Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Today Jun 12
Mostly Sunny then Slight Chance Showers And Thunderstorms
87° 61°

Mostly Sunny then Slight Chance Showers And Thunderstorms

💨 15 mph 💧 17%

Leave a Comment





Latest News Stories

mokena library logo graphic.4

Mokena Library Holds Public Hearing on Budget & Appropriation Ordinance

Article SummaryThe Mokena Community Public Library District Board of Trustees conducted its legally required public hearing for the 2025-2026 Budget and Appropriation Ordinance during a special meeting on August 26....
Meeting-Briefs

Meeting Summary and Briefs: Mokena Fire Protection District for August 2025

Mokena Fire Protection District Meeting | August 2025 The Mokena Fire Protection District Board of Trustees on Tuesday, August 12, 2025, focused on fleet management, approving the final payment for...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 15, 2025

Mokena Village Board Meeting | September 15, 2025 The Mokena Village Board held a special meeting on Monday, September 15, 2025, where its primary action was the unanimous approval of...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Mokena Logo Graphic.5

Mokena Board Approves Final Plat for 50-Home Boulder Ridge Phase IV Subdivision

Mokena Village Board Meeting | September 15, 2025 Article Summary: The Mokena Village Board approved the final plat for the 50-lot fourth phase of the Boulder Ridge subdivision, clearing the way...
mokena fire protection district logo graphic.3

Mokena Fire District Hiring, Deploys Drone to Assist Frankfort in Crisis

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is in the process of hiring a new firefighter/paramedic after receiving 11 applications for a vacant...
Joliet-Junior-college.-Graphic-Logo.3

JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees passed a controversial policy change allowing the student trustee to be counted...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 8, 2025

Mokena Village Board Meeting | September 8, 2025 The Mokena Village Board on Monday, September 8, 2025, unanimously approved a major overhaul of its police ticketing system, raising fines for...
Mokena Logo Graphic.5

Mokena Board Greenlights Boulder Ridge Development Settlement

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board has approved a settlement agreement involving the developer of the Boulder Ridge subdivision, resolving outstanding issues and...
mokena fire district #2 logo graphic.5

Mokena Fire District Invests in New Inventory System for $5,500 Annually

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is upgrading its internal operations by purchasing a new inventory management system called PSTrax. The board...
Mokena Logo Graphic.1

Mokena Appoints Jacob Hazek as New Village Arborist

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board has appointed Jacob Hazek to the position of Arborist within the Public Works Department. Hazek was selected...
Joliet-Junior-college.-Graphic-Logo.2

Joliet Junior College, City of Joliet to Explore Joint Public Safety Institute

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved an intergovernmental agreement with the City of Joliet to begin...
Mokena Logo Graphic.2

Mokena Awards Nearly $300,000 in Contracts for Road Maintenance and Project Oversight

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board approved two contracts totaling over $292,000 for its Fiscal Year 2026 street improvement and maintenance programs. The...
Mokena Logo Graphic.6

Mokena Board Approves Sweeping Increases to Police Ticket Fines

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board unanimously approved a new ordinance that significantly increases fines for a wide range of non-traffic municipal code...
mokena fire protection district logo graphic.4

Mokena Fire District Adds New Ambulance, Addresses $18,000 in Fleet Repairs

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is preparing to put a new ambulance into service by the end of August after completing...