Mokena Awards $204,888 Contract for Wastewater Pump Replacement
Village of Mokena Board of Trustees Meeting | October 13, 2025
Article Summary: The Mokena Village Board has awarded a $204,888 contract to Dahme Mechanical Industries Inc. to replace three aging pumps at the village’s wastewater treatment plant. The project addresses critical infrastructure needs and follows a similar replacement of three other pumps in 2023.
Wastewater Pump Contract Key Points:
-
The board approved a contract for $204,888 to replace Return Activated Sludge (RAS) pumps one through three.
-
The winning bidder was Dahme Mechanical Industries Inc. of Arlington Heights, which submitted the lowest of three bids.
-
The project follows the 2023 replacement of pumps four through six, which cost approximately $178,290.
The Mokena Village Board on Monday, October 13, 2025, approved a contract for $204,888 to replace essential equipment at its wastewater treatment plant. The board awarded the contract to Dahme Mechanical Industries Inc. of Arlington Heights to replace the plant’s first three Return Activated Sludge (RAS) pumps.
Public Works Director Dan Peloquin informed the board that the pumps, which recycle heavy, viscous fluids back into the water treatment process, have reached the end of their operational life and require replacement. This project is the second phase of a complete overhaul of the system, following the replacement of RAS pumps four through six in 2023 at a cost of $178,290.
The village received three bids for the current project. The bid from Dahme Mechanical was the lowest but came in approximately 8% over the budgeted amount of $190,000, which Peloquin attributed to rising costs.
“We have seen the cost increases,” Peloquin said, comparing the current bid to the lower cost of the first phase of the project in 2023. He noted that his staff was confident in Dahme Mechanical’s qualifications, as the company has completed similar work for other municipalities.
The board voted unanimously to approve the bid and award the contract, ensuring the continued operational reliability of the village’s wastewater treatment facility.
Latest News Stories
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for October 2025
Library Board Approves Annual Transfer to Special Reserve Fund
Board Approves Permit to Rebuild Historic Barn on Schoolhouse Road
Mokena and Tinley Park Fire Departments Renew 5-Year Fleet Maintenance Agreement
Will County Saves Nearly $5.74 Million in Bond Refinancing, Explores Future Borrowing Options
Will County Board Advances New Speed Limits in Green Garden and Frankfort Townships
New Lenox Garage Variance Denied After Neighbor Cites ‘Massive’ Scale and Neighborhood Impact
JJC Celebrates “Future Wolves” Partnerships with Joliet and Troy School Districts
State Veto Session Passes Energy Bill Limiting County Zoning, Approves Toll Hike for Mass Transit
Voting rights group warns CA redistricting push could undermine trust in IL
Chicago downtown office space vacancy rate jumps to record high levels
Mokena Announces Proposed 2025 Property Tax Levy of $2.3 Million