Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Tue Jun 9
Showers And Thunderstorms Likely
91° 72°

Showers And Thunderstorms Likely

💨 5 to 20 mph 💧 65%

Leave a Comment





Latest News Stories

Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Screenshot 2026-02-22 at 5.06.42 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for February 18, 2026

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Meeting SummaryThe Joliet Junior College Board of Trustees met on Wednesday, February 18, 2026, for a regular meeting dominated...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...
Screenshot 2026-02-22 at 4.29.56 PM

Advisory Committee Debates Rigor of Online Summer School Options

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The District 210 Advisory Committee reported on discussions regarding the potential expansion of online summer school offerings,...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
mokena school district 159.5

Elementary PE Teacher Recognized for Raising Over Half a Million Dollars for Heart Health

Mokena School District 159 Meeting | February 18, 2026 Article Summary: Mokena Elementary School PE teacher Steve Hippleheuser was honored for 21 years of service to the American Heart Association, having...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Bath House Regulations Updated; Removes 60-Day Licensing Window

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to the regulations governing bath houses and...
Committee-Land Use.Graphic

Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use and Development Committee voted against recommending a controversial solar farm proposal...
Screenshot 2026-02-22 at 5.06.42 PM

Trustees Renew Federal Lobbyist Contract Following $800,000 Funding Win

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board voted to renew its contract for federal lobbyist services on Wednesday. Administration and supporting...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Screenshot 2026-02-22 at 4.29.56 PM

Contracts Approved for New West Principal and District Technology Director

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board appointed Dr. Jennifer Killeen as the new Principal of Lincoln-Way West High School and Kyle...
mokena school district 159.2

Board Member Clashes with Colleagues Over Meeting Minutes and Bill Review Transparency

Mokena School District 159 Meeting | February 18, 2026 Article Summary: A disagreement over the level of detail included in meeting minutes and the sharing of questions regarding district bills sparked...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...