Report: PJM power grid electrification faces bumpy transition

Report: PJM power grid electrification faces bumpy transition

Spread the love

(The Center Square) – The nation’s power grid is entering a new era of soaring demand – the full extent of which remains uncertain – and energy leaders warn that investments in new generation, efficiency, and infrastructure must begin now to prevent future shortfalls.

U.S. electricity demand is projected to rise 25% by 2030 and up to 78% by 2050, with peak demand growing 14% and 54% over the same period, according to a new report by consulting and technology firm ICF.

The report, “Rising Current: America’s growing electricity demand,” highlights three main concerns – reliability, affordability, and new generation – and suggests how grid planners can work together to meet those challenges.

Most new demand is driven by data centers and industrial sites, which require steady baseload generation, such as natural gas and nuclear plants, and robust demand-side management.

The report notes that in PJM’s region, data centers, building electrification, and semiconductor manufacturing, along with electric vehicles, account for 35% of projected load growth through 2040.

Reliability and Affordability

Reserve margins, the cushion between available generation and peak demand, average 24% nationally but could fall below the 15% reliability threshold by 2030.

Interconnection delays and firm generation like natural gas, nuclear, and hydropower lag behind retirements, so new capacity isn’t coming online fast enough to match accelerating demand.

ICF notes that it’s unlikely the U.S. will run out of electricity, but the next few years could be especially challenging as new projects take years to complete.

In one scenario based on estimated capacity reserves – and assuming some near-term power plant additions and retirements – ERCOT’s region, in Texas, was projected as the first to experience tighter conditions by 2026, followed by MISO, which covers the Midwest, and PJM by 2028. By 2040, the combined markets could collectively face a total shortfall of more than 150 GW, which is enough electricity to power as many as 37.5 million homes.

Rising demand will likely drive up both wholesale electricity and capacity prices, which are, inevitably, passed on to customers.

The extent will vary by utility based on underlying market dynamics, but ICF projects residential rates could climb 15% to 40% by 2030 compared to 2025, and some could double by 2050.

Roughly 80 GW of new capacity, or enough power to supply as many as 24 million homes, must be added each year, which is double the 40 GW installed annually over the past five years.

Planners are turning to demand-side management programs and behind-the-meter resources such as rooftop solar and battery storage, which can be deployed quickly and could supply more than 10% of demand by 2030.

Utility-scale projects will still be essential, and ICF calls for an all-of-the-above mix. Capacity growth must average 3.3% annually through 2050, up from the historical average of 1.8%.

Renewables and energy storage will see the largest installation gains, but fossil fuels, especially natural gas, will remain vital for round-the-clock power. Interest in nuclear is returning, though hurdles remain.

Transmission and Distribution

New power plants can increase supply, but the additional power still requires an infrastructure that can accommodate it as it moves from the generation source to the transmission grid and then to customers via the distribution grid.

As retail prices rise, more homes and businesses are expected to consider behind-the-meter resources, such as rooftop solar and battery storage, further complicating distribution grid investment decisions.

New infrastructure is essential, but utilities must also maximize the performance of what’s already in place. One proposed solution is to deploy technologies like dynamic line ratings.

By attaching dynamic line rating sensors to transmission lines, utilities can adjust the amount of electricity that safely flows through power lines based on real-time weather conditions rather than relying on static, worst-case assumptions.

ICF stresses that agencies need advanced planning tools to assess policy impacts, guide infrastructure development, avoid overbuilding and stranded assets.

“This is a pivotal moment as rising demand creates urgent challenges for the grid,” said Anne Choate, ICF executive vice president for energy, environment and infrastructure in a press release. “Meeting this demand will take a coordinated effort from across the energy sector on an ‘all-of-the-above’ strategy. Success will require nuanced pricing, temporal considerations, and customer engagement, including demand-side management programs which can deliver fast, affordable solutions while scaling for long-term capacity, reliability, and affordability.”

Leave a Comment





Latest News Stories

mokena fire district #2 logo graphic.5

Mokena Fire Station 2 Slated for Bunk Room Renovations

Mokena Fire Protection District Meeting | September 2025 Article Summary: The Mokena Fire Protection District is budgeting up to $35,000 to renovate the bunk rooms at Fire Station 2 on 191st...
Golf Cart

Mokena Enacts New Regulations for E-Bikes, Scooters, and Golf Carts

Village of Mokena Board of Trustees Meeting | October 27, 2025 Article Summary: The Mokena Village Board has passed a new ordinance establishing comprehensive regulations for electric bicycles, scooters, and...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Authorizes Land Buy for Grundy County Expansion, Secures Site in Morris

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees has authorized negotiations for a land acquisition to build a...
FAA funding problems hit airports in California, elsewhere

FAA funding problems hit airports in California, elsewhere

By Madeline ShannonThe Center Square As Christine Finch helped her father, Graham Finch, gather his luggage at the San Francisco International Airport, she was worried about how flight delays caused...
Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

By Jonathan Bilyk | Legal NewslineThe Center Square A Chicago federal judge has barred federal agents from U.S. Border Patrol and ICE from conducting crowd control actions anywhere in northern...
Report: IL public schools show low academic proficiency, higher taxpayer funding

Report: IL public schools show low academic proficiency, higher taxpayer funding

By Jim Talamonti | The Center SquareThe Center Square (The CEnter Square) – The latest education statistics indicate stagnant proficiency for public school students in Illinois, despite dramatic increases in...
Watchdog: Special interest group paid legislators’ $25,000 resort bill

Watchdog: Special interest group paid legislators’ $25,000 resort bill

By Elyse ApelThe Center Square A government watchdog group has filed ethics complaints against more than a dozen Democratic legislators in Colorado. Common Cause alleges the legislators had $25,000 in...
will county board graphic

Commission Grants Green Garden Solar Farm Project Variance Extension

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial...
Union Pacific to ask appeals court for biometrics lawsuit exemption

Union Pacific to ask appeals court for biometrics lawsuit exemption

By Jonathan Bilyk | Legal NewslineThe Center Square Though he has said he believes the company's position would lead to legally "absurd" results, a federal judge will still allow freight...