Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

⚠️ Special Weather Statement issued June 4 at 4:25AM CDT by NWS Chicago IL
Today Jun 3
Mostly Sunny
87° 66°

Mostly Sunny

💨 5 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

Meeting-Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
frankfort-park-district

Meeting Briefs: Frankfort Park District Board for June 10, 2025

The Frankfort Park District Board of Commissioners discussed a legal dispute with the Five Oaks homeowners association over park development rules at its Tuesday meeting. Executive Director Gina Hassett reported...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will-County-Land-Use-July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...
Will-County-Land-Use-July3.2

Residents Allege Health Crises, Violations from Peotone Grain Facility

Two residents of unincorporated Peotone delivered emotional testimony to the Will County Land Use and Development Committee Thursday, alleging that a neighboring grain facility is causing severe health problems and...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department May Seek Property Tax Increase to Maintain Critical Services

The Will County Health Department is grappling with significant budget shortfalls as multiple federal grants have been terminated or reduced, potentially forcing the agency to seek additional property tax revenue...
Will-County-Land-Use-July-3.1

Crete Township Solar Project Approved Despite Township Objections

A 21-acre commercial solar project in Crete Township received a favorable recommendation from the Will County Land Use and Development Committee on Thursday, despite an official objection from the township....
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Opens Second Breast Milk Depot in Bolingbrook

The Will County Health Department has opened its second breast milk depot in partnership with Mother's Milk Bank of the Western Great Lakes, expanding access to donated breast milk for...
Will-County-Land-Use-July3.2

Lockport Township Solar Farm Gains Committee Approval

The Will County Land Use and Development Committee on Thursday approved a special use permit for a 25-acre commercial solar energy facility in Lockport Township. The project, proposed by Daniel...
Will-County-Public-Health-Safety-Committee-Meeting-July-3-2025

Health Department Plans Back-to-School Fair July 12

The Will County Health Department will host a Back-to-School Health Fair Saturday, July 12, from 10 a.m. to 2 p.m. at the Community Health Center, 1106 Neal Ave., Joliet. The...
Meeting-Briefs

Meeting Briefs: Will County Land Use & Development Committee for July 3, 2025

Green Garden Township Rezoning for Future Subdivision ApprovedThe committee recommended approval of a map amendment for an 81-acre property on South 88th Avenue in Green Garden Township. The applicant, represented...
Meeting-Briefs

Will County Public Health & Safety Committee July 3 Meeting Briefs

Grain Dust Complaint Prompts Investigation: Will County resident Tracy Henning of unincorporated Peotone addressed the committee about health problems she attributes to grain dust from a neighboring facility. Henning, who...
Will-County-Legislative-Committee-Meeting-July-1-2025

Will County Seeks Asian Carp Provision in Federal Legislative Agenda

Will County Board member Julie Berkowicz is pushing to add specific language addressing Asian carp invasion to the county's federal legislative agenda, citing the ongoing threat to local waterways as...
Will-County-Legislative-Committee-Meeting-July-1-2025

State Legislative Session Update: Transit, Energy Bills Stall Despite Democratic Control

Illinois lawmakers failed to advance major transit funding and comprehensive energy legislation during the recently concluded spring session, leaving key issues unresolved despite Democratic supermajorities in both chambers, according to...
Will-County-Capital-Improvements-IT-Committee-Meeting-July-1-2025

Will County’s Major Capital Projects Hit Key Milestones, VAC Buildout on “Aggressive Schedule”

Will County is making significant headway on several major capital improvement projects, with the new Veterans Assistance Commission (VAC) & Support Center in Joliet on an “aggressive schedule” for a...