Will County P&Z Commission Grants Extensions for Joliet Township Solar Farm Ground Cover

Spread the love

Will County Planning and Zoning Commission Meeting | April 7, 2026

Article Summary: The Will County Planning and Zoning Commission unanimously granted a final deadline extension for a commercial solar developer in Joliet Township, giving the company until September 2026 to plant specialized native pollinator ground cover beneath its solar arrays.

Joliet Solar Farm Key Points:

  • Nexamp Solar, operating as Moon Shoal Renewables and Summer Stone Renewables, requested Variance Extensions #VEXT-26-001 and #VEXT-26-002.

  • The extensions apply to previously approved variances that reduced required mowing from five times a year to one time, and increased maximum plant height from 13 inches to 36 inches.

  • The extensions were necessary because the property’s farmer planted traditional crops last season, preventing the solar developer from seeding the required native pollinators before the original variance expired.

On Tuesday, April 7, 2026, the Will County Planning and Zoning Commission granted a final round of variance extensions to Nexamp Solar, ensuring the developer has the legal runway to establish native pollinator habitats at its forthcoming commercial solar facilities in Joliet Township.

The developer is currently permitting two 5-megawatt commercial solar facilities, operating under the names Moon Shoal Renewables LLC and Summer Stone Renewables LLC. The projects are located near 2618 S. Chicago Street and W. Schweitzer Road, just west of the Chicagoland Speedway.

In October 2024, the commission approved special use permits for the facilities alongside specific variances regarding ground cover. To participate in the Illinois Pollinator-Friendly Solar Site Act and create deep-rooted habitats that manage stormwater, the developer required variances to reduce the county’s required number of mowings from five times a year to just once, and to increase the maximum allowed plant height from 13 inches to 36 inches.

Because variances legally expire if a project is not established within one year, the developer had to seek extensions.

Land Use Planner Marguerite Kenny explained that the developer was unable to plant the specialized native seed mix last year because the land was still actively being farmed.

“What happened was last spring the farmer planted the field before the solar facility can go in and establish a ground cover section,” Kenny said.

Because the applicant could not plant the section of the field to establish the native pollinators before the previous extension expired on March 30, 2026, they applied for their second and final 180-day extension, as permitted by the Will County Zoning Ordinance.

The commission held separate votes for each variance extension (#VEXT-26-001 and #VEXT-26-002), unanimously approving both. The extensions are now valid through September 26, 2026, giving the developer the spring and summer seasons to establish the native plantings as their building permits finalize.

⚠️ Special Weather Statement issued June 11 at 2:46PM CDT by NWS Chicago IL
⚠️ Tornado Watch issued June 11 at 2:02PM CDT until June 11 at 9:00PM CDT by NWS Chicago IL
⚠️ Flood Watch issued June 11 at 12:39PM CDT until June 11 at 11:00PM CDT by NWS Chicago IL
Today Jun 10
Chance Showers And Thunderstorms
84° 58°

Chance Showers And Thunderstorms

💨 15 to 20 mph 💧 43%

Leave a Comment





Latest News Stories

Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...
Screenshot 2026-02-22 at 5.06.42 PM

Board Approves New Chief of Staff and Dean Roles; Trustees Clash Over Hiring Transparency

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board approved the appointments of a new Chief of Staff and a Dean of Workforce...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
Screenshot 2026-02-22 at 4.29.56 PM

Board Approves $479,000 Wireless Network Overhaul to Replace Aging Tech

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board of Education approved a $479,526.96 contract with CDW to replace the indoor wireless access points...
mokena school district 159.3

Principals Present Mid-Year Data Showing Gains in Writing and Math Proficiency

Mokena School District 159 Meeting | February 18, 2026 Article Summary: Mokena School District 159 principals presented mid-year updates on their School Improvement Plans, highlighting data-driven gains in writing proficiency and...
Committee-Executive.Graphic

Executive Committee: Tension Rises as Republican Whip Removed from Panel

Will County Executive Committee Meeting | February 11, 2026 Article Summary: A dispute over committee appointments erupted when Republican leadership challenged the removal of Member Vince Logan from the Executive...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: County Stripped of Power to Regulate Motor Races, Must Drop Solicitor Fees Due to State Statutes

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee repealed county regulations regarding motor stunt events and removed...

Commission Overrides Staff Recommendation, Approves Manhattan Township Barn Expansion

Will County Planning and Zoning Commission Meeting | February 17, 2026 Article Summary: A Manhattan Township homeowner received unanimous approval for three variances to expand a pole barn, despite county...
Committee-Executive.Graphic

Executive Committee Advances “Project Northwinds”: 2,475 Jobs and $346 Million Investment Proposed for Former Caterpillar, Lion Electric Sites

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Will County Board Executive Committee moved forward a resolution supporting a massive manufacturing project that promises nearly 2,500...
Committee-Land Use.Graphic

Land Use Committee Advances Mokena Scrap Yard and Homer Glen Landscape Business Over Local Objections

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use Committee approved special use permits for two businesses in Frankfort and...
Screenshot 2026-02-22 at 4.29.56 PM

District 210 Reports Insurance Deficit Amid National Healthcare Cost Spikes; Finances Remain Stable

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: Assistant Superintendent Michael Duback reported a $630,000 deficit in the District’s medical plan performance for the 2025...
solar panels photovoltaics in solar farm

Planning Commission Backs 5-MW Peotone Solar Farm; Developer Pledges Pollinator Habitat and Community Funds

Will County Planning and Zoning Commission Meeting | February 17, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously recommended approval for a new 5-megawatt commercial solar farm...
mokena school district 159.5

Mokena 159 Moves Forward with Over $1 Million in Summer Capital Project Plans

Mokena School District 159 Meeting | February 18, 2026 Article Summary: The Mokena School District 159 Board of Education authorized the administration to seek bids for major summer facility improvements, including...
Screenshot 2026-02-22 at 5.06.42 PM

Joliet Junior College Board Approves $2 Tuition Increase Amidst Heated Debate Over Enrollment and Spending

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The Joliet Junior College (JJC) Board of Trustees on Wednesday voted to increase tuition by $2 per...
Screenshot 2026-02-22 at 4.29.56 PM

Lincoln-Way Board Ratifies Three-Year Support Staff Contract with Significant Hourly Raises

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Lincoln-Way Community High School District 210 Board of Education ratified a new three-year collective bargaining agreement...