Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Sat Jun 13
Chance Rain Showers then Mostly Sunny
73° 51°

Chance Rain Showers then Mostly Sunny

💨 10 to 15 mph 💧 33%

Leave a Comment





Latest News Stories

JJC Foundation Executive Director Retires Following $2.3 Million Estate Gift

Joliet Junior College Board Meeting | Dec. 10, 2025 Article Summary: Longtime Joliet Junior College Foundation Executive Director Kristi Mulvey announced her retirement at her final board meeting, capping a...
Screenshot 2025-12-20 at 12.25.51 PM

Lincoln-Way Board Approves $92.5 Million Tax Levy for 2025

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The Lincoln-Way Community High School District 210 Board of Education officially adopted a $92,522,000 tax levy during...
mokena school district 159.5

Mokena District 159 Board Approves 2025 Tax Levy Following Debate Over Fund Allocations

Mokena School District 159 Meeting | December 17, 2025 Article Summary: The Mokena School District 159 Board of Education on Wednesday, Dec. 17, 2025, approved a $22.5 million final tax...
Will County Board Graphic.04

Liquor License Amendments Approved for Frankfort, Joliet, and Lockport Businesses

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Executive Committee approved amendments to the County’s Liquor Control Ordinance to increase the number of available licenses,...
Planning & Zoning Graphic.3

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 16, 2025

Will County Planning and Zoning Commission Meeting | December 16, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission navigated attendance issues during its December 16, 2025, meeting, beginning...
Will County P&Z Logo Planning Zoning.2

Joliet Property Owner Cleared to Convert Non-Conforming Building into Two-Unit Residence

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: The Planning and Zoning Commission legalized the status of a Joliet residence that had previously contained four illegal...
Meeting Briefs

Meeting Summary and Briefs: Will County Committee of the Whole for Dec. 2025

Will County Committee of the Whole Meeting | December 2025 Overall Meeting SummaryThe Will County Board Committee of the Whole met on Tuesday, Dec. 9, 2025, for a series of...

JJC Board Approves 2025 Tax Levy and Bond Abatement

Joliet Junior College Board Meeting | Dec. 10, 2025 Article Summary: The Joliet Junior College Board of Trustees approved the 2025 tax levy and voted to abate taxes related to...
Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for Dec. 2025

Will County Land Use & Development Committee Meeting | December 2025 Overall Meeting SummaryThe Will County Land Use and Development Committee met on Thursday, Dec. 4, 2025, addressing a range...
Will County Board Graphic.03

Board Committee Approves Rate Hike for Private Pay Residents at Sunny Hill Nursing Home

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: To address operating deficits and rising costs, the Executive Committee approved a rate increase for private pay residents...
Meeting-Briefs

Meeting Summary and Briefs: Mokena Fire Protection District for Nov. 2025

Mokena Fire Protection District Meeting | Nov. 11, 2025 The Mokena Fire Protection District Board of Trustees met on Tuesday, November 11, 2025, to handle financial levies, facility maintenance, and...
(c)Eric Pancer

Pace Expands I-55 Service and Launches ‘VanGo’ in Joliet

Will County Committee of the Whole Meeting | December 2025 Article Summary: Pace officials highlighted service expansions in Will County, including the recent launch of the "VanGo" reservation-based van service...

Will County Speaker Praises JJC for ‘Heroes’ Scholarship Success

Joliet Junior College Board Meeting | Dec. 10, 2025 Article Summary: Will County Board Speaker Joe VanDuyne addressed the Joliet Junior College Board, commending the institution for its efficient handling...
Will County Board Graphic.01

Will County Executive Committee Rejects School Choice Advisory Referendum

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Will County Board Executive Committee voted against advancing a resolution that would have placed an advisory referendum...
mokena fire district #2 logo graphic.5

District Approves Station Repairs and Addresses Engine Issues

Mokena Fire Protection District Meeting | Nov. 11, 2025 Article Summary: The Mokena Fire Protection District Board authorized spending for facility repairs, including new flooring and door replacements at two stations....