Lincoln-Way 210 Advances Summer Site Improvements and Asbestos Abatement Projects

Spread the love

Lincoln-Way Community High School District 210 Meeting | March 19, 2026

Article Summary: The Board of Education approved an asbestos abatement contract and initial site improvement bids to prepare for a massive $30 million HVAC overhaul and complete scheduled campus upgrades.

Site Improvements Key Points:

  • NES, Inc. was awarded a $38,000 contract for asbestos abatement at Lincoln-Way Central.

  • Henry Brothers was approved for the base bid and alternates 1-5 for summer site improvements.

  • Turf selection for an auxiliary field was postponed until April to utilize purchasing cooperatives.

Preparing for a massive $30 million HVAC overhaul and various summer maintenance projects, the Lincoln-Way Community High School District 210 Board of Education on Thursday, March 19, 2026, approved an asbestos abatement contract and initial site improvement bids.

The district will complete approximately $30,000,000 in HVAC improvements at the Lincoln-Way Central and East campuses during the summers of 2026 and 2027. To prepare for this work, the district must ensure that any ceiling tiles or materials disturbed by the HVAC updates are clear of asbestos. According to a memo from Director of Buildings & Grounds Chuck Welke and Assistant Superintendent Michael J. Duback, a small section of abatement work is needed at Lincoln-Way Central.

The Board awarded the asbestos abatement contract to the lowest responsive bidder, NES, Inc., for a total cost of $38,000. The cost will be covered by life safety contingencies and the operating budget. The abatement work is scheduled to take place over spring break when students are out of the building, allowing HVAC contractors to begin their preparatory work in April and May.

In a separate vote, the Board advanced its annual summer site improvements, which typically encompass $4 million to $6 million worth of non-HVAC work. The Board approved the base bid and alternates one through five from Henry Brothers. The approved work includes tennis courts at Lincoln-Way West, concrete and paving work at the transportation center, field events behind the stadium at Lincoln-Way East, and parking expansions.

However, the Board held off on approving alternates six, seven, and eight, which related to different turf options for an auxiliary field. Duback explained that pricing clarifications with manufacturers prompted the district to pause on the turf selection. The district plans to explore purchasing the turf material directly through a cooperative to increase efficiency and will bring a product recommendation back to the Board in April.

Both the asbestos abatement contract and the site improvement bids passed in 5-0 split votes, with Board Secretary Deadra W. Stokes abstaining from both items.

Leave a Comment





Latest News Stories

Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...
will county Committee-Legislative.Graphic

Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts

Legislative Committee Meeting | March 2026 Article Summary: The Will County Legislative Committee unanimously approved a resolution supporting a state legislative push to increase the Local Health Protection Grant by $10...
Monee Fire

Barn Fire on Whispering Hills Lane Claims Livestock, Draws Extensive Mutual Aid Response

Article Summary: A massive late-night structure fire completely destroyed a 60-by-60-foot wood frame barn on Whispering Hills Lane, resulting in the loss of 15 animals but no human injuries. Firefighters from...
Will County Board Graphic.01

Will County Public Works Committee Shelves License Plate Reader Agreement Amid Bipartisan Privacy Concerns

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee abruptly removed an agreement with the Illinois State Police...
Will County P&Z Logo Planning Zoning.2

Will County Planning and Zoning Commission Overrides Staff to Approve New Lenox Accessory Building Variance

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission voted to override a staff recommendation of denial, approving a...
sheriff dog

Will County Sheriff’s Office Welcomes Remi, First Electronic Scent Detection Dog

Article Summary: The Will County Sheriff’s Office announced the addition of Remi, a Labrador serving as the department's first Electronic Scent Detection dog. The newly trained K9 will assist investigators...
Will County Public Works Committee

Will County Transportation Department Announces Open House for Manhattan-Monee Road Expansion

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Division of Transportation is inviting residents to a public open house on March 19...