Commission Grants Green Garden Solar Farm Project Variance Extension

Spread the love

Will County Planning and Zoning Commission Meeting | November 4, 2025

Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial solar energy facility in Green Garden Township, allowing the developer to wait for optimal planting conditions in Spring 2026 before proceeding. The variances, originally approved in March, concern the mowing schedule and plant height for the native pollinator habitat required for the project.

Green Garden Solar Farm Key Points:

  • The first-time extension was granted for variances associated with a 35-acre solar project on LaGrange Road near West Manhattan-Monee Road.

  • The variances reduce the required number of mowings from five to one per year and increase the maximum allowed ground cover height from 13 to 36 inches.

  • The developer requested the extension to allow time to prepare the site for planting a native pollinator seed mix in favorable spring conditions.

A commercial solar energy facility planned for Green Garden Township received a procedural timeline extension from the Will County Planning and Zoning Commission on Tuesday, November 4, 2025.

The commission approved a 180-day extension for two variances previously granted to applicant TPE IL WI258, LLC, an affiliate of TPE Development, LLC, for a 35-acre solar farm. The project is located on vacant property at the northeast corner of LaGrange Road and West Manhattan-Monee Road in Monee.

The variances, originally approved by the commission on March 4, 2025, are key to the project’s use of native plantings and agrivoltaics—the simultaneous use of land for agriculture and solar power generation. One variance reduces the required number of mowings from five times per year to just one, while the other increases the maximum allowable plant height from 13 inches to 36 inches. These changes are necessary to establish and maintain a healthy native pollinator habitat on the site, which is a requirement of the state’s community solar program.

According to a memo from county staff, the developer has not yet applied for a building permit because “favorable planting conditions for the site are not expected until after the variances expire on March 4, 2026.” The extension was requested to allow the developer time to prepare the site for planting in the spring of 2026.

The commission, which is authorized to grant up to two 180-day extensions for good cause, approved the request. The variances will now expire on August 31, 2026.

Events

No events

Leave a Comment





Latest News Stories

Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Mokena Logo Graphic.6

Mokena Awards $472K Contract for Countryview Estates Storm Sewer Project

The Village of Mokena is moving forward with a major infrastructure project, awarding a contract worth over $472,000 to a local company for the Countryview Estates Storm Sewer Replacement Project....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Champaign-based Pavlov

Fiber Internet Provider Pavlov Media Details Plans to Expand into Mokena

Mokena residents may soon have another choice for high-speed internet service, as Champaign-based Pavlov Media has announced its intent to build a fiber optic network throughout the village. Mark Sheldon,...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Mokena Logo Graphic.1

Mokena Celebrates Successful July 4th Events, Honors Parade Winners

A celebratory atmosphere filled the Mokena Village Board meeting on July 14, as officials and community leaders recounted the success of the village's Independence Day festivities and honored the winners...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Meeting-Briefs

Meeting Briefs: Mokena Village Board for July 14, 2025

The Mokena Village Board on July 14 approved a major overhaul of its zoning code, awarded a contract for a significant storm sewer project, and heard plans for a new...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO-Exec-Cmte-July-10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting-Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
frankfort-park-district

Meeting Briefs: Frankfort Park District Board for June 10, 2025

The Frankfort Park District Board of Commissioners discussed a legal dispute with the Five Oaks homeowners association over park development rules at its Tuesday meeting. Executive Director Gina Hassett reported...
Will-County-Land-Use-July-3.1

Committee Rejects Troy Township Solar Projects Amid Strong Local Opposition

The Will County Land Use and Development Committee recommended denial for two controversial commercial solar energy projects in Troy Township on Thursday, following a wave of opposition from local municipalities,...
Will-County-Land-Use-July3.2

Controversial DuPage Township Rezoning for Outdoor Storage Advances

A contentious proposal to rezone a 20-acre parcel in DuPage Township from agricultural (A-1) to heavy industrial (I-3) for an outdoor vehicle storage facility narrowly passed the Will County Land...