Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Thu Jun 4
Slight Chance Showers And Thunderstorms then Showers And Thunderstorms Likely
83° 66°

Slight Chance Showers And Thunderstorms then Showers And Thunderstorms Likely

💨 10 to 20 mph 💧 63%

Leave a Comment





Latest News Stories

WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Mokena Logo Graphic.5

Mokena Overhauls Zoning Code to Streamline Rules for Sheds, Pools, and Patios

The Mokena Village Board has unanimously approved a significant overhaul of its zoning regulations for accessory structures, a move aimed at making rules for items like sheds, decks, and pools...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Mokena Logo Graphic.6

Mokena Awards $472K Contract for Countryview Estates Storm Sewer Project

The Village of Mokena is moving forward with a major infrastructure project, awarding a contract worth over $472,000 to a local company for the Countryview Estates Storm Sewer Replacement Project....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Champaign-based Pavlov

Fiber Internet Provider Pavlov Media Details Plans to Expand into Mokena

Mokena residents may soon have another choice for high-speed internet service, as Champaign-based Pavlov Media has announced its intent to build a fiber optic network throughout the village. Mark Sheldon,...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Mokena Logo Graphic.1

Mokena Celebrates Successful July 4th Events, Honors Parade Winners

A celebratory atmosphere filled the Mokena Village Board meeting on July 14, as officials and community leaders recounted the success of the village's Independence Day festivities and honored the winners...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for July 14, 2025

The Mokena Village Board on July 14 approved a major overhaul of its zoning code, awarded a contract for a significant storm sewer project, and heard plans for a new...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO-Exec-Cmte-July-10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...