solar panels photovoltaics in solar farm

Will County Executive Committee Recommends 600 MW Pride of the Prairie Solar Project in 6-5 Split Vote

Spread the love

Will County Board Executive Committee Meeting | May 14, 2026

Article Summary: The Will County Board Executive Committee on Thursday, May 14, 2026, voted 6-5 to recommend approval of a special use permit for the Pride of the Prairie commercial solar energy facility, a 6,099-acre, 600-megawatt project spanning Manhattan, Green Garden and Wilton townships, despite a 1-4 denial recommendation from the county’s Planning and Zoning Commission two nights earlier and lengthy opposition from residents, township officials and an attorney representing adjoining property owners.

Pride of the Prairie Solar Project Key Points:

  • The committee rejected a motion to postpone the vote until the application is deemed complete; that motion, made by Trustee Dan Butler and seconded by Dave Oxley, failed on a roll call.
  • The recommended ordinance, ORD 26-109 / ZC-25-129, attaches six conditions to the special use permit, including a requirement that the applicant negotiate and execute a road use agreement with each affected township road district and post surety bonds before construction.
  • According to the staff report, the concept site plan calls for 16,921 panels comprising roughly 1.19 million modules across 96 parcels, with a 35-year anticipated operating life that could extend to 50 years if all lease options are exercised.
  • The full Will County Board is scheduled to take final action at its meeting on Wednesday, May 21, 2026.

WILL COUNTY — The Will County Board Executive Committee on Thursday, May 14, 2026, voted 6-5 to recommend approval of the Pride of the Prairie commercial solar energy facility, sending the proposal to the full County Board over the objections of three affected townships, dozens of residents and the county’s own Planning and Zoning Commission, which voted 1-4 two days earlier to deny the special use permit.

The project, formally filed as ZC-25-129 / S-25-056 by Lincoln Solar Energy, LLC, would site a 600-megawatt facility across approximately 6,099 acres south of West Stuenkel Road, west of South 104th Avenue, east of South Gougar Road and north of West Wilmington-Peotone Road. According to the Will County Land Use Department staff report dated March 23, 2026, the applicant, Earthrise Energy PBLLC, has entered into lease agreements with 46 property owners covering 96 separate parcel identification numbers. The project’s concept site plan identifies 16,921 panels and 1,190,868 modules and proposes connection to the existing grid through the natural gas peaker plant operated by affiliates Earthrise Lincoln Interconnection LLC and Lincoln Generating Facility, LLC.

Public Comment Dominated by Opposition

More than a dozen residents and officials spoke against the project during public comment, with concerns ranging from steel-pile corrosion in hydric soils to property-value loss to inadequate identification of wetlands. Steven Becker, an attorney representing multiple clients with property adjoining the proposed footprint, asked the committee to preserve legal objections on the record, arguing the project violates due process and equal protection provisions of the state and federal constitutions and is preempted by federal farmland-preservation policy. Becker said the project’s LESA score of 236 placed the site in the “essential farmland” category, and he raised concerns about an estimated 300,000 galvanized steel posts being driven into hydric soils, which he said could leach zinc into the groundwater and the headwaters of Prairie, Forked and Hickory creeks.

Judy Mitchell, a Manhattan resident, read a statement on behalf of the Manhattan Township Board renewing its request that the County Board postpone the vote until state legislators have an opportunity to advance corrective legislation restoring local control under Senate Bill 25. Dean Christofilos, the Green Garden Township supervisor, told the committee the official reason his township opposes the project is that it is “not in compliance with our comprehensive land use map for solar facilities.”

Eileen Fitzer, a 76-year-old Manhattan widow, said she had lived on her property for more than 20 years and asked the board to “slow this down, halt, or delay approval of this project until further research is done and clear local protections are in place.” Jim Baltus, identified as the Manhattan Township road commissioner, told the committee the applicant had driven heavy equipment and pounded survey stakes on township roads posted at 12-ton limits without a road use agreement, and then removed the stakes without notice.

Representing the applicant during public comment, Earthrise Director of Development Robert Kalbouss said the application was complete and had been deemed so by the Land Use Department. “We delineated wetlands. We went above and beyond the requirements to delineate wetlands,” Kalbouss said. Benjamin Jacobi of Polsinelli, the project’s attorney, told the committee that a Will County circuit judge had dissolved a temporary restraining order in the case earlier that morning, removing what he called a “legal hurdle” that had required additional cross-examination at a continued planning commission hearing on May 12.

Cross-Examination, Conditions and the Postponement Motion

Will County Land Use Department planner Margarite Kenny told the committee the May 12 Planning and Zoning Commission session, ordered by the court, included a roughly three-hour cross-examination between Becker and Jacobi focused on the completeness of the application, wetlands and floodplain studies, solar materials and equipment, and lease agreements. The commission voted 5-0 to amend conditions 3, 5 and 6 to match language approved on April 23, 2026, for the Plum Valley solar project (ZC-25-139), then voted 1-4 to deny the underlying special use permit with all six conditions in place.

Condition 3 allows above-ground on-site power lines and utility connections to avoid pipelines and wetland areas and authorizes the applicant to use the CAB above-ground cabling system between panels as described at hearing. Condition 5 specifies that fire lanes and access roads shall be gravel per the request of the fire departments, with such lanes considered pervious under the Will County Code. Condition 6 requires the applicant to negotiate and execute a road use agreement with each affected township road district and post district surety bonds before commencement of construction or issuance of a site development permit.

Butler made an extended motion to postpone, citing five examples he said showed the application was incomplete under Will County Code section 155-9.245, including the absence of a stated number of arrays or racks, an incomplete identification of farmed wetlands and federally protected waters, and the lack of an updated consultation with the Illinois Department of Natural Resources regarding the short-eared owl, listed as endangered in Illinois. “I made a motion to postpone until all these obligations have been met,” Butler said. Oxley seconded.

