Meeting Summary and Briefs: Will County Landfill Committee for Jan. 13, 2026
Will County Landfill Committee Meeting | Jan. 13, 2026
The Will County Board Landfill Committee met on Tuesday, January 13, 2026, to address operational improvements at the Prairie View Landfill and its associated Renewable Natural Gas (RNG) plant. The meeting focused on future expansion plans, litter control, and significant capital equipment investments aimed at increasing revenue reliability.
RNG Plant Equipment Rental Review:
The committee discussed the ongoing rental costs for a telehandler and manlift at the RNG plant, which currently total nearly $12,000 per month. Committee members directed staff to investigate the feasibility of purchasing the equipment outright or converting the rental agreement to a lease-to-own model to save money. Staff was also instructed to stop renting the equipment through a third-party contractor to avoid markups and instead rent directly from the supplier.
Vertical vs. Horizontal Expansion:
Consultants confirmed that the county is pursuing both vertical and horizontal expansion permits for the landfill simultaneously. While vertical expansion is straightforward, the horizontal plan requires complex engineering to divert leachate pipes around existing waste cells.
Confidential Negotiations:
The committee briefly discussed stalled negotiations with Local 150 regarding land acquisition needed for the landfill expansion. Outside counsel Chuck Helston agreed to re-initiate contact with the union’s general counsel, potentially offering a land-for-dirt-removal deal that could serve as a training opportunity for union apprentices.
Tarping Enforcement:
Board Member Herbert Brooks Jr. raised questions about enforcing tarping regulations for trucks leaving the landfill. Staff clarified that while incoming trucks are required by state law to be tarped, the county’s host agreement also requires trucks to be clean before leaving. Staff committed to monitoring this more closely.
Return on Investment (ROI):
Regarding the proposed fourth compressor for the RNG plant, staff presented data estimating a 3 to 4.9-year return on investment. The additional unit is projected to stabilize production, allowing the plant to consistently hit higher revenue targets by avoiding downtime associated with the current three-compressor setup.
Latest News Stories
Noem refuses Pritzker enforcement pause request, IL passes sanctuary enhancement
WATCH: Energy bill opponents say increases IL electric bills by $8 billion passes
WA Dems blame GOP for government shutdown; 1 million in state could lose SNAP benefits
Officials react to allegations of civilians impersonating ICE
Illinois quick hits: IL taxpayers have highest pension debt obligations in U.S.
WATCH: Bonta visits food bank amid lawsuit over CalFresh
IL taxpayers to pay $20M for food banks as SNAP funding lapses start Saturday
Poll: 7 in 10 of Americans are against mail-order abortion without a doctor visit
Trump’s plan to re-start nuclear weapons testing faces criticism
Illinois quick hits: Corrections director appointment approved; Clean Slate Act passes
Tyler Robinson’s in-person hearing delayed to January
WATCH: Clean Slate Act passes Illinois legislature despite opposition