Will County Board Unanimously Rejects Controversial Solar Farm in Troy Township

Spread the love

Will County Board Meeting | February 19, 2026

Article Summary: The Will County Board unanimously rejected a special use permit for a commercial solar energy facility near Shorewood following strong opposition from local municipalities and taxing bodies. The denial followed public comments highlighting safety concerns at a nearby intersection and conflicts with local development plans.

Pivot Energy Solar Proposal Key Points:

  • Location: 58.067 acres at 26347 W. Baltz Road, Joliet (Troy Township), near the intersection of County Line Road and Route 52.

  • Project Details: Proposed 8 MW co-located solar energy arrays (Pivot Energy IL 62 LLC and Pivot Energy IL 62b LLC).

  • Opposition: 10 taxing bodies objected, including the Village of Shorewood, City of Joliet, Troy Fire Protection District, and Troy School District 30-C.

  • Result: The County Board voted 0-19 to deny the permit, resulting in the failure of the motion.

The Will County Board on Thursday, February 19, 2026, unanimously rejected a proposal by Pivot Energy to construct a commercial solar energy facility on approximately 58 acres of agricultural land in Troy Township.

The proposal, located at the intersection of County Line Road and Baltz Road, sought a special use permit to construct two co-located solar arrays. While the Will County Land Use and Development Committee had previously forwarded the petition with a recommendation for denial, the full board delivered the final rejection in a 0-19 vote.

Prior to the vote, representatives for Pivot Energy addressed the board, highlighting efforts to mitigate community concerns. Pivot Energy representative Brittney Krebsbach noted that the company had offered a “healthy impact mitigation package” to the Village of Shorewood.

“We shortened the project lifespan almost by half from 40 years to 25 to free up that land sooner,” Krebsbach told the board. She added that the package included pre-annexation agreements and an estimated $350,000 increase in first-year tax revenue for local bodies.

Attorney Jim Griffin, representing Pivot Energy, argued that the project met all county and statewide siting standards. He reminded the board of Illinois Supreme Court precedent regarding comprehensive plans.

“Incompatibility with a comprehensive plan is not a basis to deny a special use for a project,” Griffin stated, urging the board to approve the measure with the 25-year lifespan condition.

However, the proposal faced a coalition of opposition from local officials. Shorewood Mayor C.C. DeBold spoke during public comment, emphasizing that the village’s objection was based on siting rather than opposition to green energy.

“The proposal of this project, Route 52 and County Line Road, has already been deemed a dangerous intersection,” DeBold said. “We’re currently working with IDOT to improve this into a roundabout. Matter of fact, we had an accident there two days ago.”

DeBold listed ten objections filed against the project from entities including the City of Joliet, Troy Township, Troy Fire Protection District, Minooka Community High School, and the Grand Prairie Water Commission. He noted that the site is directly across the street from the village’s corporate limits and argued it would negatively impact future residential and commercial growth.

Land Use Committee Chair Frankie Pretzel (R-New Lenox) initiated the motion to deny the request, citing the area’s readiness for other types of development.

“This portion of the county is ripe for development of residential. It’s literally knocking on the door there,” Pretzel said. “To tie that up for 25 years with the solar project would be detrimental to not only Shorewood, but to Will County.”

Board Member Katie Deane-Schlottman (R-Joliet), who represents the district where the project is located, echoed the opposition. “I know this area very, very well and I know the residents in this area do not want this here,” she said.

Following the discussion, the board voted 19-0 against the measure, effectively killing the proposal. Two related variances regarding ground cover height and mowing frequency were also denied.

Today Jun 12
Mostly Sunny then Slight Chance Showers And Thunderstorms
87° 61°

Mostly Sunny then Slight Chance Showers And Thunderstorms

💨 15 mph 💧 17%

Leave a Comment





Latest News Stories

mokena library logo graphic.4

Mokena Library Holds Public Hearing on Budget & Appropriation Ordinance

Article SummaryThe Mokena Community Public Library District Board of Trustees conducted its legally required public hearing for the 2025-2026 Budget and Appropriation Ordinance during a special meeting on August 26....
Meeting-Briefs

Meeting Summary and Briefs: Mokena Fire Protection District for August 2025

Mokena Fire Protection District Meeting | August 2025 The Mokena Fire Protection District Board of Trustees on Tuesday, August 12, 2025, focused on fleet management, approving the final payment for...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 15, 2025

Mokena Village Board Meeting | September 15, 2025 The Mokena Village Board held a special meeting on Monday, September 15, 2025, where its primary action was the unanimous approval of...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Mokena Logo Graphic.5

Mokena Board Approves Final Plat for 50-Home Boulder Ridge Phase IV Subdivision

Mokena Village Board Meeting | September 15, 2025 Article Summary: The Mokena Village Board approved the final plat for the 50-lot fourth phase of the Boulder Ridge subdivision, clearing the way...
mokena fire protection district logo graphic.3

Mokena Fire District Hiring, Deploys Drone to Assist Frankfort in Crisis

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is in the process of hiring a new firefighter/paramedic after receiving 11 applications for a vacant...
Joliet-Junior-college.-Graphic-Logo.3

JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees passed a controversial policy change allowing the student trustee to be counted...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for September 8, 2025

Mokena Village Board Meeting | September 8, 2025 The Mokena Village Board on Monday, September 8, 2025, unanimously approved a major overhaul of its police ticketing system, raising fines for...
Mokena Logo Graphic.5

Mokena Board Greenlights Boulder Ridge Development Settlement

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board has approved a settlement agreement involving the developer of the Boulder Ridge subdivision, resolving outstanding issues and...
mokena fire district #2 logo graphic.5

Mokena Fire District Invests in New Inventory System for $5,500 Annually

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is upgrading its internal operations by purchasing a new inventory management system called PSTrax. The board...
Mokena Logo Graphic.1

Mokena Appoints Jacob Hazek as New Village Arborist

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board has appointed Jacob Hazek to the position of Arborist within the Public Works Department. Hazek was selected...
Joliet-Junior-college.-Graphic-Logo.2

Joliet Junior College, City of Joliet to Explore Joint Public Safety Institute

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved an intergovernmental agreement with the City of Joliet to begin...
Mokena Logo Graphic.2

Mokena Awards Nearly $300,000 in Contracts for Road Maintenance and Project Oversight

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board approved two contracts totaling over $292,000 for its Fiscal Year 2026 street improvement and maintenance programs. The...
Mokena Logo Graphic.6

Mokena Board Approves Sweeping Increases to Police Ticket Fines

Mokena Village Board Meeting | September 8, 2025 Article Summary: The Mokena Village Board unanimously approved a new ordinance that significantly increases fines for a wide range of non-traffic municipal code...
mokena fire protection district logo graphic.4

Mokena Fire District Adds New Ambulance, Addresses $18,000 in Fleet Repairs

Mokena Fire Protection District Meeting | August 2025 Article Summary: The Mokena Fire Protection District is preparing to put a new ambulance into service by the end of August after completing...