Watchdog: Canceled NASA contracts more than doubled in cost

Watchdog: Canceled NASA contracts more than doubled in cost

Spread the love

A new federal watchdog report found contract values on canceled Artemis systems more than doubled, to $5.9 billion, and NASA still hasn’t disclosed what its Moon-to-Mars program will cost.

NASA Administrator Jared Isaacman and Moon Base program manager Carlos García-Galán will hold a virtual briefing at 2:30 p.m. EDT June 30 to discuss the next round of lunar lander mission awards and preview upcoming contracting opportunities.

The briefing comes as the NASA Office of Inspector General reported Wednesday that four Artemis systems NASA canceled or repurposed earlier this year saw their combined contract values grow from $2.8 billion to $5.9 billion. The watchdog projected costs would have climbed even higher had work continued.

NASA has not provided a total cost estimate for its Moon-to-Mars program. At a March briefing, Administrator Jared Isaacman said NASA would invest approximately $20 billion over seven years to build the moon base, but did not provide a total cost for the broader program when reporters asked about funding.

The watchdog projected the Boeing-built Exploration Upper Stage alone would have cost $3.7 billion if completed, nearly four times its original $962 million contract value and about 7.5 years behind schedule.

NASA’s acting inspector general testified before Congress in January 2024 that the Artemis program alone was projected to exceed $93 billion through 2025. The inspector general also projected the SLS/Orion system would cost at least $4.2 billion per launch for the program’s first four missions, not including $42 billion in formulation and development costs.

The Government Accountability Office has designated NASA acquisition management a high-risk area for more than 30 years.

The agency faces budget uncertainty. The White House proposed cutting NASA from $24.4 billion to $18.8 billion, a 23% reduction, while the House has advanced legislation keeping funding flat.

U.S. Rep. Brian Babin, R-Texas, chairman of the House Science, Space and Technology Committee, said the White House proposal could not support President Donald Trump’s own exploration goals.

A NASA spokesperson said the agency was unlikely to meet a request for comment before publication on the total cost of its Moon-to-Mars program or when such an estimate would be available.

NASA officials said in March that canceled Gateway hardware would be repurposed for the Moon Base, but the inspector general reported Wednesday that NASA has yet to decide whether or how to use it.

Leave a Comment





Latest News Stories

Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Mokena Park District.logo.graphic.1

Mokena Park District Approves $550,000 Fund Transfer for Major Park Projects

The Mokena Community Park District Board of Commissioners has approved a $550,000 fund transfer to complete several key capital projects, including the construction of a new bathroom facility at Hecht...
LWSRA

Mokena Park District Joins Regional Partners in Renewed Funding Commitment for LWSRA

The Mokena Community Park District is renewing its financial commitment to the Lincolnway Special Recreation Association (LWSRA), joining eight other local park districts in an intergovernmental agreement that ensures continued...
mokena park Yunker Barn

Mokena Park District Seeks Nearly $1 Million State Grant for Yunker Barn Renovation

The Mokena Park District is seeking nearly $1 million in state funding to help transform the historic Yunker Park Barn into a year-round facility. Executive Director Greg Vitale announced at...
Meeting-Briefs

Meeting Briefs: Mokena Park District Board of Commissioners for June 27, 2023

The Mokena Park District Board of Commissioners met on June 27 to approve funding for capital projects, renew a regional partnership agreement, and review staff reports on recent and upcoming...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
mokena library logo graphic.4

Library Board Approves Annual Budget, Begins Review of Financial Advisor Proposals

The Library Board of Trustees unanimously approved its working budget for the new fiscal year at its June 24 meeting and formally began the process of selecting a financial advisor...
Screenshot-2025-07-06-at-9.50.39-AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot-2025-07-06-at-9.45.35-AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...