mokena school district 159.5

Mokena 159 Moves Forward with Over $1 Million in Summer Capital Project Plans

Spread the love

Mokena School District 159 Meeting | February 18, 2026

Article Summary: The Mokena School District 159 Board of Education authorized the administration to seek bids for major summer facility improvements, including a near-$860,000 roofing project and significant flooring replacements across the district.
Mokena School District 159 Key Points:

  • Roofing Project: The Board approved a roof replacement and restoration project for Mokena Elementary and Intermediate Schools with an estimated cost of $858,965.

  • Flooring Upgrades: A Request for Proposals (RFP) was authorized for office flooring replacements at all three schools, estimated at $180,180.

  • Funding: Both projects are slated to be funded through the Fiscal Year 2027 Fund 21 budget.

  • Timeline: Work is scheduled to be completed during the summer of 2026.

The Mokena School District 159 Board of Education on Wednesday, February 18, 2026, advanced plans for more than $1 million in facility improvements scheduled for the upcoming summer break. The Board voted to approve the project parameters and authorized the administration to issue Requests for Proposals (RFP) for roofing and flooring work.

The largest project discussed was the roof replacement and restoration at Mokena Elementary School (MES) and Mokena Intermediate School (MIS). According to a memo provided by Chief School Business Official Dr. Teri Shaw, the district is working with Tremco to obtain bids through a National Joint Purchasing Agreement.

The estimated cost for the roofing project is $858,965. The scope of work involves replacing ballasted roof sections that cannot be restored, specifically covering 22,185 square feet. This includes MES Central sections 4 and 4A (above the third-grade hallway), MES South section 1 (above the south gym), and MIS section 4 (west end of north-end classrooms). Additionally, the project includes restoration work on the MES South Gym roof. The new roofs will carry a 20-year warranty.

“We are working off the Capital Plan and the next biggest projects at MIS and MES are the Roof Replacement or Restoration,” Dr. Shaw wrote in the memo to the Board.

In a separate vote, the Board approved issuing an RFP for a flooring projects package with a total project cost budget not to exceed $180,180. This project targets the main offices, reception areas, and administrative offices at MES, MIS, and Mokena Junior High School (MJHS). At the junior high, an alternative option to add stairwell treads is also being considered.

Board Member Eric Bush questioned the estimated price tag for the flooring work during the meeting.

“I was, you know, a little taken back at $180,000 for flooring costs. That’s quite a bit,” Bush said during the discussion. However, he noted that after speaking with the administration, he understood the necessity of the vote.

“To be clear, this is an RFP. This is not a legal statement that we have to do this project,” Bush said. “I think it’s imperative that we get these right numbers tonight and then we can analyze it better next month.”

Dr. Shaw confirmed that the $180,180 figure is an estimate from the district’s architects, Wold Architects and Engineers, and that the actual cost could fluctuate between $150,000 and $210,000 depending on the bids received. The Board also approved an architect fee of $8,281 associated with the flooring project.

In other facility news, the Board reviewed informational items regarding paving projects planned for the summer. This includes sealcoating the MIS hard surface play area, the MES north parking lot, and Willowcrest Lane, with an anticipated cost not to exceed $50,000. Additionally, the MJHS front circle drive is scheduled for resurfacing, with a projected cost not to exceed $45,000.

The roofing and flooring items were approved via a roll call vote.

Leave a Comment





Latest News Stories

mokena fire district #2 logo graphic.5

Mokena Fire Station 2 Slated for Bunk Room Renovations

Mokena Fire Protection District Meeting | September 2025 Article Summary: The Mokena Fire Protection District is budgeting up to $35,000 to renovate the bunk rooms at Fire Station 2 on 191st...
Golf Cart

Mokena Enacts New Regulations for E-Bikes, Scooters, and Golf Carts

Village of Mokena Board of Trustees Meeting | October 27, 2025 Article Summary: The Mokena Village Board has passed a new ordinance establishing comprehensive regulations for electric bicycles, scooters, and...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Authorizes Land Buy for Grundy County Expansion, Secures Site in Morris

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees has authorized negotiations for a land acquisition to build a...
FAA funding problems hit airports in California, elsewhere

FAA funding problems hit airports in California, elsewhere

By Madeline ShannonThe Center Square As Christine Finch helped her father, Graham Finch, gather his luggage at the San Francisco International Airport, she was worried about how flight delays caused...
Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

By Jonathan Bilyk | Legal NewslineThe Center Square A Chicago federal judge has barred federal agents from U.S. Border Patrol and ICE from conducting crowd control actions anywhere in northern...
Report: IL public schools show low academic proficiency, higher taxpayer funding

Report: IL public schools show low academic proficiency, higher taxpayer funding

By Jim Talamonti | The Center SquareThe Center Square (The CEnter Square) – The latest education statistics indicate stagnant proficiency for public school students in Illinois, despite dramatic increases in...
Watchdog: Special interest group paid legislators’ $25,000 resort bill

Watchdog: Special interest group paid legislators’ $25,000 resort bill

By Elyse ApelThe Center Square A government watchdog group has filed ethics complaints against more than a dozen Democratic legislators in Colorado. Common Cause alleges the legislators had $25,000 in...
will county board graphic

Commission Grants Green Garden Solar Farm Project Variance Extension

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial...
Union Pacific to ask appeals court for biometrics lawsuit exemption

Union Pacific to ask appeals court for biometrics lawsuit exemption

By Jonathan Bilyk | Legal NewslineThe Center Square Though he has said he believes the company's position would lead to legally "absurd" results, a federal judge will still allow freight...