Will County P&Z Commission Grants Extensions for Joliet Township Solar Farm Ground Cover

Spread the love

Will County Planning and Zoning Commission Meeting | April 7, 2026

Article Summary: The Will County Planning and Zoning Commission unanimously granted a final deadline extension for a commercial solar developer in Joliet Township, giving the company until September 2026 to plant specialized native pollinator ground cover beneath its solar arrays.

Joliet Solar Farm Key Points:

  • Nexamp Solar, operating as Moon Shoal Renewables and Summer Stone Renewables, requested Variance Extensions #VEXT-26-001 and #VEXT-26-002.

  • The extensions apply to previously approved variances that reduced required mowing from five times a year to one time, and increased maximum plant height from 13 inches to 36 inches.

  • The extensions were necessary because the property’s farmer planted traditional crops last season, preventing the solar developer from seeding the required native pollinators before the original variance expired.

On Tuesday, April 7, 2026, the Will County Planning and Zoning Commission granted a final round of variance extensions to Nexamp Solar, ensuring the developer has the legal runway to establish native pollinator habitats at its forthcoming commercial solar facilities in Joliet Township.

The developer is currently permitting two 5-megawatt commercial solar facilities, operating under the names Moon Shoal Renewables LLC and Summer Stone Renewables LLC. The projects are located near 2618 S. Chicago Street and W. Schweitzer Road, just west of the Chicagoland Speedway.

In October 2024, the commission approved special use permits for the facilities alongside specific variances regarding ground cover. To participate in the Illinois Pollinator-Friendly Solar Site Act and create deep-rooted habitats that manage stormwater, the developer required variances to reduce the county’s required number of mowings from five times a year to just once, and to increase the maximum allowed plant height from 13 inches to 36 inches.

Because variances legally expire if a project is not established within one year, the developer had to seek extensions.

Land Use Planner Marguerite Kenny explained that the developer was unable to plant the specialized native seed mix last year because the land was still actively being farmed.

“What happened was last spring the farmer planted the field before the solar facility can go in and establish a ground cover section,” Kenny said.

Because the applicant could not plant the section of the field to establish the native pollinators before the previous extension expired on March 30, 2026, they applied for their second and final 180-day extension, as permitted by the Will County Zoning Ordinance.

The commission held separate votes for each variance extension (#VEXT-26-001 and #VEXT-26-002), unanimously approving both. The extensions are now valid through September 26, 2026, giving the developer the spring and summer seasons to establish the native plantings as their building permits finalize.

Thu Jun 11
Sunny
79° 60°

Sunny

đŸ’¨ 10 to 15 mph đŸ’§ 0%

Leave a Comment





Latest News Stories

Screenshot 2025-10-25 at 10.49.32 AM

Crete Township ‘Tiny Home’ Owner Appeals Permit Denial

Will County Planning and Zoning Commission Meeting | October 21, 2025 Article Summary: A Crete Township property owner has appealed to the Will County Planning and Zoning Commission after being...
Will County Finance Logo

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board

Will County Finance Committee Forwards 1.75% Compromise Property Tax Levy to Full Board Article Summary:The Will County Board’s Finance Committee on Tuesday, November 12, 2025, narrowly approved a series of...
mokena school district 159.1

Board Approves $190,000 Transfer from Working Cash Fund Amid Dissent

Mokena School District 159 Meeting | November 19, 2025 Article Summary: The Mokena School District 159 Board of Education approved a resolution to abate $190,000 from its working cash fund...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Mokena Logo Graphic.6

Mokena Board Approves 2025 Tax Levy; Municipal Rate Set to Decrease

Mokena Village Board Meeting | November 24, 2025 Article Summary: The Mokena Village Board on Monday, Nov. 24, 2025, approved a $2.3 million property tax levy for the 2025 taxing...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
mokena fire district #2 logo graphic.5

Mokena Fire District Secures $160,000 in Grants to Replace Hoses and Nozzles

Mokena Fire Protection District Meeting | October 14, 2025 Article Summary: The Mokena Fire Protection District has successfully secured approximately $160,000 in grant funding, nearly covering the entire cost to...
solar panels photovoltaics in solar farm

New Lenox to Host Large Pollinator-Friendly Solar Farm

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a commercial solar energy facility spanning approximately 63 acres in...
Meeting Briefs

Meeting Summary and Briefs: Mokena Village Board for November 10, 2025

Mokena Village Board Meeting | November 10, 2025 The Mokena Village Board met on Monday, Nov. 10, 2025, to address rising administrative costs and celebrate local philanthropy. The most significant...
joliet junior college logo

JJC Receives Clean Audit, Reports $21.6 Million Increase in Net Position

Joliet Junior College Meeting | November 12, 2025 Article Summary:Joliet Junior College received a "clean unmodified audit opinion" for the fiscal year ending June 30, 2025, the highest level of...
will county board graphic

Will County Board Passes 0% Tax Levy, Creating “Unbalanced” Budget Crisis

Will County Board Meeting | November 2025 Article Summary: In a contentious fiscal showdown, the Will County Board voted to keep the corporate property tax levy flat, rejecting a proposed...
Poll: Majority of Americans still support legal immigration

Poll: Majority of Americans still support legal immigration

By Andrew RiceThe Center Square A majority of Americans say that legal immigration is good for the United States, according to a new poll commissioned by The Center Square. The...