An assistant state’s attorney advised the committee that the Land Use Department’s professional opinion controlled the completeness determination, citing the third district appellate court’s decision in Equity Solar Illinois v. County of Grundy, 2026 IL App (3d) 250289, which he said established that county discretion in commercial solar siting decisions is “minimized on the front end and limited on the back end of the process.” Kenny told the committee her professional opinion was that the application met county standards. The postponement motion failed on a roll call.

The Approval Vote

On the underlying motion to recommend approval, the executive committee voted 6-5. Members Butler and Frankie Pretzel both said they would oppose the recommendation, with Pretzel arguing the project’s scale was the central problem. “This board has approved 10 solar projects for every one that we’ve voted no on,” Pretzel said. “But lumped together, we’ve got 96 parcels, 300,000 posts.” Kelly Hickey, who voted to recommend approval, said that while she shared the concerns raised by residents, the state legislative framework left the county little discretion. “No matter how this committee votes today, no matter how the board votes on the 21st, there will be a solar field in this place,” Hickey said.

Republican Leader Jim Richmond and several other members questioned the long-term consequences. “I’m a young man,” Richmond said. “In the 80s, there was discussion of super funds. I’m gonna put my Nostradamus hat on right now, and I’m going to predict that in 2040, the super funds will be cleaning up these messes.”

The project must comply with Illinois Public Law 102-1123 and 55 ILCS 5/5-12020, which the staff report described as requiring counties to hear commercial solar siting requests within 60 days of a complete application and decide them within 30 days of the close of the public hearing. The applicant has signed an Agricultural Impact Mitigation Agreement with the Illinois Department of Agriculture dated September 26, 2025, and is required to provide financial assurance for deconstruction under that agreement. A drain tile map and conservation plan developed with the Will-South Cook Soil and Water Conservation District will be required at the site development permitting stage.

Today Jun 13
Chance Rain Showers then Mostly Cloudy
71° 51°

Chance Rain Showers then Mostly Cloudy

💨 10 to 20 mph 💧 45%

Leave a Comment





Latest News Stories

Screenshot 2025-10-25 at 12.42.59 PM

Will County Committee Grapples with $8.9 Million Budget Gap After Contentious 0% Tax Levy Vote

Will County Board Finance Committee Meeting | October 21, 2025 Article Summary: The Will County Board Finance Committee held a contentious debate over how to close an $8.9 million budget shortfall...

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 for October 16, 2025

Meeting Briefs

Meeting Summary and Briefs: Mokena School District 159 Board of Education for October 15, 2025

Mokena School District 159 Board of Education Meeting | October 15, 2025 The Mokena School District 159 Board of Education's October 15, 2025, meeting was marked by several contentious votes...
Meeting-Briefs

Meeting Summary and Briefs: Frankfort Township Board for September 8, 2025

Frankfort Township Board | September 8, 2025 During its meeting on Monday, September 8, 2025, the Frankfort Township Board unanimously denied a special use permit for a new bar proposed...
Screenshot 2025-10-17 at 11.24.23 AM

Lincoln-Way to Purchase New Buses, Add Smaller Vehicles to Address Driver Shortage

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 plans to update its transportation fleet by purchasing 28 new gasoline-powered school buses, three activity buses,...
mokena school district 159.4

Mokena 159 Board Adopts New Policies on AI, Student Support Despite Dissent

Mokena School District 159 Board of Education Meeting | October 15, 2025 Article Summary: The Mokena School District 159 Board of Education adopted a series of policy updates addressing topics from...
Screenshot 2025-10-17 at 11.31.38 AM

Lincoln-Way Board Honors Students with Perfect ACT Scores, Music Educator of the Year

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 celebrated exceptional academic and faculty achievement by formally recognizing nine students who earned a perfect composite...
frankfort township graphic

Frankfort Township Board Denies Permit for New Bar on St. Francis Road

Frankfort Township Board | September 8, 2025 Article Summary: The Frankfort Township Board on Monday unanimously denied a special use permit required for a new bar to open at 7663...
mokena school district 159.1

Mokena 159 Receives Clean Audit Report, Earns State’s Highest Financial Recognition

Mokena School District 159 Board of Education Meeting | October 15, 2025 Article Summary: Mokena School District 159 has received the State of Illinois' highest financial rating after an independent audit...
Meeting-Briefs

Meeting Summary and Briefs: Mokena Village Board for September 22, 2025

Mokena Village Board Meeting | September 22, 2025 The Mokena Village Board on Monday, September 22, 2025, took steps to bolster downtown redevelopment by unanimously approving a three-year extension of...
Screenshot 2025-10-17 at 11.32.04 AM

Lincoln-Way Support Staff Union Rejects Tentative Contract Agreement

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Members of the Lincoln-Way Community High School District 210 support staff union have voted down a tentative five-year contract...
Mokena Logo Graphic.6

Mokena to Replace Invasive Callery Pear Trees with Grant Funding

Mokena Village Board Meeting | September 22, 2025 Article Summary: Mokena will remove invasive Callery Pear trees throughout the village and plant new, non-invasive species, thanks to a matching grant from...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
mokena school district 159.2

Mokena School Board Approves Pacts with Unions to Address Bus Driver Shortage

Mokena School District 159 Board of Education Meeting | October 15, 2025 Article Summary: Mokena School District 159 will offer paid CDL training and stipends to teachers and staff who volunteer...
Mokena Logo Graphic.3

Mokena Hikes Business License Late Fees to $30

Mokena Village Board Meeting | September 22, 2025 Article Summary: The Mokena Village Board has approved an ordinance that significantly increases the penalty for late renewal of business licenses from a...