresen said. “This is not making the students do without. This is making sure we are protecting the capital investments we made with our equipment… We have to take care of our equipment and this is no different.”

Andresen added that a “forever lock” was placed on the referendum funds, requiring a unanimous board vote to ever use them for purposes outside of facilities, such as salaries or school supplies. “Please do not think for a second that that trust is going to be violated,” he said.

Board member Lisa Zielinski also expressed reservations but ultimately supported the project. “I struggle with the warm, safe, and dry and if it’s aesthetics,” she commented, before thanking the administration for bringing the cost increase to the board for a vote, even though the amount was within a 10% threshold that did not technically require re-approval.

The motion to approve the increased cost passed 5-2, with members MacMillan and Julie Oost voting against it.

Leave a Comment





Latest News Stories

Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Plans Back-to-School Fair July 12

The Will County Health Department will host a Back-to-School Health Fair Saturday, July 12, from 10 a.m. to 2 p.m. at the Community Health Center, 1106 Neal Ave., Joliet. The...
Meeting-Briefs

Meeting Briefs: Will County Land Use & Development Committee for July 3, 2025

Green Garden Township Rezoning for Future Subdivision ApprovedThe committee recommended approval of a map amendment for an 81-acre property on South 88th Avenue in Green Garden Township. The applicant, represented...
Meeting-Briefs

Will County Public Health & Safety Committee July 3 Meeting Briefs

Grain Dust Complaint Prompts Investigation: Will County resident Tracy Henning of unincorporated Peotone addressed the committee about health problems she attributes to grain dust from a neighboring facility. Henning, who...
Will-County-Legislative-Committee-Meeting-July-1-2025

Will County Seeks Asian Carp Provision in Federal Legislative Agenda

Will County Board member Julie Berkowicz is pushing to add specific language addressing Asian carp invasion to the county's federal legislative agenda, citing the ongoing threat to local waterways as...
Will-County-Legislative-Committee-Meeting-July-1-2025

State Legislative Session Update: Transit, Energy Bills Stall Despite Democratic Control

Illinois lawmakers failed to advance major transit funding and comprehensive energy legislation during the recently concluded spring session, leaving key issues unresolved despite Democratic supermajorities in both chambers, according to...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”

Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

County Board Approves 2026-2031 Transportation Plan Despite Project Opposition

Will County board members approved a contested five-year transportation improvement plan Tuesday after heated debate over a controversial Homer Glen road project that has drawn sustained community opposition. The Will...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Contentious I-3 Rezoning for DuPage Township Storage Yard Narrowly Advances

A proposal to rezone a 20-acre parcel in DuPage Township from agricultural to the county's most intensive industrial classification narrowly earned a recommendation for approval from the Will County Planning...
Meeting-Briefs

Will County Legislative Committee July 1 Meeting Briefs

Federal Budget Impact: Will County could face significant funding challenges if federal budget reconciliation measures reduce Medicaid and SNAP benefits. The county health department and social services rely heavily on...
Will-County-Finance-Committee-Meeting-July-1-2025

County Moves Forward with $200.8 Million Bond Refinancing Plan

Will County Finance Committee members on July 1 approved moving forward with a comprehensive bond refinancing ordinance that could save taxpayers more than $716,000 over the life of the bonds...
Will-County-Public-Works-Transportation-Committee-Meeting-July-1-2025

Access Will County Dial-a-Ride Program Sees Record Growth, Eyes Expansion

Will County's dial-a-ride transportation service for seniors and disabled residents reached record ridership levels while officials plan major expansion to cover all county townships. The Access Will County program served...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County to Launch New Public Meeting Agenda System in August Amidst Data Conversion Concerns

Will County is set to launch its new public meeting agenda and records software, Granicus “OneMeeting,” in August, but the transition will see over a decade of historical records converted...
Will-County-Planning-and-Zoning-Commission-Meeting-July-1-2025

Green Garden Township Poised for First Major Subdivision in Years After Rezoning

The Will County Planning and Zoning Commission has recommended a rezoning that could pave the way for the first major residential subdivision in Green Garden Township in nearly two decades....
Will-County-Finance-Committee-Meeting-July-1-2025

County RNG Facility Shows Strong Performance Despite Solar Challenges

Will County's Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability. Project manager Greg Komperda told Finance Committee...
Meeting-Briefs

PZC Briefs: Solar Farm in Crete, Post-Fire Permit for Troy Business, and More

The Will County Planning and Zoning Commission handled several other cases during its July 1 meeting, including a new solar farm, a temporary permit for a fire-damaged business, and routine...