Monee Solar Farm Projects Granted Extensions
Will County Board Meeting | December 18, 2025
Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee Township. The projects, located near Will Center Road, are moving through the permitting and development phases.
Solar Farm Extension Key Points:
-
Projects: Monee 77 LLC and Monee 32 LLC.
-
Location: Properties along South Will Center Road and West Pauling Road in Monee Township.
-
Action: First extension granted for 180 days, valid until July 17, 2026.
-
Development Status: Applicants are currently working through permitting processes.
The Will County Board on Thursday, December 18, 2025, voted to approve extensions for two commercial solar energy developments in Monee Township.
The board granted a first extension for a special use permit issued to Monee 77 LLC for a commercial solar energy facility located at 26723 South Will Center Road. The original permit, approved in January 2024, included four conditions.
Additionally, the board approved a first extension for Monee 32 LLC for a commercial solar energy facility located at the northwest corner of West Pauling Road and South Will Center Road.
Under the Will County Zoning Ordinance, special use permits can be extended on up to four separate occasions for up to 180 days each. These extensions allow the developers additional time to complete necessary permitting and pre-construction activities. Both extensions are valid until July 17, 2026.
Latest News Stories
GOP rep, Dem alderman: Sanctuary policies drove immigration enforcement surge
WATCH: Labor leaving agreed-bill process has consequences, Illinois legislator warns
County Board Abates Over $25 Million in Property Taxes for Bond Payments
Frankfort Highway Department Plans Levy Increase to Replace Aging Trucks
Mokena Library Board Pauses Expansion Plans, Citing Financial Impact
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025
Frankfort Township Board Grants Supervisor Authority to Negotiate Real Property Development
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers