Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

⚠️ Special Weather Statement issued June 4 at 4:25AM CDT by NWS Chicago IL
Today Jun 3
Mostly Sunny
87° 66°

Mostly Sunny

💨 5 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for May 5, 2026

Will County Board Finance Committee Meeting | May 5, 2026 The Will County Board Finance Committee dedicated nearly its entire May 5, 2026, meeting to a series of rapid-fire, preliminary...
Will County Board Graphic.02

Committee Advances Nearly $212,000 in Road and Facility Contracts for Jackson Township and Monee

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee approved two infrastructure contracts totaling over $212,000 for...
Will County Board Graphic.03

Will County Committee Hits Brakes on License Plate Reader Agreements Awaiting Privacy Policy Review

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee delayed votes on five intergovernmental agreements for Automated...
Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for May 5, 2026

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 The Will County Board Capital Improvements & IT Committee focused heavily on long-term infrastructure planning during its...
Will County P&Z Logo Planning Zoning

Green Garden Solar Project Cleared to Implement Higher “Agrivoltaic” Standards

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission approved four variances on Tuesday, May 5, 2026, to facilitate...
Will County Board Graphic.01

Committee: Facilities Department Reports $92,000 in Energy Savings, Completes Veterans Assistance Commission Buildout

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 Article SummaryAssistant Director of Facilities Ken Rogalski reported significant energy savings and the completion of key county...
Will County P&Z Logo Planning Zoning

Green Garden Solar Farm Approved in Split Vote; Battery Storage Component Rejected

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission recommended approval for a new 4.98-megawatt solar facility in Green...
Screenshot 2026-05-05 at 1.46.14 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for April 15, 2026

Joliet Junior College Board of Trustees Meeting | April 15, 2026 The Joliet Junior College (JJC) Board of Trustees held a strictly ceremonial meeting on Wednesday evening after failing to...
Screenshot 2026-05-05 at 1.46.14 PM

JJC Board Meeting Halted by Lack of Quorum; New Student Trustee Sworn In

Joliet Junior College Board of Trustees Meeting | April 15, 2026 Article Summary: A lack of a voting quorum forced the Joliet Junior College Board of Trustees to delay all official...
Screenshot 2026-05-05 at 1.46.14 PM

JJC Entrepreneur and Business Center Celebrates $800,000 Federal Grant, Client Successes

Joliet Junior College Board of Trustees Meeting | April 15, 2026 Article Summary: The Joliet Junior College Entrepreneur and Business Center highlighted its recent community impact and rapid growth during a...
Chicago mayor to push for local funding, keeping Bears

Chicago mayor to push for local funding, keeping Bears

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – As he travels to Springfield to lobby for state funding of local governments, Chicago Mayor Brandon Johnson...
Senate Republicans unveil $72 billion budget package to fund ICE, CBP

Senate Republicans unveil $72 billion budget package to fund ICE, CBP

By Thérèse BoudreauxThe Center Square Republicans are forging ahead with legislation to fund Immigration and Customs Enforcement and Customs and U.S. Border Patrol along party lines. The two Senate committees...
Illinois AI regulations have mild industry support, could draw federal ire

Illinois AI regulations have mild industry support, could draw federal ire

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Experts in artificial intelligence spoke to state lawmakers recently, providing guidance on four bills introduced in the...
DOJ files complaint to block Minnesota climate lawsuit

DOJ files complaint to block Minnesota climate lawsuit

By Elyse ApelThe Center Square The U.S. Department of Justice has filed a complaint against Minnesota, seeking to block the state from continuing to pursue a lawsuit against energy companies...
Hegseth: Ceasefire holds despite Iranian aggression

Hegseth: Ceasefire holds despite Iranian aggression

By Morgan SweeneyThe Center Square Despite Iranian forces opening fire on American warships in the Strait of Hormuz Monday, War Secretary Pete Hegseth said the ceasefire still holds and the...