Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Sat Jun 13
Chance Rain Showers then Mostly Sunny
73° 51°

Chance Rain Showers then Mostly Sunny

💨 10 to 15 mph 💧 33%

Leave a Comment





Latest News Stories

mokena fire district #2 logo graphic.5

Mokena Fire Station 2 Slated for Bunk Room Renovations

Mokena Fire Protection District Meeting | September 2025 Article Summary: The Mokena Fire Protection District is budgeting up to $35,000 to renovate the bunk rooms at Fire Station 2 on 191st...
Golf Cart

Mokena Enacts New Regulations for E-Bikes, Scooters, and Golf Carts

Village of Mokena Board of Trustees Meeting | October 27, 2025 Article Summary: The Mokena Village Board has passed a new ordinance establishing comprehensive regulations for electric bicycles, scooters, and...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Authorizes Land Buy for Grundy County Expansion, Secures Site in Morris

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees has authorized negotiations for a land acquisition to build a...
FAA funding problems hit airports in California, elsewhere

FAA funding problems hit airports in California, elsewhere

By Madeline ShannonThe Center Square As Christine Finch helped her father, Graham Finch, gather his luggage at the San Francisco International Airport, she was worried about how flight delays caused...
Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

By Jonathan Bilyk | Legal NewslineThe Center Square A Chicago federal judge has barred federal agents from U.S. Border Patrol and ICE from conducting crowd control actions anywhere in northern...
Report: IL public schools show low academic proficiency, higher taxpayer funding

Report: IL public schools show low academic proficiency, higher taxpayer funding

By Jim Talamonti | The Center SquareThe Center Square (The CEnter Square) – The latest education statistics indicate stagnant proficiency for public school students in Illinois, despite dramatic increases in...
Watchdog: Special interest group paid legislators’ $25,000 resort bill

Watchdog: Special interest group paid legislators’ $25,000 resort bill

By Elyse ApelThe Center Square A government watchdog group has filed ethics complaints against more than a dozen Democratic legislators in Colorado. Common Cause alleges the legislators had $25,000 in...
will county board graphic

Commission Grants Green Garden Solar Farm Project Variance Extension

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial...
Union Pacific to ask appeals court for biometrics lawsuit exemption

Union Pacific to ask appeals court for biometrics lawsuit exemption

By Jonathan Bilyk | Legal NewslineThe Center Square Though he has said he believes the company's position would lead to legally "absurd" results, a federal judge will still allow freight...