Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Today Jun 4
Chance Showers And Thunderstorms
68°

Chance Showers And Thunderstorms

Leave a Comment





Latest News Stories

Net negative migration is harmful to the economy, economists say

Net negative migration is harmful to the economy, economists say

By Morgan SweeneyThe Center Square Though the economy and immigration were issues that helped President Donald Trump secure the White House, some economists have said that too steep a decline...
Details pending on billions in foreign investments coming from trade deals

Details pending on billions in foreign investments coming from trade deals

By Brett RowlandThe Center Square When President Donald Trump announced a string of trade deals with key U.S. trading partners recently, he touted pledges for billions of dollars in U.S....
WCO-Finance-Aug-5.1

Will County Health Department Seeks $1 Million to Avert ‘Drastic’ Service Cuts from Expiring Grants

ARTICLE SUMMARY: The Will County Health Department is requesting an additional $1 million in county funding for its 2026 budget to prevent the elimination of 11 critical staff positions, warning...
WCO-Cap-Imp-8.5.1

Will County’s “First-in-Nation” Veterans Center to House Workforce Services, Sparking Debate

ARTICLE SUMMARY: The new Will County Veteran's Assistance & Support Center will also become the home for the county's Workforce Services department, a move officials say will save approximately $250,000 in...
WCO-Finance-Aug-5.2

Improved Vendor Service Creates $1.2 Million Shortfall in Sheriff’s Medical Budget

ARTICLE SUMMARY: The Will County Sheriff’s Office is facing a more than $1.2 million shortfall in its budget for inmate medical services, a problem officials attribute to an ironic cause:...
WCO-PZ-Aug-5.1

Will County Public Works Committee Unveils 25-Year Transportation Plan, Projects $258 Million Gap

ARTICLE SUMMARY: Will County officials have presented "Our Way Forward 2050," a new long-range transportation plan that provides a 25-year vision for infrastructure projects while forecasting a $258 million shortfall in...
WCO-Public-Safety.4

Will County Animal Protection Services Seeks New Facility Amid “Gaping Wound” of Space Crisis

Article Summary: Will County Animal Protection Services is seeking approval for a new facility, telling a county committee that its current building is critically inadequate for housing animals, leading to...
WCO-Cap-Imp-8.5.2

Board Confronts Animal Services Crowding, Explores Future Facility Options

ARTICLE SUMMARY: Will County officials are grappling with an ongoing animal housing crisis that has overwhelmed the county’s Animal Protective Services facility, prompting discussions about expansion, new construction, or even repurposing...
WCO-Finance-Aug-5.3

Will County Board Members Demand Transparency in Cannabis Tax Fund Allocation

ARTICLE SUMMARY: A debate over transparency and process erupted at the Will County Board’s Finance Committee meeting regarding the distribution of local cannabis tax revenue. Board members called for more...
WCO-PZ-Aug-5.2

Homer Glenn Residents Push Back on 143rd Street Widening as Officials Signal “Tentative Agreement”

ARTICLE SUMMARY: A Homer Glenn farm owner voiced strong opposition to the planned widening of 143rd Street during a county meeting, while committee members indicated a "tentative agreement" is in the...
WCO-LEG-8.5.1

Will County Forges 2026 Federal Agenda Amid D.C. Policy Shifts, ‘Big Beautiful Bill’ Impacts

ARTICLE SUMMARY: The Will County Board's Legislative Committee is reshaping its federal priorities for 2026, adding new language on environmental justice and LGBTQIA+ rights while creating a more transparent process for...
WCO-Public-Safety.3

Health Department Seeks $1 Million Levy Increase to Prevent “Weakened System”

Article Summary: The Will County Health Department is asking for a $1 million increase to its property tax levy to save 11 critical jobs that are at risk as post-pandemic...
WCO-Cap-Imp-8.5.3

County Rolls Out New “OneMeeting” Software to Improve Public Access

ARTICLE SUMMARY: Will County has officially launched a new agenda and meeting management software called "OneMeeting," aimed at improving transparency and making it easier for the public and officials to access...
Meeting-Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for August 5, 2025

The Will County Board’s Finance Committee confronted major budget challenges during its Tuesday meeting, led by a stark presentation from the Will County Health Department. Health officials are requesting an...
WCO-PZ-8.12.2

Will County PZC Approves Rezoning for Truck Repair Facility on Manhattan Road Amid Resident Concerns

Article Summary: The Will County Planning and Zoning Commission voted 4-2 to rezone nearly 14 acres in Joliet Township for a truck repair facility. The approval came after a neighboring...