will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities that will serve both a new residential subdivision and the upcoming Laraway Road widening project.

Laraway Road / LNS Development Key Points:

  • Will County and LNS Development Group, LLC will co-fund shared stormwater infrastructure.

  • The county will pay an estimated $332,209.92 for its share of the detention facility and storm sewer upgrades.

  • The county is also paying LNS Development $19,862.03 to acquire 0.43 acres of right-of-way required for the Laraway Road widening project.

  • The Laraway Road project will widen the highway to four lanes between Cedar Road and Spencer Road.

Will County is leveraging private development to streamline its own infrastructure costs, approving an agreement with LNS Development Group, LLC on Tuesday, April 7, 2026, to construct shared stormwater facilities along Laraway Road in New Lenox.

The agreement centers on a parcel of land (PIN 15-08-35-100-011) where LNS Development is planning a new residential subdivision. Concurrently, Will County is engineering a major capacity project to widen Laraway Road (County Highway 74) from a two-lane road to a four-lane highway with a center barrier median from Cedar Road to Spencer Road.

Because both the county’s highway expansion and the private residential development require significant stormwater management, the two entities agreed to co-locate and share the costs of a detention facility and upgraded storm sewers on the developer’s parcel.

According to the engineer’s estimates provided in the agenda packet, Will County’s financial obligation for the construction of the shared improvements is capped at an estimated $332,209.92. This breaks down to $179,218.92 (21% of the total cost) for the detention basin, and $152,991.00 (100% of the required upgrades) to properly size the storm sewers to accommodate WCDOT drainage. LNS Development will cover the remaining construction costs.

Furthermore, the agreement secures the land Will County needs to physically widen the road. LNS Development will convey 0.43668 acres of right-of-way to the county in exchange for $19,862.03. In return, the county guarantees the developer’s vested rights to specific access points and drainage capacity along the newly widened highway.

The measure was passed unanimously and advances to the full County Board.

⚠️ Tornado Watch issued June 11 at 2:02PM CDT until June 11 at 9:00PM CDT by NWS Chicago IL
⚠️ Flood Watch issued June 11 at 12:39PM CDT until June 11 at 11:00PM CDT by NWS Chicago IL
Thu Jun 11
Sunny
79° 60°

Sunny

💨 10 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

Trump says US troops will get paid Oct. 15 despite funding lapse

Trump says US troops will get paid Oct. 15 despite funding lapse

By Brett RowlandThe Center Square President Donald Trump said Saturday that America's 1.3 million military service members will get paid on Oct. 15 despite a congressional budget lapse that led...
$4.5B awarded in new contracts to build Smart Wall along southwest border

$4.5B awarded in new contracts to build Smart Wall along southwest border

By Bethany BlankleyThe Center Square Roughly $4.5 billion in contracts have been awarded to expand border wall construction, including adding advanced technological surveillance along the southwest border. Ten new construction...
Do No Harm expects FTC to take action to protect minors from transgender procedures

Do No Harm expects FTC to take action to protect minors from transgender procedures

By Tate MillerThe Center Square (The Center Square ) – After submitting comments to the Federal Trade Commission's public inquiry on how the child transgender industry has harmed and deceived...
2024 was deadliest year for journalists on record

2024 was deadliest year for journalists on record

By Bethany BlankleyThe Center Square Last year was the deadliest year for journalists on record, with the Gaza Strip being the deadliest location, according to multiple reports. Totals vary depending...
Govt shutdown raises concerns over national security

Govt shutdown raises concerns over national security

By Andrew RiceThe Center Square As partisan divides appear to deepen and prolong the partial government shutdown, bipartisan lawmakers said they are concerned about national security effects of the funding...
Ex-speaker Madigan to begin 7.5-year prison sentence Monday

Ex-speaker Madigan to begin 7.5-year prison sentence Monday

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – One day before the Illinois General Assembly’s fall veto session is scheduled to begin, one of the...
Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Will County Finance Committee Meeting October 7, 2025 Article Summary: Will County's Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the...
Screenshot 2025-10-10 at 11.36.47 AM

Will County to Draft First-Ever Policy on Artificial Intelligence Use

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: The Will County Board's Capital Improvements & IT Committee has initiated the process of drafting a comprehensive...
Screenshot 2025-10-10 at 11.20.18 AM

Will County Sees 50% Drop in Opioid Deaths, But Alarming Rise in Suicides

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is experiencing a dramatic 50% reduction in opioid overdose deaths compared to last year, a...
Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
Trump says new 100% tariff on China as trade war escalates

Trump says new 100% tariff on China as trade war escalates

By Brett RowlandThe Center Square President Donald Trump on Friday said imports from China will face a new 100% tariff "over and above" existing import taxes on the world's second-largest...
Arizona congressman calls for end to government shutdown

Arizona congressman calls for end to government shutdown

By Chris WoodwardThe Center Square U.S. Rep. Abe Hamadeh, R-Arizona, wants Democrats to “come to their senses” and end the government shutdown. Hamadeh told The Center Square that Democrats’ reasons...

WATCH: Pritzker continues encouraging ICE protests after Guard blocked

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – With the National Guard’s deployment in Illinois for public safety blocked by a federal judge, Gov. J.B....
Illinois quick hits: Ag incentives announced; Cook County announces increased budget

Illinois quick hits: Ag incentives announced; Cook County announces increased budget

By Jim Talamonti | The Center SquareThe Center Square Ag incentives announced The Illinois Environmental Protection Agency and the Illinois Department of Agriculture have announced $67 million in funding to...