lincoln way school district 210 logo.2

Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | March 19, 2026

Article Summary: The Board of Education approved a $1.98 million contract with CDW/Greatline Solutions to upgrade aging wired infrastructure at the Central and East campuses to support modern technology and faster network speeds.

Cabling Upgrade Key Points:

  • A contract for a total cost of $1,982,901.00 was awarded to CDW/Greatline Solutions.

  • The project replaces 20-to-25-year-old CAT 5e cabling with CAT 6A, supporting up to 10 gigabits per second.

  • The district anticipates receiving $480,000 in reimbursements through the federal E-Rate program.

  • The new cabling comes with a 25-year manufacturer warranty.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, March 19, 2026, unanimously approved a contract for a total cost of $1,982,901.00 with CDW/Greatline Solutions for a district-wide wired infrastructure upgrade.

The district issued a Request for Proposals (RFP) in January 2026 to upgrade components of its wired infrastructure through the federal E-Rate process. According to Director of Technology Cheryl Kay, much of the existing cabling at Lincoln-Way Central and East is 20 to 25 years old. The older CAT 5 and CAT 5e cabling standards do not support the faster speed capabilities of modern switching and wireless equipment recently purchased by the district.

“To put this into perspective for you, CAT 5e cabling supports speeds up to 1 gigabit per second, while CAT 6A cabling can support speeds up to 10 gigabits per second,” Kay explained to the Board. “I’ve used the garden hose versus the fire hose analogy in the past. So essentially, the new cabling allows more data to move through the network at one time.”

The upgraded infrastructure will also establish a foundation for future technology projects, including IP communication systems, digital signage, emergency alerting, and intercom systems that are nearing the end of their usable life.

The district received three proposals. While Netsource Solutions submitted a lower bid of $1,885,001.00, the district rejected it because the company only had 25 total employees. Kay noted that the district had significant concerns about a company of that size being able to complete the massive scope of work on time across multiple buildings. CDW/Greatline, a vendor the district has successfully used for past fiber projects, was selected instead.

The project is included in the district’s 5-year technology plan. Because a significant portion of the work qualifies for E-Rate reimbursements, the district anticipates receiving roughly $480,000 back after the project is completed. The installation work will be completed between April 1, 2026, and September 30, 2027, working around the district’s upcoming HVAC construction schedule.

Leave a Comment





Latest News Stories

Will County P&Z Logo Planning Zoning.2

Will County P&Z Grants Variances for Unpermitted Structures in Crete and Manhattan

Will County P&Z Commission Meeting | Jan. 20, 2026 Article Summary: The Planning and Zoning Commission approved variances for property owners in Crete and Manhattan who built agricultural structures without...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Landfill Committee for Jan. 13, 2026

Will County Landfill Committee Meeting | Jan. 13, 2026 The Will County Board Landfill Committee met on Tuesday, January 13, 2026, to address operational improvements at the Prairie View Landfill...
Scam Alert Grahpic

Monee Police warn residents of phone scammers impersonating officers

MONEE, Ill. – The Monee Police Department issued a community alert this week regarding a resurgence of telephone scams in which fraudsters are impersonating police officers to solicit money from residents....
Will County P&Z Logo Planning Zoning

Will County P&Z Approves Mokena Scrap Drop-Off Despite Municipal Objections

Will County P&Z Commission Meeting | Jan. 20, 2026 Article Summary: The Will County Planning and Zoning Commission granted a special use permit for an outdoor recyclable material drop-off facility...
solar panels photovoltaics in solar farm

Will County Braces for 6,000-Acre Solar Project; Prepare for ‘Massive’ Solar Hearings

Will County P&Z Commission Meeting | Jan. 20, 2026 Will County Braces for 6,000-Acre Solar Project; Commissioners Weigh Conflicts and Crowds Article Summary:The Will County Planning and Zoning Commission is...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board for January 15, 2026

Will County Board Meeting | January 15, 2026 Meeting SummaryThe Will County Board met on January 15, 2026, to tackle a heavy agenda focused on infrastructure investment, legislative policy, and...
Police Crime

Pursuit following railroad theft ends in New Lenox; one suspect at large

NEW LENOX, Ill. – A reported cargo theft in Wilmington Township sparked a multi-jurisdictional pursuit Saturday morning that ended with a crash and a manhunt in a New Lenox neighborhood. The...
Will County Board Graphic.04

Waste Management Commits to Expanded Litter Patrols Around Landfill

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: Following complaints from county officials, Waste Management has agreed to significantly expand its litter collection efforts along roadways surrounding...
Meeting Briefs

Meeting Summary and Briefs: Mokena School District 159 for January 21, 2026

Mokena School District 159 Meeting | January 21, 2026 Overall Meeting SummaryThe Mokena School District 159 Board of Education met on Wednesday, January 21, 2026, addressing a mix of student...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for Jan. 13, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, January 13, 2026, to continue its comprehensive update...
Will County Board Graphic.01

County Approves $22 Million in Road Projects for Lorenzo Road and Mills Road

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved major infrastructure contracts, including an $18.8 million bridge replacement on Lorenzo Road and a $3.2...
Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Will County Landfill Committee Meeting | Jan. 13, 2026 Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable...
mokena school district 159.5

Fifth Graders Honored for DARE Essays on Decision Making

Mokena School District 159 Meeting | January 21, 2026 Article Summary: Two fifth-grade students were spotlighted at the Mokena School District 159 Board meeting for their winning essays on the...
Will County Board Graphic.03

Ad-Hoc Committee Retains Noise Ordinance Despite Enforcement Frustrations

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Ad-Hoc Ordinance Review Committee voted to retain the county’s public nuisance noise ordinance despite members describing...
Will County Board Graphic.03

Will County Commits $15M to Transfer Sanitary District Operations to City of Joliet

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board has authorized an intergovernmental agreement to dissolve the Southeast Joliet Sanitary District and transfer its water...