Mokena Approves Additional $30,000 for Concrete Pavement Patching
Village of Mokena Board of Trustees Meeting | October 27, 2025
Article Summary: The Mokena Village Board authorized an additional $30,000 for its fiscal year 2026 concrete patching program, bringing the total project cost to $127,950. The extra funds will allow contractor P.T. Ferro Construction to address more extensive cracking found at repair sites along the village’s July 4th parade route.
Pavement Patching Key Points:
-
The board approved a change order not to exceed $30,000 for the PCC Pavement Patching project.
-
The original contract with P.T. Ferro Construction was for $97,950 to repair approximately 220 square yards of concrete.
-
Additional funds were needed after discovering more extensive underlying damage at the repair locations.
The Mokena Village Board on Monday, October 27, 2025, approved spending up to an additional $30,000 on its annual concrete pavement patching program. The funds were added to an existing contract with P.T. Ferro Construction, raising the total authorized amount for the project to $127,950.
Public Works Director Dan Peloquin explained that the village had initially awarded a $97,950 contract in September to repair about 220 square yards of concrete at three locations that required emergency asphalt patches over the summer. These spots were along the route for the village’s July 4th parade.
After the initial contract was awarded, Peloquin said that upon further examination with the contractor, it became “evident that due to the underlying cracking underneath that temporary patching, that additional pavement removal would probably be likely.”
To address the more extensive damage, staff recommended using $30,000 budgeted for emergency patchwork to increase the quantity of concrete that can be replaced as part of the planned project. The board unanimously approved the change order, allowing the contractor to complete the more comprehensive repairs.
Latest News Stories
War of words reignites with Trump, Pritzker, Bailey
Judge won’t let ConAgra off hook in class action over fish fillet brine
Meeting Summary and Briefs: Will County Board Legislative Committee for May 5, 2026
Meeting Summary and Briefs: Will County Board Executive Committee for May 14, 2026
Will County Executive Committee Splits on Whether to Ask Voters About Single-Member Districts
Will County Departments to Stop Accepting Pennies, Rounding Down Cash Transactions
Legislative Committee: Federal Update Highlights $79 Billion ICE Funding and DHS Reconciliation
Will County Executive Committee Backs Funding Pursuit for $2.33 Million Harris Drive Property Buyouts
Will County Division of Transportation Requests $1 Million Increase to Highway Levy to Combat Inflation
Will County Hears Proposal to Establish County-Focused Land Bank for Distressed Properties
Will County Executive Committee Recommends 600 MW Pride of the Prairie Solar Project in 6-5 Split Vote
Aging Systems and Judicial Mandates Drive Significant FY2027 Budget Requests for Will County Courts and Sheriff