Watchdog: Canceled NASA contracts more than doubled in cost

Watchdog: Canceled NASA contracts more than doubled in cost

Spread the love

A new federal watchdog report found contract values on canceled Artemis systems more than doubled, to $5.9 billion, and NASA still hasn’t disclosed what its Moon-to-Mars program will cost.

NASA Administrator Jared Isaacman and Moon Base program manager Carlos García-Galán will hold a virtual briefing at 2:30 p.m. EDT June 30 to discuss the next round of lunar lander mission awards and preview upcoming contracting opportunities.

The briefing comes as the NASA Office of Inspector General reported Wednesday that four Artemis systems NASA canceled or repurposed earlier this year saw their combined contract values grow from $2.8 billion to $5.9 billion. The watchdog projected costs would have climbed even higher had work continued.

NASA has not provided a total cost estimate for its Moon-to-Mars program. At a March briefing, Administrator Jared Isaacman said NASA would invest approximately $20 billion over seven years to build the moon base, but did not provide a total cost for the broader program when reporters asked about funding.

The watchdog projected the Boeing-built Exploration Upper Stage alone would have cost $3.7 billion if completed, nearly four times its original $962 million contract value and about 7.5 years behind schedule.

NASA’s acting inspector general testified before Congress in January 2024 that the Artemis program alone was projected to exceed $93 billion through 2025. The inspector general also projected the SLS/Orion system would cost at least $4.2 billion per launch for the program’s first four missions, not including $42 billion in formulation and development costs.

The Government Accountability Office has designated NASA acquisition management a high-risk area for more than 30 years.

The agency faces budget uncertainty. The White House proposed cutting NASA from $24.4 billion to $18.8 billion, a 23% reduction, while the House has advanced legislation keeping funding flat.

U.S. Rep. Brian Babin, R-Texas, chairman of the House Science, Space and Technology Committee, said the White House proposal could not support President Donald Trump’s own exploration goals.

A NASA spokesperson said the agency was unlikely to meet a request for comment before publication on the total cost of its Moon-to-Mars program or when such an estimate would be available.

NASA officials said in March that canceled Gateway hardware would be repurposed for the Moon Base, but the inspector general reported Wednesday that NASA has yet to decide whether or how to use it.

⚠️ Heat Advisory issued June 28 at 2:47AM CDT until July 1 at 10:00PM CDT by NWS Chicago IL
Today Jun 27
Partly Sunny then Chance Showers And Thunderstorms
84° 75°

Partly Sunny then Chance Showers And Thunderstorms

💨 5 to 15 mph 💧 27%

Leave a Comment





Latest News Stories

Will County Board Graphic.02

Ad-Hoc Committee: Will County Sheriff’s Office to Acquire Decibel Meters for Noise Complaints

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: The Will County Sheriff's Office plans to purchase a fleet of certified decibel meters to accurately...
Will County Public Works Committee

Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday approved a request to allow commercial ingress...
Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...
will county Committee-Legislative.Graphic

Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts

Legislative Committee Meeting | March 2026 Article Summary: The Will County Legislative Committee unanimously approved a resolution supporting a state legislative push to increase the Local Health Protection Grant by $10...