Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Today Jun 12
Mostly Sunny then Slight Chance Showers And Thunderstorms
87° 61°

Mostly Sunny then Slight Chance Showers And Thunderstorms

💨 15 mph 💧 17%

Leave a Comment





Latest News Stories

Committee-Land Use.Graphic

Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use and Development Committee voted against recommending a controversial solar farm proposal...
Screenshot 2026-02-22 at 5.06.42 PM

Trustees Renew Federal Lobbyist Contract Following $800,000 Funding Win

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board voted to renew its contract for federal lobbyist services on Wednesday. Administration and supporting...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Screenshot 2026-02-22 at 4.29.56 PM

Contracts Approved for New West Principal and District Technology Director

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board appointed Dr. Jennifer Killeen as the new Principal of Lincoln-Way West High School and Kyle...
mokena school district 159.2

Board Member Clashes with Colleagues Over Meeting Minutes and Bill Review Transparency

Mokena School District 159 Meeting | February 18, 2026 Article Summary: A disagreement over the level of detail included in meeting minutes and the sharing of questions regarding district bills sparked...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...
Screenshot 2026-02-22 at 5.06.42 PM

Board Approves New Chief of Staff and Dean Roles; Trustees Clash Over Hiring Transparency

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board approved the appointments of a new Chief of Staff and a Dean of Workforce...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
Screenshot 2026-02-22 at 4.29.56 PM

Board Approves $479,000 Wireless Network Overhaul to Replace Aging Tech

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board of Education approved a $479,526.96 contract with CDW to replace the indoor wireless access points...
mokena school district 159.3

Principals Present Mid-Year Data Showing Gains in Writing and Math Proficiency

Mokena School District 159 Meeting | February 18, 2026 Article Summary: Mokena School District 159 principals presented mid-year updates on their School Improvement Plans, highlighting data-driven gains in writing proficiency and...
Committee-Executive.Graphic

Executive Committee: Tension Rises as Republican Whip Removed from Panel

Will County Executive Committee Meeting | February 11, 2026 Article Summary: A dispute over committee appointments erupted when Republican leadership challenged the removal of Member Vince Logan from the Executive...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: County Stripped of Power to Regulate Motor Races, Must Drop Solicitor Fees Due to State Statutes

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee repealed county regulations regarding motor stunt events and removed...

Commission Overrides Staff Recommendation, Approves Manhattan Township Barn Expansion

Will County Planning and Zoning Commission Meeting | February 17, 2026 Article Summary: A Manhattan Township homeowner received unanimous approval for three variances to expand a pole barn, despite county...