'Ghost projects' haunt power grid planners and taxpayers

‘Ghost projects’ haunt power grid planners and taxpayers

Spread the love

(The Center Square) – As the country braces for a surge in electricity demand driven by large energy users like data centers, two questions lie at the center of the debate over the grid’s future: can it remain reliable and who will pay for it?

Utility experts warn that rising load forecasts are colliding with projected supply shortfalls. And, while PJM works to finalize new rules for connecting large load customers to the grid, some state officials, consumer advocates, and industry groups are zeroing in on the affordability piece of the puzzle.

Accurate load forecasting is essential in meeting rising demand without wasting capital on infrastructure that may never be used, and it affects everything – from keeping the lights on to the prices customers pay each month.

“Ghost projects” are a big part of the issues that are creating uncertainty, Todd Snitchler, president and CEO of the Electric Power Supply Association, or EPSA, told The Center Square.

A ghost project is a generation or transmission project that is announced or funded but never gets built.

Snitchler said gigawatts of new demand are being reported to the system, but there are duplications. Data center developers and hyperscalers routinely scout multiple locations at once, so the same potential project gets counted several times, artificially inflating the load forecast – leading to the risk of overbuilding, stranded costs, or unnecessary spending.

According to Snitchler, there are utilities pointing to these numbers to justify getting back into the business of rate-based generation, claiming they can deliver new plants faster and more cheaply, and with no impact on customers.

None of this can be true, he added, “because they’re subject to the same pressures we are as independent power producers.” And under their business model, they recover their costs plus a reasonable rate of return through a non-bypassable charge paid by customers.

Some states, he said, are tightening their tariffs to include only credible, large-load projects in forecasts. When AEP Ohio applied its new tariff, its projected growth over five years dropped from 30 GW to 13 GW – a 60% reduction. The former is equivalent to powering 26 million homes, while the latter is enough for 1.1 million.

“That suggests to me,” he said, “they can’t be alone in experiencing that.”

He noted that the load forecast for most Pennsylvania utilities was surprisingly flat, with others having only 1-1.5% annual growth, while PPL’s amounted to a 200% increase over 10 years. Something he says is wildly out of step with their peer utilities and raises questions about how thoroughly they are vetting projects, and how many are real.

He argued that overstated demand forecasts suggest developers need to build like crazy, justifying the utilities’ preference to get back into the rate-based generation business – and forcing customers to pay for new power plants instead of relying on the competitive market.

In these cases, Snitchler questions whether the projects are real, or simply advocacy tools designed to help publicly traded utilities grow their rate base and boost shareholder returns, as opposed to competitive developers who invest their own capital and bear the risk themselves.

His concern is that in addition to not having the best answer, there’s an incentive to have the wrong answer, because that helps advance policy objectives that may be better for some organizations, but are intentionally harmful to others.

The bottom line, EPSA says, is that realistic, data-driven planning ensures reliability for the 67 million customers in the PJM region. The solution to meeting demand is continued investment through competitive electricity markets in new and existing power generation, guided by disciplined, transparent forecasting that reflects the projects most likely to materialize.

“There is no silver bullet for this – and I’m not even convinced there’s silver buckshot. Because there’s so much happening that needs coordination for us to deliver and do our best, to ensure a reliable, affordable, and growing system,” Snitchler said. “I think everyone is aiming in the right direction, and we’d do a little better if we bickered less and cooperated more. But it doesn’t feel like where we are at the moment.”

“PJM is doing everything within our authority to reform our processes so they reflect load growth that is likely to occur, not just speculative activity,” Jeffrey Shields, PJM spokesperson, told The Center Square via email.

He said the potential for duplicative requests is one issue they are addressing with their stakeholders in the Critical Information Fast Path process for Large Load Additions, which will conclude on Nov. 19 with a recommendation to the PJM Board of Managers. The CIFP process was initiated by the Board in August to explore ways to continue to connect large loads to the system quickly and reliably without risking electricity shortages.

As part of the CIFP discussions, they are recommending several improvements to the load forecasting process, building on existing enhancements that incorporate large load adjustments into the long-term forecast. They have also standardized the system that load-serving entities use to request large load additions, to include evidence of binding commitments that facilities will be built.

PJM has also recommended a specific review process involving the states and utilities that operate within their borders; those states and their utilities also have authority to set rates and require commitments from data centers and other “large load” customers.

A summary of their proposal to deal with the issue will be considered along with 11 others.

Leave a Comment





Latest News Stories

WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting-Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Mokena Logo Graphic.5

Mokena Overhauls Zoning Code to Streamline Rules for Sheds, Pools, and Patios

The Mokena Village Board has unanimously approved a significant overhaul of its zoning regulations for accessory structures, a move aimed at making rules for items like sheds, decks, and pools...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Mokena Logo Graphic.6

Mokena Awards $472K Contract for Countryview Estates Storm Sewer Project

The Village of Mokena is moving forward with a major infrastructure project, awarding a contract worth over $472,000 to a local company for the Countryview Estates Storm Sewer Replacement Project....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Champaign-based Pavlov

Fiber Internet Provider Pavlov Media Details Plans to Expand into Mokena

Mokena residents may soon have another choice for high-speed internet service, as Champaign-based Pavlov Media has announced its intent to build a fiber optic network throughout the village. Mark Sheldon,...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Mokena Logo Graphic.1

Mokena Celebrates Successful July 4th Events, Honors Parade Winners

A celebratory atmosphere filled the Mokena Village Board meeting on July 14, as officials and community leaders recounted the success of the village's Independence Day festivities and honored the winners...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for July 14, 2025

The Mokena Village Board on July 14 approved a major overhaul of its zoning code, awarded a contract for a significant storm sewer project, and heard plans for a new...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...